ML043370318

From kanterella
Jump to navigation Jump to search
IR 05000312-04-004 & 07200011-04-004, on 10/05/04 to 10/28/04,Energy Supply, Sacramento Municipal Utility District, Rancho Seco Nuclear Generating Station
ML043370318
Person / Time
Site: Rancho Seco, 07200011
Issue date: 12/01/2004
From: Spitzberg D
Division of Nuclear Materials Safety IV
To: Shetler J
Sacramento Municipal Utility District (SMUD)
References
+sispmjr200506 IR-04-004
Download: ML043370318 (9)


See also: IR 05000312/2004004

Text

December 1, 2004

Mr. James Shetler, Assistant General Manager

Energy Supply

Sacramento Municipal Utility District

6201 'S' Street

P.O. Box 15830

Sacramento, California 95852

SUBJECT: NRC INSPECTION REPORT 050-00312/04-004; 072-00011/04-004

Dear Mr. Shetler:

This report refers to NRC inspections conducted on October 5-6, 12, and 27-28, 2004, at your

Rancho Seco Nuclear Generating Station. On November 3, 2004, a telephonic exit briefing

was conducted with Mr. Steve Redeker, Manager, Plant Closure and Decommissioning.

The inspections included the heavy lifts of the B steam generator upper section, the collection

of soil samples from beneath the spent fuel pool floor, and a review of the analysis for

accidental explosion or rapid burning of natural gas at the Cosumnes Power Plant. The

enclosed report presents the scope and results of the inspections. No violations of NRC

requirements were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be made available electronically for public inspection

in the NRC Public Document Room or from the Publicly Available Records (PARS) component

of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please note that on October 25, 2004, the NRC suspended public access to ADAMS, and

initiated an additional security review of publicly available documents to ensure that potentially

sensitive information is removed from the ADAMS database accessible through the NRC's web

site. Interested members of the public may obtain copies of the referenced documents for

review and/or copying by contacting the Public Document Room pending resumption of public

access to ADAMS. The NRC Public Document Room is located at NRC Headquarters in

Rockville, MD, and can be contacted at 800-397-4209 or 301-415-4737 or pdr@nrc.gov.

Should you have any questions concerning this inspection, please contact Scott Atwater at

(817) 860-8286 or the undersigned at (817) 860-8191.

Sincerely,

/R.J. EVANS FOR RA/

D. Blair Spitzberg, Ph.D., Chief

Fuel Cycle and Decommissioning Branch

Sacramento Municipal Utility District -2-

Docket Nos.: 050-00312; 072-00011

License Nos.: DPR-54; SNM-2510

Enclosure:

NRC Inspection Report

050-00312/04-004; 072-00011/04-004

cc w/enclosure:

Thomas A. Baxter, Esq.

Shaw, Pittman, Potts & Trowbridge

2300 N. Street, N.W.

Washington, D.C. 20037

Jerry Delezenski, Superintendent

Quality and Compliance

Sacramento Municipal Utility District

Rancho Seco Nuclear Generating Station

14440 Twin Cities Road

Herald, California 95638-9799

Sacramento County

Board of Supervisors

700 H. Street, Suite 2450

Sacramento, California 95814

Dana Appling, General Counsel

Sacramento Municipal Utility District

6201 S Street

P.O. Box 15830

Sacramento, California 95813

Ed Bailey, Radiation Program Director

California Radiologic Health Branch

State Department of Health Services

P.O. Box 997414 (MS 7610)

Sacramento, California 95899-7414

Cindy Buchanan, Site Document

Control Supervisor

Rancho Seco Nuclear Generating Station

14440 Twin Cities Road

Herald, California 95638-9799

James D. Boyd, Commissioner

California Energy Commission

1516 Ninth Street (MS 34)

Sacramento, California 95814

Sacramento Municipal Utility District -3-

bcc w/enclosure (via ADAMS distrib):

EECollins

JBHickman, NRR/DLPM/PDIV-2

ACMcMurtray, NRR/DSSA/SPLB

DBSpitzberg

EMGarcia

SPAtwater

KEGardin

FCDB File

ADAMS: :Yes 9No Initials: SPA

Publicly Available 9Non-Publicly Available 9Sensitive :Non-Sensitive

DOCUMENT NAME: s:\dnms\fcdb\spa\rs04-04.wpd final r:\_dnms

RIV:DNMS:FCDB RIV:DNMS:FCDB C:FCDB

EMGarcia SPAtwater DBSpitzberg

/S.ATWATER FOR RA/ /RA/ /R.EVANS FOR RA/

11/29/04 11/29/04 12/01/04

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket Nos.: 050-00312; 072-00011

License Nos.: DPR-54; SNM-2510

Report No.: 050-00312/04-004; 072-00011/04-004

Licensee: Sacramento Municipal Utility District

Facility: Rancho Seco Nuclear Generating Station

Location: 14440 Twin Cities Road

Herald, California 95638

Dates: October 5-6, 12, 27-28, and November 3, 2004

Inspectors: Emilio M. Garcia, Health Physicist

Scott P. Atwater, Health Physicist

Approved By: D. Blair Spitzberg, Ph.D., Chief

Fuel Cycle and Decommissioning Branch

Attachment: Supplemental Information

ADAMS Entry : IR 05000312-04-004; 072-00011/04-004 on 10/05/04 -11/03/04;

Sacramento Municipal Utility District; Rancho Seco Nuclear

Generating Station; Decommissioning Report; No Violations.

-2-

EXECUTIVE SUMMARY

Rancho Seco Nuclear Generating Station

NRC Inspection Report 050-00312/04-004; 072-00011/04-004

During these inspections, the inspectors observed movement of the B steam generator upper

section from its D-Ring enclosure to the transfer trailer and sampling of the soil beneath the

spent fuel pool floor. The inspectors also reviewed the analysis for accidental explosion or

rapid burning of natural gas at the Cosumnes Power Plant and its effect on the Rancho Seco

Independent Spent Fuel Storage Installation (ISFSI).

Decommissioning Performance and Status Review

  • The crane and rigging capacities, lifting heights, load travel paths, procedural controls,

and personnel safety measures were appropriate for the segmented steam generator

heavy lift evolutions. The work observed was being conducted in a safe and orderly

manner consistent with generally accepted industrial rigging and crane practices

(Section 1.2.a).

  • The site characterization samples of the soil beneath the spent fuel pool floor were

collected in accordance with site procedures, and sample integrity was maintained at all

times. Preliminary results from the licensee gamma spectroscopy analysis indicated no

radioactivity levels above background. A follow-up letter will be sent to the licensee

once the sample results are received from the Oak Ridge Institute for Science and

Education and are reviewed by the NRC (Section 1.2.b).

Operation of an ISFSI

  • The inspectors concurred with the licensees conclusion that the impact on the Rancho

Seco ISFSI from an explosion or rapid burning of natural gas at the Consumnes Power

Plant or Gas Metering Station was bounded by the ISFSI design for tornado and flood

events (Section 2.2).

-3-

Report Details

Summary of Facility Status

The Rancho Seco facility was undergoing active decommissioning with dismantlement work in

progress in the auxiliary, reactor and spent fuel buildings and outdoor areas. The licensee had

removed all 493 spent fuel assemblies from the spent fuel pool. Twenty-one canisters had

been loaded with spent fuel and transferred to the Independent Spent Fuel Storage Installation

(ISFSI). Most major components in the auxiliary building have been removed, packaged and

shipped for disposal. In the reactor building, most of the major piping, the four reactor coolant

pumps, the core flood tanks, the reactor vessel head, and the pressurizer had been removed,

packaged and disposed. The B steam generator had been segmented into upper and lower

sections. Two 24-inch lifting trunnions had been welded to the sides of the steam generator

shell for lifting. In the fuel handling building, most of the spent fuel pool liner had been removed

and released offsite. Borings had been made through the floor of the spent fuel pool for site

characterization sampling of the soil below the pool floor.

1 Decommissioning Performance and Status Review (71801)

1.1 Inspection Scope

The licensee was segmenting the two steam generators into upper and lower sections,

and removing the four resultant sections from the reactor building. Each section was a

heavy load weighing approximately 300 tons. This inspection focused on crane and

rigging capacities, lifting heights, load travel paths, procedural controls, and personnel

safety measures.

The licensee was obtaining site characterization samples of the soil beneath the spent

fuel pool floor. This inspection focused on the sampling methodology, integrity of

samples and preliminary sample results.

1.2 Observations and Findings

a. Movement of the B Steam Generator Upper Section

Both steam generators were to be segmented into upper and lower sections. Each of

the four resultant sections were to be removed from the reactor building, loaded onto a

special rail car assembly and shipped to a disposal site. The licensee had obtained U.S.

Department of Transportation Exemption, DOT-E 13338, which authorized the four

steam generator sections, classified as surface contaminated objects class II (SCO-II),

to be transported from the Rancho Seco station to a low level radioactive waste disposal

site in Clive, Utah without specification packaging. The steam generator shells serve as

the non-specification transportation packages and unique placarding was required. All

four steam generator sections were to be shipped by exclusive use rail freight.

The licensee had contracted with Bigge Power Constructors to remove the four steam

generator sections from the reactor building and load them onto special rail car

assemblies. Each steam generator section weighed approximately 300 tons and the

-4-

reactor building polar crane girders, rails, and rail supports had a rated capacity of

700 tons. However, the crane trolley did not provide the required capacity nor lifting

height, so it was not used. Instead, two steel towers were erected on top of the crane

girders to provide the needed capacity and lifting height. The towers, link chains and

lifting yoke had a rated capacity of 500 tons and the load was raised and lowered

hydraulically.

The B steam generator upper section heavy lifts were conducted in accordance with

Bigge drawing titled Rigging Arrangement - Upper Shell Steam Generator Removal

Project, dated September 3, 2004, and with Bigge drawing titled General Arrangement

- Upper Shell Removal, dated September 9, 2004. These two drawings provided the

building and equipment arrangement, removal sequence, rigging, lift heights and travel

paths. During the site visit of October 5-6, 2004, these drawings were reviewed for

clarity and function. Since a load drop would not impact any spent fuel or safe

shutdown equipment, NUREG-0612, Control of Heavy Loads at Nuclear Power Plants,

did not apply to these lifts. However, the BIGGE crane and rigging practices were

consistent with the NUREG-0612 guidelines in terms of handling system design, load

handling instructions and safe load paths.

During the site visit of October 12, 2004, a 110-percent load test was performed on the

crane and rigging. Just prior to the final cut on the B steam generator shell, the lifting

yoke was attached to the trunnions and 4700 psi of hydraulic pressure, the equivalent of

a 330 ton load, was applied to the towers and lifting chains. The hydraulic pressure was

then reduced to 4300 psi, the equivalent of 300 tons, and the final shell cuts were made.

The upper section of the steam generator was then lifted slightly and a diaper was

installed under the shell to catch any loose debris. The B steam generator upper

section was then lifted over the D-Ring wall to near the center of the reactor building.

On October 13, 2004, the polar crane was rotated into alignment with the equipment

hatch. The B steam generator upper section was then moved to the east and lowered

onto a closure lid in front of the equipment hatch. From October 14-27, 2004, the

closure lid was welded onto the open end of the steam generator section and a

polymeric coating was applied to the exterior to encapsulate any remaining removable

contamination.

During the site visit of October 27-28, 2004, the B steam generator upper section and

welded closure lid were downended and loaded onto the Bigge 10 axle trailer.

Preparations were begun for moving it out of the reactor building and onto a special rail

car assembly for shipment to the disposal site.

The BIGGE craft supervisor directed all load movements through his lead rigger who

executed the heavy lifts via radio contact with the crane operators on top of the crane.

The evolution was performed at a methodical pace and in accordance with the BIGGE

drawings. All personnel stayed clear of the load whenever it was suspended.

-5-

b. Characterization Sampling of Soil Beneath the Spent Fuel Pool

During the site visit of October 27-28, 2004, site characterization sampling of the soil

beneath the spent fuel pool floor was observed. The sampling operation was performed

in accordance with Spent Fuel Pool Subsurface Soil Sampling General Instructions,

dated September 27, 2004, and with Survey Sample Instruction Package

  1. SB8120070, Rev. 0.

Thirteen of the fifteen planned borings through the concrete in the spent fuel pool floor

had been completed. In each hole, split spoon samples were to be taken at one meter

increments down to a depth of 7 meters below the surface of the spent fuel pool floor.

