Firstenergy Nuclear Operating Company Public Meeting Presentation Davis-Besse Nuclear Power Station
ML043420442
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 12/06/2004
From:
FirstEnergy Nuclear Operating Co
To:
Office of Nuclear Reactor Regulation
References
Download: ML043420442 (1)


Text

Davis-Besse Nuclear Power Station September 28, 2004 IMC 0350 Meeting IMC 0350 Meeting December 6, 2004 December 6, 2004

Davis-Besse Nuclear Power Station 2

December 6, 2004 Davis-Besse Nuclear Power Station Desired Outcomes Demonstrate Davis-Besses operations continue to be safe and conservative Status the improvement initiatives and Confirmatory Order Independent Assessments Mark Bezilla Vice President People with a People with a strong safety strong safety focus delivering focus delivering top fleet operating top fleet operating performance performance

Davis-Besse Nuclear Power Station 3

December 6, 2004 Davis-Besse Nuclear Power Station Meeting Agenda Plant Performance..Barry Allen Independent Assessments Operations Performance....Barry Allen Corrective Action Program Implementation.Bob Schrauder Safety Culture/SCWE..Mark Bezilla Backlog Reduction...Barry Allen Mid-Cycle Outage Preparations.....Barry Allen Oversight Perspective.....Ray Hruby

Davis-Besse Nuclear Power Station 4

December 6, 2004 Davis-Besse Nuclear Power Station Plant Performance Barry Allen Director - Site Operations

Davis-Besse Nuclear Power Station 5

December 6, 2004 Davis-Besse Nuclear Power Station People with a strong safety focus delivering top fleet operating performance Plant Status

- ~100% power

- ~ 925 Mwe

-121 continuous days of service

-60 Human Performance success days

Davis-Besse Nuclear Power Station 6

December 6, 2004 Davis-Besse Nuclear Power Station Noteworthy items

- September 16 - October 1 -

Confirmatory Order Independent Assessment - Corrective Action Program Implementation

- September 29 - NRC Inspection of SC/SCWE Cycle 14 OIP Items

- September 29 - Routine NRC Exit

- October 4 - NRC inspection of Service Water System Problems affecting Safety-Related equipment (GL 89-13)

- October 4 SCWE Survey Conducted

- October 5 NEIL Boiler and Machinery Evaluation

- October 5 Industry Representative Site Visit Plant Performance

Davis-Besse Nuclear Power Station 7

December 6, 2004 Davis-Besse Nuclear Power Station Noteworthy items (continued)

- October 6 NEIL conducted Annual Property Insurance Survey

- October 7 - NRC Region III Deputy Administrator site visit

- October 11 Confirmatory Order Independent Assessment -

Engineering Program Effectiveness

- October 11 Oversight personnel conducted annual safety culture/safety conscious work environment interviews

- October 15 - Successfully completed Emergency Plan Drill

- October 18 - Nuclear Oversight 3rd Quarter Continuous Assessment Exit Plant Performance NRC Region III Deputy Administrator Site Visit

Davis-Besse Nuclear Power Station 8

December 6, 2004 Davis-Besse Nuclear Power Station Plant Performance Noteworthy items (continued)

- October 20 - Conduct Monthly Performance Review

- October 21 - FirstEnergy General Staff Meeting in Akron

- October 25 - NRC inspection of ALARA, Access Control and NRC Performance Indicator

- October 25 - NRC inspection of Alert and Notification System Reliability

- October 25 & 26 - Conducted annual Safety Culture Assessment

- October 29 - Achieved compliance with the NRC Security Order FENOC President meets with Employees

Davis-Besse Nuclear Power Station 9

December 6, 2004 Davis-Besse Nuclear Power Station Noteworthy items (continued)

- November 1 NRC Security Baseline Inspection

- November 1 Confirmatory Order Independent Assessment - Safety Culture and Safety Conscious Work Environment (Information gathering)

- November 8 & 9 - National Board "VR" stamp renewal review

- November 12 - Mid-cycle outage readiness review

- November 14 Company Nuclear Review Board Plant Performance National Board Renewal Certification

Davis-Besse Nuclear Power Station 10 December 6, 2004 Davis-Besse Nuclear Power Station Noteworthy items (continued)

- November 14 & 15 - Industry Accreditation Team Manager Visit

- November 15 - Licensed Operator Requalification NRC Inspection

- November 16 - NRC (Region 1 & 3) /

FENOC Senior Management Meeting

- November 17 - Routine NRC Exit

- November 29 - NRC Problem Identification and Resolution Inspection

- December 1 & 2 - Industry Site Representatives Visit Plant Performance Mid-Cycle Outage Preparation

Davis-Besse Nuclear Power Station 11 December 6, 2004 Davis-Besse Nuclear Power Station 2005 Key Events Calendar

- January 17 - Mid-cycle outage commences

- January 17 NRC Mid-cycle ISI Special Inspection

- March 14 Industry Training Accreditation

- May 17 - Evaluated Emergency Preparedness Exercise

- August - Industry Plant, Corporate,

& Simulator Evaluation FENOC Vision FENOC Vision with a strong safety focus delivering top fleet operating performance with a strong safety focus delivering top fleet operating performance Beaver Valley

  • Davis-Besse
  • Perry
  • Akron
  • BETA Beaver Valley
  • Davis-Besse
  • Perry
  • Akron
  • BETA Plant Performance

Davis-Besse Nuclear Power Station 12 December 6, 2004 Davis-Besse Nuclear Power Station Conclusion Davis-Besses operations continue to be safe and conservative

Davis-Besse Nuclear Power Station 13 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Barry Allen Director - Site Operations

Davis-Besse Nuclear Power Station 14 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Confirmatory Order Action Plan 2004 Schedule Operations Performance (August)

Corrective Action Program Implementation (September)

Engineering Program Effectiveness (October)

- Organizational Safety Culture, including SCWE (November)

  • Completed

Davis-Besse Nuclear Power Station 15 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Operations Performance Work Management Interface

-Communicated process to Operations

-Scheduling Operations routine monthly activities

-Operators attending routine scheduling meetings Procedure Backlogs

-Reviewed for priority and significance

-Reduction plan developed and implemented

-Additional resources assigned

Davis-Besse Nuclear Power Station 16 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Operations Performance Corrective Action Program Backlog

-Reviewed for priority and significance

-Integrating with procedure effort Routine Tasks

-End of shift crew critiques

-Independent cross-crew SRO surveillance review

-Operations Management review

Davis-Besse Nuclear Power Station 17 December 6, 2004 Davis-Besse Nuclear Power Station Bob Schrauder Director - Performance Improvement Independent Assessments Corrective Action Program Implementation

Davis-Besse Nuclear Power Station 18 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Corrective Action Program Implementation Dates: September 13 - October 1, 2004 Assessment Team found the corrective action program at Davis-Besse to be marginally effective Areas reviewed:

- Identification, Classification and Categorization of Conditions Adverse to Quality

- Evaluation and Resolution of Problems

- Corrective Action Implementation and Effectiveness

- Effectiveness of Program Trending

- Effect of Program Backlogs

- Effectiveness of Internal Assessments Activities, and

- Corrective actions taken in response to the NRC Special Team Inspection -

Corrective Action Program Implementation (Report 05000346/2003010)

Davis-Besse Nuclear Power Station 19 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Corrective Action Program Implementation Area for Improvement

-Some Organizations were not initiating Condition Reports (CRs) as required Actions to Improve Performance

-Review and evaluate the CR threshold initiation criteria

-Issue expectations directive to communicate and reaffirm CR initiation criteria

-Perform self-assessment to evaluate the effectiveness of CR initiation

Davis-Besse Nuclear Power Station 20 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Corrective Action Program Implementation Area for Improvement

-Process for prioritizing, scheduling, and extending work does not consistently support the timely implementation of actions to fix long-standing problems Actions to Improve Performance

-Create and implement a comprehensive Integrated Backlog Reduction Plan

Davis-Besse Nuclear Power Station 21 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Corrective Action Program Implementation Area for Improvement

-Review of open Corrective Action implementation extensions classified as non-restart should be conducted to ensure appropriate compensatory actions are in place Actions to Improve Performance

-Review backlog of SCAQ & CAQ Root and Apparent Cause Preventive and Remedial corrective actions to consider interim actions or accelerated completion

-Update CREST to require evaluation for and documentation of the consideration of interim action extensions

-Issue an expectation directive to have SCAQ & CAQ Root and Apparent Cause extension requests evaluate and document whether interim actions are required

Davis-Besse Nuclear Power Station 22 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Corrective Action Program Implementation Area for Improvement

