November 15, 2004 R. T. Ridenoure Vice President Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
P.O. Box 550 Fort Calhoun, NE 68023-0550
SUBJECT:
ASSESSMENT FOLLOWUP LETTER - FORT CALHOUN STATION
Dear Mr. Ridenoure,
On November 5, 2004, the NRC staff completed a quarterly plant performance review of the Fort Calhoun Station. The assessment evaluated the performance indicators (PIs) and inspection results compiled during the previous 12 months. The purpose of this letter is to inform you of your safety performance during this period and our plans for a future inspection at your facility.
Our review identified that you have crossed the threshold from Green to White for the Emergency AC Power Unavailability performance indicator. The unavailability was associated with Diesel Generator 2 being inoperable for approximately 28 days due to a failed fuse.
As a result, we have assessed Fort Calhoun Station performance to be in the Regulatory Response column of the NRCs Action Matrix. Therefore, we plan to conduct a supplemental inspection in accordance with NRC Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area, to review the actions taken in response to this White performance indicator. The purpose of this supplemental inspection will be to provide assurance that the root and contributing causes for the White performance indicator are understood, the extent of condition and extent of cause are identified, and the corrective actions are sufficient to address the root and contributing causes and prevent their recurrence. The schedule for this inspection will be communicated to you in separate correspondence.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Omaha Public Power District Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
/RA/ by Anton Vegel acting for Arthur T. Howell III, Director Division of Reactor Projects Docket: 50-285 License: DPR-40 cc:
John B. Herman, Manager Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
P.O. Box 550 Fort Calhoun, NE 68023-0550 Richard P. Clemens, Division Manager Nuclear Assessments Fort Calhoun Station P.O. Box 550 Fort Calhoun, NE 68023-0550 David J. Bannister Manager - Fort Calhoun Station Omaha Public Power District Fort Calhoun Station FC-1-1 Plant P.O. Box 550 Fort Calhoun, NE 68023-0550 James R. Curtiss Winston & Strawn 1400 L. Street, N.W.
Washington, DC 20005-3502 Chairman Washington County Board of Supervisors P.O. Box 466 Blair, NE 68008
Omaha Public Power District Sue Semerena, Section Administrator Nebraska Health and Human Services System Division of Public Health Assurance Consumer Services Section 301 Centennial Mall, South P.O. Box 95007 Lincoln, NE 68509-5007 Daniel K. McGhee Bureau of Radiological Health Iowa Department of Public Health 401 SW 7th Street, Suite D Des Moines, IA 50309 Institute of Nuclear Power Operations (INPO)
Records Center 700 Galleria Parkway SE, Suite 100 Atlanta, GA 30339
Omaha Public Power District Electronic distribution by RIV:
Regional Administrator (BSM1)
DRP Director (ATH)
DRS Director (DDC)
DRS Deputy Director (GLS)
Senior Resident Inspector (JDH1)
Branch Chief, DRP/C (KMK)
Senior Project Engineer, DRP/C (WCW)
Team Leader, DRP/TSS (RVA)
RITS Coordinator (KEG)
Matt Mitchell, OEDO RIV Coordinator (MAM4)
FCS Site Secretary (vacant)
V. Dricks, PAO (VLD)
W. Maier, RSLO (WAM)
C. Gordon (CJG)
DRS Branch Chiefs (LJS, MPS1, ATG, JAC)
L. Reyes, EDO (LAR1)
S. Richards, Chief, NRR/DIPM/IIPB (SAR)
R. Frahm, PPR Program Manager, NRR/DIPM/IIPB (RKF)
C. Carpenter, Deputy Dir. for Inspection and Programs (CAC)
B. Sheron, Associate Dir. for Project Licensing and Technical Analysis (BWS)
T. Bergman, Chief, ROPMS, OEDO (TAB)
H. Berkow, Director, LPD4, NRR/DLPM (HNB)
R. Gramm, Chief, PDIV-2B, NRR/DLPM (RAG)
A. B. Wang, NRR Project Manager (ABW)
ADAMS: / Yes G No Initials: __kmk__
/ Publicly Available G Non-Publicly Available G Sensitive / Non-Sensitive S:\\DRP\\DRPDIR\\3rd Quarter Memo 2004\\FCS 3Q 2004 Assessment Letter Update.wpd RIV:C:DRP/C D:DRP KMKennedy;df ATHowell III
/RA/
/RA/ by AVegel 11/10/04 11/15/04 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax