November 29, 2004 Mr. Stephen M. Quennoz, Vice President Power Supply/Generation Portland General Electric Company Trojan Nuclear Plant 71760 Columbia River Highway Rainier, Oregon 97048
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION REGARDING PORTLAND GENERAL ELECTRIC COMPANYS APPLICATION FOR CONSENT TO INDIRECT TRANSFER OF FACILITY LICENSES
Dear Mr. Quennoz:
On June 14, 2004, Portland General Electric Company (PGE) submitted an Application for Consent to Indirect Transfer of Facility Licenses to the U.S. Nuclear Regulatory Commission (NRC) for review and approval. Specifically, the application requested approval under 10 CFR 50.80, in connection with the proposed acquisition of PGE by Oregon Electric Utility Company, LLC (OEUC) from Enron. PGE provided supplemental information on September 29, 2004.
The NRC staff has completed its review and concludes that additional information is required before NRC can determine the acceptability of PGEs application for Consent to Indirect Transfer of Facility Licenses. Specifically, the NRC is requesting the following information:
1.
Describe approximately what percentage of PGE annual electric power revenues are typically accounted for by: (1) wholesale sales under FERC jurisdiction; and (2) retail sales under OPUC jurisdiction. If wholesale sales exceed 20 percent of PGEs total revenue, state whether any wholesale revenues are relied upon to cover costs to complete decommissioning or to manage spent fuel.
2.
Describe the current percentage of foreign capital ownership of each of the TPG limited partnerships, TPG Partners III, L.P., and TPG Partners IV, L.P., and of each of the TPG General Partners.
3.
Provide the information required in 10 CFR 50.33(d) as it applies to TPG itself.
4.
Explain if, and under what condition(s) and likely timing, a separate application might be submitted to the NRC regarding interim ownership of PGE by a trust.
5.
Provide a current list of the members of the PGE Board of Directors and their current citizenship. Provide the names and citizenship of any other members in addition to those already identified in the application that currently are anticipated to be elected to the PGE Board either before, or after, closing the proposed sale.
S. Quennoz Per the teleconference on November 18, 2004, the staff understands that PGE will submit the requested information within three weeks.
If you have any questions concerning this evaluation, please contact me at (301) 415-6607.
Sincerely,
/RA/
John T. Buckley, Project Manager Decommissioning Directorate Division of Waste Management and Environmental Protection Office of Nuclear Material Safety and Safeguards
Attachment:
As stated Docket No.: 50-344 License No.: NPF-1
S. Quennoz Per the teleconference on November 18, 2004, the staff understands that PGE will submit the requested information within three weeks.
If you have any questions concerning this evaluation, please contact me at (301) 415-6607.
Sincerely, John T. Buckley, Project Manager Decommissioning Directorate Division of Waste Management and Environmental Protection Office of Nuclear Material Safety and Safeguards Attachment; As stated Docket No.: 50-344 License No.: NPF-1 DISTRIBUTION: