Press Release-04-139: NRC Approves Stretch Power Uprate for Indian Point Unit 2
ML043020581
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 10/28/2004
From:
NRC/OIP
To:
References
Press Release-04-139
Download: ML043020581 (1)


Text

NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Telephone: 301/415-8200 Washington, DC 20555-0001 E-mail: opa@nrc.gov Web Site: http://www.nrc.gov/OPA No.04-139 October 28, 2004 NRC APPROVES STRETCH POWER UPRATE FOR INDIAN POINT UNIT 2 The Nuclear Regulatory Commission has approved a request by Entergy Nuclear Operations to increase the generating capacity of Unit 2 at the Indian Point Energy Center by 3.26 percent. The NRC staff determined that Entergy could safely increase the reactors power output primarily by upgrading minor plant components, as well as performing evaluations that showed the plants existing design can handle the increased power level.

Stretch power uprates are typically on the order of up to 7 percent and usually involve changes to instrument settings. The stretch power uprate for the Indian Point unit, located 24 miles north of New York City, will increase its generating capacity from approximately 995 to 1040 megawatts electric. Entergy intends to operate Indian Point Unit 2 at the higher power level following its fall refueling operations.

NRC previously published a notice about the power uprate application in the Federal Register providing the public an opportunity to comment or request a hearing. No comments or hearing requests were received by the NRC.

The NRC's safety evaluation of the plants proposed stretch power uprate focused on several areas, including nuclear steam supply systems, instrumentation and control systems, electrical systems, accident evaluations, radiological consequences, operations, and other technical specification changes.