MONTHYEARIR 05000213/20240012024-08-27027 August 2024 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation NRC Inspection Report Nos. 07200039/2024001 and 05000213/2024001 ML24094A0742024-05-30030 May 2024 Issuance of Exemption for Connecticut Yankee Atomic Power Company Regarding Haddam Neck Plant Independent Spent Fuel Storage Installation ML23342A0972024-01-0909 January 2024 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan CY-23-014, Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI2023-12-0404 December 2023 Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI ML23124A2012023-04-20020 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2022 CY-23-006, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2023-03-0606 March 2023 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report CY-23-007, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2023-03-0606 March 2023 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22340A4922023-02-24024 February 2023 Closeout Letter to Connecticut Yankee Regarding 2018 and 2021 Updated DFPs for Haddam Neck Plant ISFSI CY-23-003, Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage2023-01-17017 January 2023 Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage CY-23-004, Independent Spent Fuel Storage Installation, Property Insurance Coverage2023-01-17017 January 2023 Independent Spent Fuel Storage Installation, Property Insurance Coverage CY-23-002, Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments2023-01-0505 January 2023 Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments CY-23-001, Independent Spent Fuel Storage Installation, Report of 10 CFR 50.59 Changes, Tests, and Experiments2023-01-0505 January 2023 Independent Spent Fuel Storage Installation, Report of 10 CFR 50.59 Changes, Tests, and Experiments IR 07200039/20224012022-10-0505 October 2022 Connecticut Yankee Atomic Power Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200039/2022401 CY-22-012, Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan2022-08-0303 August 2022 Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan CY-22-010, Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation, Formal Announcement of New ISFSI Manager2022-05-25025 May 2022 Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation, Formal Announcement of New ISFSI Manager CY-22-006, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 20212022-04-25025 April 2022 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2021 CY-22-003, and Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report2022-03-14014 March 2022 and Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report CY-22-004, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2022-03-14014 March 2022 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22011A1352022-01-31031 January 2022 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan CY-22-002, Independent Spent Fuel Storage Installation - Property Insurance Coverage2022-01-20020 January 2022 Independent Spent Fuel Storage Installation - Property Insurance Coverage CY-22-001, Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage2022-01-20020 January 2022 Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage CY-21-015, Independent Spent Fuel Storage Installation, Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan2021-12-10010 December 2021 Independent Spent Fuel Storage Installation, Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan CY-21-011, Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI2021-12-0101 December 2021 Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI CY-21-013, Biennial Update to the Haddam Neck Plant License Termination Plan2021-12-0101 December 2021 Biennial Update to the Haddam Neck Plant License Termination Plan ML22075A2382021-12-0101 December 2021 Biennial Update to the Haddam Neck Plant Updated Final Safety Analysis Report CY-21-014, Independent Spent Fuel Storage Installation - Adoption of Amendment 8 of NAC-MPC Certificate of Compliance No. 72-1025 and Canister Registration2021-11-18018 November 2021 Independent Spent Fuel Storage Installation - Adoption of Amendment 8 of NAC-MPC Certificate of Compliance No. 72-1025 and Canister Registration IR 05000213/20210012021-10-26026 October 2021 Connecticut Yankee Atomic Power Company - NRC Independent Spent Fuel Storage Installation Inspection Report Nos. 07200039/2021001 and 05000213/2021001 ML21144A2512021-04-13013 April 2021 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2020 CY-21-006, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-21-005, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report CY-21-004, Independent Spent Fuel Storage Installation - Property Insurance Coverage2021-01-27027 January 2021 Independent Spent Fuel Storage Installation - Property Insurance Coverage CY-21-003, Independent Spent Fuel Storage Installation Nuclear Liability Insurance Coverage2021-01-27027 January 2021 Independent Spent Fuel Storage Installation Nuclear Liability Insurance Coverage ML21012A3192021-01-13013 January 2021 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan IR 07200039/20204012020-11-20020 November 2020 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Report 07200039/2020401, Without Enclosure (Public - Cover Letter Only) ML20150A3352020-06-19019 June 2020 COVID-19 Exemption for Haddam Neck CY-20-011, Independent Spent Fuel Storage Installation - Request for a Temporary Exemption from 10 CFR 73, Appendix B, Section Le and 10 CFR 73.55(r) Annual Physical Requalification Requirement2020-05-14014 May 2020 Independent Spent Fuel Storage Installation - Request for a Temporary Exemption from 10 CFR 73, Appendix B, Section Le and 10 CFR 73.55(r) Annual Physical Requalification Requirement ML20143A0972020-04-16016 April 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2019 CY-20-007, Independent Spent Fuel Storage Installation - Formal Announcement of New Tsfst Manager2020-03-31031 March 2020 Independent Spent Fuel Storage Installation - Formal Announcement of New Tsfst Manager