Summary of Telephone Conference Held on September 16, 2004, Between the U.S. Nuclear Regulatory Commission and Indiana Michigan Power Company, Concerning Unresolved Items Pertaining to the Donald C. Cook Nuclear Plant, Units 1 and 2, LRA
ML042920437
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 10/15/2004
From: Rowley J
NRC/NRR/DRIP/RLEP
To:
Indiana Michigan Power Co
Rowley J, NRR/DRIP/RLEP, 415-4053
References
Download: ML042920437 (6)


Text

October 15, 2004 LICENSEE: Indiana Michigan Power Company FACILITY: Donald C. Cook Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 16, 2004, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND INDIANA MICHIGAN POWER COMPANY, PERTAINING TO THE DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Indiana Michigan Power Company (I&M) held a telephone conference call on September 16, 2004, to discuss and clarify a request for additional information (RAI) concerning the Donald C. Cook Nuclear Plant, Units 1 and 2, license renewal application (LRA). The conference call was useful in clarifying the intent of the staffs RAI. provides a listing of the telephone conference call participants. Enclosure 2 contains the RAI discussed with the applicant, including a brief description on the status of the RAI.

The applicant has had an opportunity to comment on this summary.

/RA/

Jonathan G. Rowley, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos. 50-315 and 50-316

Enclosures:

As stated cc w/encls: See next page

ML042920437 DOCUMENT NAME: C:\ORPCheckout\FileNET\ML042920437.wpd OFFICE PM:RLEP LA:RLEP SC:RLEP NAME JRowley YEdmonds SLee DATE 10/15/04 10/15/04 10/15/04 DISTRIBUTION: Licensee: Indiana Michigan Power Co., Re: Donald C.Cook Plant, Units 1 and 2, Dated: October 15, 2004 Accession No: ML042920437 HARD COPY RLEP RF J. Rowley (PM)

E-MAIL:

RidsNrrDrip RidsNrrDe G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair RidsNrrDssa RidsNrrDipm D. Thatcher R. Pettis C. Li M. Itzkowitz (RidsOgcMailCenter)

R. Weisman M. Mayfield A. Murphy S. Smith (srs3)

S. Duraiswamy Y. L. (Renee) Li RLEP Staff R. Gramm A. Howell J. Stang J. Strasma, RIII M. Kotzalas OPA NRR/ADPT secretary (RidsNrrAdpt)

LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALL TO DISCUSS THE DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION SEPTEMBER 16, 2004 Participants Affiliations Jonathan Rowley U.S. Nuclear Regulatory Commission (NRC)

Hansraj Ashar NRC Ralph Schlichter Indiana Michigan Power Company Enclosure 1

REQUEST FOR ADDITIONAL INFORMATION DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION SEPTEMBER 16, 2004 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Indiana Michigan Power Company (I&M) held a telephone conference call on September 16, 2004, to discuss and clarify the Donald C. Cook Nuclear Plant, Units 1 and 2 (Cook), license renewal application (LRA). The following RAI was discussed during the telephone conference call.

RAI 3.5-1 In line item 3.5.1-3 of Table 3.5.1 of the LRA, the applicant indicates that the aging effects related to loss of material due to corrosion of bellows, and dissimilar metal welds are managed consistent with NUREG-1801. NUREG-1801 recommends the examination of penetration bellows and the associated dissimilar welds based on the operating experience with the stress corrosion cracking of bellows as documented in NRC Information Notice 92-20. The applicant is requested to provide the following information related to the examination and/or testing of containment penetration bellows:

How many penetration bellows are in the Cook containments? Please summarize the operating experience related to the examination of these bellows. If provisions are made to assess their leaktightness (as they are not accessible for visual examination), please provide a summary of these provisions (including frequency of tests), and indicate if such leaktightness assessment of the bellows is part of the LRA aging management program (AMP) B.1.15 or B.1.8.

Additional Information Requested I&Ms supplemental response to RAI 3.5-1 indicates that the Cook penetration bellows do not provide a containment pressure-boundary function, they are not included in the scope of license renewal, and are not subject to aging management. The staff had concerns that cracking in two sets of bellows in the penetration could jeopardize containment isolation and that the bellows do perform support functions for two safety-related pipes and structures. The applicant is requested to justify why these bellows should not be in the scope of license renewal.

Discussion The applicant directed the staff to Figure 5.2-4 of the Cook updated final safety analysis report (UFSAR). Figure 5.2-4 illustrates the fuel transfer tube on which the bellows in question are located. I&M used the figure to confirm how the bellow inside containment is completely independent of those bellows outside containment and that it was impossible for there to be communication between the inside and outside bellows. I&M used the figure to confirm that the bellows do not perform support functions. The staff will evaluate this information and no further I&M action is requested at this time.

Enclosure 2

Donald C. Cook Nuclear Plant, Units 1 and 2 cc:

Regional Administrator, Region III Michigan Department of Environmental U.S. Nuclear Regulatory Commission Quality 2443 Warrenville Road, Suite 210 Waste and Hazardous Materials Div.

Lisle, IL 60532-4351 Hazardous Waste & Radiological Protection Section Township Supervisor Nuclear Facilities Unit Lake Township Hall Constitution Hall, Lower-Level North P.O. Box 818 525 West Allegan Street Bridgman, MI 49106 P.O. Box 30241 Lansing, MI 48909-7741 U.S. Nuclear Regulatory Commission Resident Inspectors Office Michael J. Finissi, Plant Manager 7700 Red Arrow Highway Indiana Michigan Power Company Stevensville, MI 49127 Nuclear Generation Group One Cook Place David W. Jenkins, Esquire Bridgman, MI 49106 Indiana Michigan Power Company One Cook Place Mr. Joseph N. Jensen, Site Vice President Bridgman, MI 49106 Indiana Michigan Power Company Nuclear Generation Group Mayor, City of Bridgman One Cook Place P.O. Box 366 Bridgman, MI 49106 Bridgman, MI 49106 Mr. Fred Emerson Special Assistant to the Governor Nuclear Energy Institute Room 1 - State Capitol 1776 I Street, N.W., Suite 400 Lansing, MI 48909 Washington, DC 20006-3708 Mr. John A. Zwolinski Richard J. Grumbir Director, Design Engineering and Project Manager, License Renewal Regulatory Affairs Indiana Michigan Power Company Indiana Michigan Power Company Nuclear Generation Group Nuclear Generation Group 500 Circle Drive 500 Circle Drive Buchanan, MI 49107 Buchanan, MI 49107 Mr. Mano K. Nazar Laura Kozak Senior Vice President and Chief Nuclear 2443 Warrenville Rd. Officer Lisle, IL 60532 Indiana Michigan Power Company Nuclear Generation Group 500 Circle Drive Buchanan, MI 49107