MONTHYEARML0430000532004-10-27027 October 2004 Notice of Consideration, Revise Allowed Outage Times of Technical Specification 3.3.3.6, Accident Monitoring Instrumentation, to Be Consistent with the Completion Times in Related Specification in NUREG-1431, Revision 3 Project stage: Other ML0432202652004-11-17017 November 2004 Facsimile Transmission, Draft Request for Additional Information Project stage: Draft RAI ML0516801022005-06-15015 June 2005 Tech Spec Pages Re Allowed Outage Times for Accident Monitoring Instrumentation Project stage: Other ML0506303102005-06-15015 June 2005 License Amendment 103 Revision to Technical Specifications Related to Allowed Outage Times for Accident Monitoring Instrumentation Project stage: Approval 2004-11-17
[Table View] |
|
---|
Category:Memoranda
MONTHYEARML23053A0502023-02-22022 February 2023 Cover Memo and Response to C-10 Questions Regarding 3Q2022 Inspection Report ML22306A0202022-11-0202 November 2022 Cover Memo and Response to C-10 Questions Regarding 2Q2022 Inspection Report ML24285A2012022-06-29029 June 2022 Memo Response - LTR-24-0212 - Response from Thomas Szabo - C-10 Board Member - David Lochbaum ML21242A2242021-08-26026 August 2021 C-10 Research & Education Foundation Memo Dated 8/26/21 Re Questions Regarding the 2021 Second Quarter Integrated Inspection Report (05000443/2021002) ML21062A1462021-04-21021 April 2021 Memo to File: Final Ea/Fonsi of 2012 and 2015 Decommissioning Funding Plans for Seabrook Station Unit 1 Independent Spent Fuel Storage Installation (2012 and 2015) ML19057A3832019-03-0404 March 2019 Renewal of Full-Power Operating License for Seabrook Station, Unit No. 1 ML19058A2162019-03-0404 March 2019 Update to Proposed Issuance of a Final No Significant Hazards Consideration Determination and License Amendment Regarding Which a Hearing Has Been Requested (CAC No. MF8260; EPID L-2016-LLA-0007) ML18226A2052018-09-28028 September 2018 Redacted, Submission of Alkali-Silica Reaction License Amendment Request Draft Safety Evaluation to Support Advisory Committee on Reactor Safeguards Review of Seabrook License Renewal (CAC No. MF8260; EPID L-2016-LLA-0007) ML18243A4522018-08-31031 August 2018 License Renewal Application Memorandum ML17278A1662017-10-0505 October 2017 Teleconference Meeting Summary Dated August 28, 2017 with Massachusetts Attorney General'S Office and Massachusetts Emergency Management Agency ML17254A7522017-09-0606 September 2017 Alkali-Silica Reaction Issue Technical Team Charter Revision 2 ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16056A3342016-03-0101 March 2016 Memorandum to File Regarding Transcript for 10 CFR 2.206 Petition from C-10 Research & Education Foundation Regarding Seabrook Station, Unit 1 ML15096A1682015-07-27027 July 2015 Memorandum to File from John Lamb, DORL, NRR No Significant Hazards Consideration Analysis and Categorical Exclusion Related to Proposed Exemption ML14014A3782014-02-19019 February 2014 Alkali-Silica Reaction (ASR) Issue Technical Team Charter, Revision 1 ML13193A0742013-07-16016 July 2013 Request for Additional Information - Seabrook Station Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (Tac No. MF0837) ML13128A5212013-06-10010 June 2013 Memo Position Paper -Assessment of Aci 318-71 as Design Basis for Category I Concrete Structures Affected by Alkalisilica Reaction at Seabrook Station. ML13154A5052013-06-0404 June 2013 Rai'S Following Ifib Analysis of NextEra Energy'S 2013 Decommissioning Funding Status Reports for Seabrook ML13099A2152013-04-18018 April 2013 Forthcoming Meeting with Nextera Energy Seabrook, LLC (Nextera) Regarding a Pre-Submittal for a Fixed Incore Detector License Amendment Request ML13066A4882013-03-21021 March 2013 Summary of Meeting Held on February 21, 2013, Between the NRC and NextEra Energy Seabrook, LLS Regarding License Renewal Application, Seabrook Station ML12242A3702012-09-0505 September 2012 Request for Deviation from the Reactor Oversight Process Action Matrix to Provide Increased Oversight of the Alkali-Silica Reaction Issue at Seabrook ML12236A3852012-08-23023 August 2012 Memo Summary of NextEra Energy Seabrook Drop in Visit and Slides, August 22, 2012 ML12222A0392012-08-0909 August 2012 8/16/2012 Cancellation Notice of Forthcoming Conference Call with NextEra Energy and Florida Power and Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Proto ML12213A0612012-08-0101 August 2012 8/16/12 Forthcoming Conference Call with NextEra Energy and Florida Power & Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol ML12164A9012012-06-22022 June 2012 Summary of Telephone Conference Call Held on 5/24/12, Between the NRC and NextEra Energy Seabrook, LLC Concerning the Drai Pertaining to the Seabrook Station LRA ML13196A2202012-06-0606 June 2012 Memo from B. Balsam, NRR and D. Logan, NRR to J. Susco, NRR on Summary of Section 7 Consultation Activities Related to the National Marine Fisheries Service'S Final Rule to List the Atlantic Sturgeon ML12173A4622012-06-0404 June 2012 Draft Letter from D. Roberts, Region I to J. Jolicoeur, NRR; Subject: Request for Technical Assistance, Seabrook Station Alkali-Silica Reaction ML12173A4632012-06-0404 June 2012 Draft Letter from D. Roberts, Region I to R. Nelson, NRR; Subject: Request for Technical Assistance, Seabrook Station Alkali-Silica Reaction ML12174A0122012-06-0404 June 2012 Draft Letter from J. Clifford, Region I to R. Nelson, NRR; Subject: Request for Technical Assistance, Seabrook Station Alkali-Silica Reaction ML12174A0172012-06-0404 June 2012 Draft Letter from J. Clifford, Region I to R. Nelson, NRR; Subject: Request for Technical Assistance, Seabrook Station Alkali-Silica Reaction ML12174A0152012-06-0404 June 2012 Draft Letter from J. Clifford, Region I to R. Nelson, NRR; Subject: Request for Technical Assistance, Seabrook Station Alkali-Silica Reaction ML1208600492012-03-23023 March 2012 Corrected Notice of Forthcoming Meeting with NextEra Energy Seabrook, LLC (NextEra) Regarding Seabrook Station Concrete Degradation ML12054A7292012-02-16016 February 2012 DRAFT- from James Clifford to Robert Nelson Request for Technical Assistance Seabrook Station ALKALI-SILICA Reaction, Draft 5 ML12054A7132012-02-16016 February 2012 DRAFT- from James Clifford to Robert Nelson Request for Technical Assistance Seabrook Station ALKALI-SILICA Reaction, Draft 8 2010817 ML12054A7312012-02-16016 February 2012 DRAFT- from James Clifford to Robert Nelson Request for Technical Assistance Seabrook Station ALKALI-SILICA Reaction, Draft 3 ML12054A7042012-02-16016 February 2012 DRAFT- from Darrell Roberts to John Jolicoeur Request for Technical Assistance Seabrook Station ALKALI-SILICA Reaction, Draft 2 ML12054A7282012-02-16016 February 2012 DRAFT- from James Clifford to Robert Nelson Request for Technical Assistance Seabrook Station ALKALI-SILICA Reaction, Draft 5 ML12054A7272012-02-16016 February 2012 DRAFT- from James Clifford to Robert Nelson Request for Technical Assistance Seabrook Station ALKALI-SILICA Reaction, Draft 4 ML12054A7112012-02-16016 February 2012 DRAFT- from James Clifford to Robert Nelson Request for Technical Assistance Seabrook Station ALKALI-SILICA Reaction, Draft 6 ML12054A7122012-02-16016 February 2012 DRAFT- from James Clifford to Robert Nelson Request for Technical Assistance Seabrook Station ALKALI-SILICA Reaction, Draft 7 (2) ML12054A7142012-02-16016 February 2012 DRAFT- from James Clifford to Robert Nelson Request for Technical Assistance Seabrook Station ALKALI-SILICA Reaction, Draft 8 Comment ML12054A7302012-02-16016 February 2012 DRAFT- from James Clifford to Robert Nelson Request for Technical Assistance Seabrook Station ALKALI-SILICA Reaction, Draft 3. Resolved ML11354A1182011-12-22022 December 2011 12/8/2011 Summary of Meeting Between NRC Staff and the Nuclear Energy Institute to Discuss Current License Renewal Topics ML11343A4482011-12-0909 December 2011 NextEra Drop in Meeting Summary and Slides from 11-14-2011 Meeting with Region-I ML11327A0722011-11-30030 November 2011 Summary of Telephone Conference Call Held on November 22, 2011, Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook, LLC, Concerning the Response to the Request for Additional Information Pertaining to the Seabrook St ML11304A1662011-11-0404 November 2011 Summary of Tele Conf Call Held on 3/3/11, Between the USNRC and NextEra Energy Seabrook, Llc. Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Responses ML11304A1512011-11-0404 November 2011 Summary of Tele Conf Call Held on 4/8/11 Between USNRC and NextEra Energy Seabrook, Llc. Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Responses ML11304A1092011-11-0404 November 2011 Summary of Tele Conf Call Held on 5/31/11, Between the USNRC and Nextera Energy Seabrook, Llc., Concerning Clarification of Information Pertaining to the Seabrook LRA ML11277A0462011-10-26026 October 2011 Summary of Public Meetings Conducted to Discuss the Dseis Related to the Review of the Seabrook Station License Renewal Application 2023-02-22
[Table view] |
Text
November 17, 2004 MEMORANDUM TO: Daniel S. Collins, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Victor Nerses, Senior Project Manager, Section 2 /RA/
Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
SEABROOK STATION, UNIT NO. 1, FACSIMILE TRANSMISSION, DRAFT REQUEST FOR ADDITIONAL INFORMATION (TAC NO.
