_ Entergy Entergy Nuclear Operations, Inc.

Pilgrim Station 600 Rocky Hill Road Plymouth, MA 02360 November 8, 2004 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555

SUBJECT:

Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station Docket No.: 50-293 License No.: DPR-35 October Operating Data Report LETTER NUMBER: 2.04.109

Dear Sir or Madam:

In accordance with Technical Specification 5.6.4, the attached operating data report for Pilgrim Nuclear Power Station is provided for your information and planning.

There are no commitments contained in this letter.

Should you have questions or comments concerning this report, please contact me at (508) 830-8403.

Sincerely, Bryan Ford Manager, Licensing MJG/dm

Attachment:

October Operating Data Report (1 page) cc: Mr. Samuel J. Collins Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Senior Resident Inspector 204109 9X~

I I OPERATING DATA REPORT DOCKET NO. 50-293 UNIT NAME Pilgrim 1 DATE November 02, 2004 COMPLETED BY Mary J. Gatshck -.

TELEPHONE (508) 830-8373 REPORTING PERIC October 2004

1. Design Electrical Rating 690.00
2. Maximum Dependable Capacity (MWe-Net) 684.70 This Month Yr-to-Date Cumulative
3. Number of Hours the Reactor was Critical 745.00 7,274.58 197,429.48
4. Number of Hours Generator On-line 745.00 7,257.92 195,202.87
5. Reserve Shutdown Hours 0.00 0.00 0.00
6. Net Electrical Energy Generated (MWHrs) 507,424.96 4,939,914.71 116,592,593.1 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments

SUMMARY

The period began and ended with the unit on line, operating at 100% power (2028 MWt). There were no power reductions during this reporting period.

1 2 Reason: Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

Page 1 of 1