With this method, the samples were to be collected from the same ground stratum

regardless of variations in spent fuel pool floor thickness. At the time of the inspection,

three holes had been fully sampled and sampling was started in the fourth hole. The

split spoon was approximately 3 inches in diameter, 1 meter in length and was driven

into the earth using a pile driver. As it was extracted from the hole, the exterior was

cleaned and the spoon was placed into a clean polyethylene bag labeled with sample

date, time, and location. The sample spoon was then carried to the preparation area

where it was opened. The center of the sample was collected into two scintillation vials,

one for a split with the NRC. Care was taken to minimize the samples exposure to air.

The remainder of the bulk sample was sifted for rocks and collected into a clean

container. A portion of the bulk sample was then transferred into a marinelli beaker for

a gamma spectroscopy analysis by the licensee. Another portion of the bulk sample

was transferred into a polyethylene container for a split with the NRC. Using this

process, soil samples from the first four borings were split with the NRC. All four

samples were extracted from the first meter of soil below the spent fuel pool floor.

Preliminary analysis results from the licensees gamma spectroscopy analysis indicated

no radioactivity levels above background. The NRC portion of the split samples were

sent to the Oak Ridge Institute for Science and Education (ORISE). ORISE will analyze

the four scintillation vial samples for volatile components such as carbon-14 and tritium

and the four bulk samples for a gamma spectrum. A follow-up letter will be sent to the

licensee once the ORISE results are received and reviewed by the NRC.

1.3 Conclusions

The crane and rigging capacities, lifting heights, load travel paths, procedural controls,

and personnel safety measures were appropriate for the segmented steam generator

heavy lift evolutions. The work observed was being conducted in a safe and orderly

manner consistent with generally accepted industrial rigging and crane practices.

The site characterization samples of the soil beneath the spent fuel pool floor were

collected in accordance with site procedures, and sample integrity was maintained at all

times. Preliminary results from the licensee gamma spectroscopy analysis indicated no

radioactivity levels above background. A follow-up letter will be sent to the licensee

once the sample results are received from ORISE and are reviewed by the NRC.

-6-

2 Operation of an ISFSI (60855)

2.1 Inspection Scope

The inspectors reviewed the Rancho Seco Quality Surveillance Report 04-S-025 which

contained the analysis of an accidental explosion or rapid burning of natural gas at the

Consumnes Power Plant or Gas Metering Station.

2.2 Observations and Findings

The analysis was performed by a licensee contractor. It evaluated a worst case

accidental explosion or rapid burning of natural gas at the new Cosumnes Power Plant

or Gas Metering Station for potential impact on the existing ISFSI. The inspectors

reviewed the analysis and found it to be comprehensive. The analysis concluded that

the impact on the Rancho Seco ISFSI from this event was less severe than the tornado

and flood events for which the ISFSI was designed.

2.3 Conclusions

The inspectors concurred with the licensees conclusion that the impact on the Rancho

Seco ISFSI from an explosion or rapid burning of natural gas at the Consumnes Power

Plant or Gas Metering Station was bounded by the ISFSI design for tornado and flood

events.

3 Exit Meeting Summary

A telephonic exit interview was conducted with Mr. Steve Redeker, Plant Manager, on

November 3, 2004. The general scope and results of these inspections were discussed.

The licensee did not identify as proprietary any information provided to or reviewed by

the inspectors.

ATTACHMENT

SUPPLEMENTAL INFORMATION

PARTIAL LIST OF PERSONS CONTACTED

Sacramento Municipal Utility District

D. Brown, ALARA Engineer

R. Burrell, Senior Decommissioning Technician

D. Clark, Senior Mechanical Engineer

J. Delezenski, Quality Assurance/Licensing/Administration/Training Superintendent

P. Melendy, Radiation Protection Technician

S. Porterfield, Supervisor Radiation Engineering Specialist

E. Ronningen, Principal Decommissioning Radiological Engineer

D. Russell, Rad Waste Handler

S. Redeker, Manager, Plant Closure and Decommissioning

J. Witte, Principal Mechanical Engineer

Bigge Power Constructors

T. Garcia, Craft Supervisor

INSPECTION PROCEDURES USED

IP 60855 Operation of an ISFSI

IP 71801 Decommissioning Performance and Status Review

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

None

Closed

None

Discussed

None

LIST OF ACRONYMS

ISFSI Independent Spent Fuel Storage Installation

ORISE Oak Ridge Institute for Science and Education