-Davis-Besse has not aggressively worked to correct Corrective Action Trending Program deficiencies identified in previous self-assessments or oversight findings Actions to Improve Performance

-Benchmark other sites

-Enhance the Quarterly trend report

-Improve guidance concerning timeliness for performing and completing Collective Significance Reviews

-Develop & implement a site wide equipment trending program

-Develop a FENOC common trending program

Davis-Besse Nuclear Power Station 23 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Corrective Action Program Implementation Area for Improvement

-Improvement is warranted in the documentation of organizational Collective Significance Self Assessments with respect to minimal procedure guidance, expectations, documentation, documentation of CRs and overall performance rating Actions to Improve Performance

- Revise governing Business Practice to clarify expectations relative to documentation of Collective Significant Self-Assessment Reports

- Establish expectations for format, documentation and overall rating

Davis-Besse Nuclear Power Station 24 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Corrective Action Program Implementation Area for Improvement

-The Self-Assessment Process does not provide a mechanism for identifying and correcting programmatic concerns or trends identified during the course of the assessment Actions to Improve Performance

-Revise governing Business Practice to clearly identify the need to consider the potential aggregate impact of programmatic concerns or trends

Davis-Besse Nuclear Power Station 25 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Corrective Action Program Implementation Area for Improvement

-Additional emphasis is warranted on timely correction of items identified by self-assessments and Nuclear Quality Assurance findings Actions to Improve Performance

-Benchmark how other nuclear sites prioritize CRs from self-assessment and NQA findings and revise the governing procedure

-Perform a sampling of current self-assessment - as necessary and NQA-initiated CRs to determine if Davis-Besse is completing those Corrective Actions at a comparable rate

Davis-Besse Nuclear Power Station 26 December 6, 2004 Davis-Besse Nuclear Power Station Independent Assessments Corrective Action Program Implementation Positive Observations

-Systematic approach to Training of CR analysts and CARB

-CARB is effective with good consensus among members

-Management is knowledgeable and involved

-Backlog is decreasing

-Independent Assessment reflects Davis-Besse self-assessments

Davis-Besse Nuclear Power Station 27 December 6, 2004 Davis-Besse Nuclear Power Station Mark Bezilla Vice President Safety Culture/

Safety Conscious Work Environment

Davis-Besse Nuclear Power Station 28 December 6, 2004 Davis-Besse Nuclear Power Station Safety Culture/ SCWE Activities September 29 - NRC Inspection of SC/SCWE Cycle 14 OIP Items October 4 Annual SCWE Survey conducted October 11 Oversight personnel conducted annual safety culture/safety conscious work environment focused interviews October 25 & 26 - Annual Safety Culture Assessment conducted November 1 Confirmatory Order Independent Assessment

- Safety Culture and Safety Conscious Work Environment (Information gathering)

Davis-Besse Nuclear Power Station 29 December 6, 2004 Davis-Besse Nuclear Power Station Safety Conscious Work Environment Survey Annual survey conducted October 4 - 9 Issue

-Some less positive results Actions

-Reviewed results (comments)

-Obtained external (Organizational Development Consultants) assistance

-Discussed results with site population

-Determining Drivers

-Will develop actions to address the Drivers

-Will compare to COIA SC/SCWE Report Results

Davis-Besse Nuclear Power Station 30 December 6, 2004 Davis-Besse Nuclear Power Station Independent Oversight 03 04

Safety Culture Safety Culture Individual Commitment Area Plant Management Commitment Area Policy or Corporate Level Commitment Area

03 03 03 04 04 04 Questioning Attitude Rigorous Work Control and Prudent Approach Open Communications Statement of Safety Policies Management Value Structure Resources Drive for Excellence Nuclear Professionalism 03 03 03 04 04 04 03 04 03 04 03 04 03 04 03 04 Self Assessment 03 04 Goals, Roles and Teamwork Ownership and Accountability Qualification and Training Commitment to Continuous Improvement Commitment to Safety Cross-Functional Work Management

& Communication 03 04 03 04 03 03 03 03 04 04 04 04 Environment of Engagement and Commitment 03 04 FENOC Safety Culture Model October 2004 Color Key All major areas are accept-able with a few minor indi-cator deviations All major areas are accept-able with several indica-tors requiring prompt man-agement action All major areas are accept-able with a few indicators requiring management at-tention Several major areas do not meet acceptable standards and require immediate management action