MC4902)
The attached draft RAI was transmitted by facsimile on November 17, 2004, to Mr. Micheal OKeefe of FPL Energy Seabrook, LLC (FPL Energy Seabrook). This draft RAI was transmitted to facilitate the technical review being conducted by Nuclear Regulatory Commission (NRC) staff and to support a conference call with FPL Energy Seabrook in order to clarify certain items. The draft RAI is related to the licensees October 22, 2004, submittal regarding proposed changes to Technical Specification 3.3.3.6, Accident Monitoring Instrumentation. Review of the RAI would allow the licensee to determine and agree upon a schedule to respond to the RAI. This memorandum and the attachment do not convey or represent an NRC staff position regarding the licensees request.
Docket No. 50-443
Enclosure:
Draft RAI
November 17, 2004 MEMORANDUM TO: Daniel S. Collins, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Victor Nerses, Senior Project Manager, Section 2 /RA/
Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
SEABROOK STATION, UNIT NO. 1, FACSIMILE TRANSMISSION, DRAFT REQUEST FOR ADDITIONAL INFORMATION (TAC NO.
MC4902)
The attached draft RAI was transmitted by facsimile on November 17, 2004, to Mr. Micheal OKeefe of FPL Energy Seabrook, LLC (FPL Energy Seabrook). This draft RAI was transmitted to facilitate the technical review being conducted by Nuclear Regulatory Commission (NRC) staff and to support a conference call with FPL Energy Seabrook in order to clarify certain items. The draft RAI is related to the licensees October 22, 2004, submittal regarding proposed changes to Technical Specification 3.3.3.6, Accident Monitoring Instrumentation. Review of the RAI would allow the licensee to determine and agree upon a schedule to respond to the RAI. This memorandum and the attachment do not convey or represent an NRC staff position regarding the licensees request.
Docket No. 50-443
Enclosure:
Draft RAI DISTRIBUTION PUBLIC PDI-2 Reading BMarcus V. Nerses GMiller Accession Number: ML043220265 OFFICE PDI-2/PE PDI-2/PM EEIB-A/SC NAME GMiller VNerses EMarinos DATE 11/15/04 11/16/04 11/15/04
OFFICIAL RECORD COPY DRAFT REQUEST FOR ADDITIONAL INFORMATION RELATED TO REQUESTED CHANGES TO TS 3.3.3.6 FPL ENERGY SEABROOK, LLC SEABROOK STATION DOCKET NO. 50-443 By letter dated October 22, 2004, FPL Energy Seabrook, LLC (FPL Energy Seabrook),
submitted LAR 04-08, which requested Nuclear Regulatory Commission (NRC) approval of a proposed amendment to facility operating license number NPF-86. The proposed change would revise the Seabrook Station Technical Specification (TS) 3.3.3.6, Accident Monitoring Instrumentation. The NRC staff has developed the following draft questions during its review of the application:
- 1. In LAR 04-08, FPL Energy Seabrook states that the revised actions proposed in the amendment request are consistent with the conditions and completion times contained in NUREG 1431, Rev. 3, Improved Standard Technical Specifications, Westinghouse Plants, (ISTS).
Please provide a comparison of the assumptions and similarities of the Seabrook Station TS 3.3.3.6 to the ISTS equivalent section 3.3.3. This comparison should include a comparison of LCOs, operating mode applicability, exceptions to other LCOs, and surveillance requirements.