Davis-Besse Nuclear Power Station 31 December 6, 2004 Davis-Besse Nuclear Power Station Backlog Reduction Barry Allen Director - Site Operations

Davis-Besse Nuclear Power Station 32 December 6, 2004 Davis-Besse Nuclear Power Station Site Workload (all documents)

-Peak: April 2004 - 18,124

-November 2004 - 12,865 Backlog Reduction Site Workload 12000 13000 14000 15000 16000 17000 18000 19000 January Restart - April November All Documents

Davis-Besse Nuclear Power Station 33 December 6, 2004 Davis-Besse Nuclear Power Station Preventive Maintenance

-Peak: May 2004 - 312

-November 2004 - 13 Backlog Reduction Preventive Maintenance (PMs)

Deferrals Beyond Due Date 0

50 100 150 200 250 300 350 January Reatart - April November

  1. of PMs

Davis-Besse Nuclear Power Station 34 December 6, 2004 Davis-Besse Nuclear Power Station Corrective Action Documents

-Condition Reports

-January 2004 - 3,921

-November 2004 - 1,123

-Corrective Actions

-January 2004 - 6,522

-November 2004 - 3,419 Backlog Reduction Corrective Action Documents Corrective Actions Condition Reports 0

1000 2000 3000 4000 5000 6000 7000 January November

  1. of CRs and CAs

Davis-Besse Nuclear Power Station 35 December 6, 2004 Davis-Besse Nuclear Power Station Procedure Change Requests

-Peak 2004 (August) - 2,209

-November 2004 - 1,828 Backlog Reduction Procedure Change Requests 0

500 1000 1500 2000 2500 January Peak 2004 (August)

November All Documents

Davis-Besse Nuclear Power Station 36 December 6, 2004 Davis-Besse Nuclear Power Station Actions for Continuous Improvement Integrated Restart Report dated November 23, 2003 & Supplement to report dated February 6, 2004

- Appendix A Commitments 38

- Closed to date 27 Cycle 14 Operational Improvement Plan

- Appendix D Commitments 94

- Closed to date 59

Davis-Besse Nuclear Power Station 37 December 6, 2004 Davis-Besse Nuclear Power Station Mid-Cycle Outage Preparations Barry Allen Director - Site Operations

Davis-Besse Nuclear Power Station 38 December 6, 2004 Davis-Besse Nuclear Power Station Mid-Cycle Outage Preparations Scheduled start date ~ January 17, 2005 Project List includes

-Once-Through Steam Generator Eddy Current Testing

-Reactor Head and Vessel Inspections

-Boric Acid Corrosion Control Inspections

-Reactor Coolant Pump Inspections Preparation for Success

-July 30 - FENOC Readiness Review

-November 12 - Mid-cycle Outage Readiness Review

-Status outage readiness with senior management

Davis-Besse Nuclear Power Station 39 December 6, 2004 Davis-Besse Nuclear Power Station Oversight Perspective Ray Hruby Manager - Nuclear Oversight - DB

Davis-Besse Nuclear Power Station 40 December 6, 2004 Davis-Besse Nuclear Power Station Oversight Perspective 3rd Quarter Assessment Report Audited 25 Primary Elements

- 6 rated Effective

- 12 rated Satisfactory

- 7 rated Marginal Continuous Assessment Process

Davis-Besse Nuclear Power Station 41 December 6, 2004 Davis-Besse Nuclear Power Station Oversight Perspective Insights and Future Focus Areas Corrective Action Program Implementation Organizational Behaviors Procedure Use and Adherence Future Focus Areas

- Operations Performance

- Recent FENOC Reorganization Implementation

- Training

- Corrective Action Program Implementation

- Emergency Preparedness

Davis-Besse Nuclear Power Station 42 December 6, 2004 Davis-Besse Nuclear Power Station Oversight Perspective Oversight SCWE Interview Results Good Correlation with the recent SCWE Survey Observations

- Issues with Some Management Behaviors

- Impact of the Recent Reorganization

- Strong Belief That the Davis-Besse Safety Culture Supports the Safe Operation of the Plant

- Personnel Believe That They Can Raise Nuclear Safety or Quality Issues Without Fear of Retaliation

- Increasing Use of the Corrective Action Program

Davis-Besse Nuclear Power Station 43 December 6, 2004 Davis-Besse Nuclear Power Station Closing Comments Mark Bezilla Vice President FENOC Vision:

People with a strong safety focus delivering top fleet operating performance