CY-20-004, Independent Spent Fuel Storage Installation - Funding Report for Managing Irradiated Fuel and GTCC Waste2020-03-17017 March 2020 Independent Spent Fuel Storage Installation - Funding Report for Managing Irradiated Fuel and GTCC Waste CY-20-003, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2020-03-12012 March 2020 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report CY-20-002, Independent Spent Fuel Storage Installation, Letter Notifying NRC the Amount of Property Insurance Coverage in Force for 20202020-01-22022 January 2020 Independent Spent Fuel Storage Installation, Letter Notifying NRC the Amount of Property Insurance Coverage in Force for 2020 ML20015A5262020-01-15015 January 2020 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML19269C4642019-10-11011 October 2019 Letter to B. Mitchell Exemption from 10 CFR 72.212 and 72.214 for Dry Spent Fuel Storage Activities - Haddam Neck Plant Independent Spent Fuel Storage Installation CY-19-014, Independent Spent Fuel Storage Installation - Formal Announcement of ISFSI Manager'S Return2019-06-0505 June 2019 Independent Spent Fuel Storage Installation - Formal Announcement of ISFSI Manager'S Return CY-19-012, Independent Spent Fuel Storage Installation - 2018 Individual Monitoring NRC Form 5 Report2019-04-23023 April 2019 Independent Spent Fuel Storage Installation - 2018 Individual Monitoring NRC Form 5 Report ML19070A0332019-02-20020 February 2019 Letter to C. Pizzella Nuclear Regulatory Commission'S Analysis of Connecticut Yankee Atomic Power Company'S Initial and Updated Decommissioning Funding Plans for the Haddam Neck Plant Independent Spent Fuel Storage Installation CY-18-021, Connecticut Yankee Atomic Power Company Haddam Neck Plant Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan2018-12-10010 December 2018 Connecticut Yankee Atomic Power Company Haddam Neck Plant Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan IR 05000213/20180012018-05-31031 May 2018 NRC Independent Spent Fuel Storage Installation Inspection Report Nos. 07200039/2018001 and 05000213/2018001, Connecticut Yankee Atomic Power Company, East Hampton, Connecticut Site IR 07200039/20184012018-05-17017 May 2018 Connecticut Yankee Atomic Power Company Independent Spent Fuel Storage Security Inspection Report No. 07200039/2018401 - (Cover Letter Only) CY-18-004, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2018-03-0505 March 2018 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report 2024-08-27
[Table view] |
Text
Connecticut Yankee Atomic Power Company Date of Distribution: 10-4-04 Notice of Receipt of Plant Procedure License Terminiation Plan (LTP)
Change No.: 04-03 To: NRC HQ Office (original)
Washington, DC Copy No.:
Copy # UNCONTROLLED Please revise your controlled copy per instructions below:
INSERT: the supplemental distribution of revision 2 according to the directions provided ATTACH:
REMOVE:
REPLACE I have read and am aware of the provisions of the above listed documents.This acknowledges receipt of the revisions listed above. In addition, all superseded pages have been removed and destroyed.
Signature: Date:
Please Return This Sheet to the Administrative Office, Connecticut Yankee 362 Injun Hollow Road, East Hampton, CT 06424 Within Thirty (30) Days. 40o1 Rceference: (Emergency Plan Procedures) ACP 12-6.1 IOCFRS0.4 (a) (5) Rev. 20
Haddam Neck Plant License Termination Plan Supplemental Distribution of Revision 2, page 2-24 Insert Instruction for Page 2-24 Memo RACY-04-086 Please revise your controlled copy per instruction below:
I Remove Page(s) I Effective Date Insert Page(s) Effective Date None Insert Page 2-24 August 2004 after Page 2-23
Haddam Neck Plant License Termination Plan Penetration Building The Penetration Building includes the Terry Turbine Building. The building has three basic levels. The lower level room contains the steam-driven auxiliary feedwater pumps and feedwater piping. The middle level room contains atmospheric main steam dump valves encased by vented metal doors and walls. The upper level room contains main steam stop valves and an outside catwalk that extends to the Service Building located directly above main steam and feedwater transfer piping. The upper level also serves as the alternate access Health Physics control point to the Reactor Containment Building via an opening cut through the Reactor Containment Building wall. Reviews of routine surveys from 1998 and 1999 indicate no detectable contamination activity on smears taken from surfaces in the Penetration Building.
The Penetration Building is being demolished to 4 feet below grade. The waste materials will be sent offsite for disposal.
Administration Building The Administration Building is located outside of the radiologically controlled area, contained no radioactive systems or materials, and has had an ongoing documented history of being a clean area. With the exception of the auxiliary boiler heating system, this building does not contain interrelated systems that provide the potential for being cross-contaminated with radioactive materials under normal operating conditions.
The Administration Building is being demolished to 4 ft below grade. The waste materials will be sent offsite for disposal.
Shutdown Auxiliary Feed Pump House The Shutdown Auxiliary Feed Pump House contains a pump, connected to the above-ground Demineralized Water Storage Tank. This building is an independent structure with outer aluminum siding, inner sheetrock walls, slightly tapered sheet metal roof, asphalt floor, building exhaust ventilation, heat traced piping, electrical control panels/wiring and a concrete support base beneath the pump.
No significant radiological events have been identified that affect this area. The most probable mechanism for affecting this building with radioactive material is by transfer of loose surface contamination from personnel or equipment.
The Shutdown Auxiliary Feed Pump House is being demolished to 4 feet below grade. The waste materials will be sent offsite for disposal.
August 2004 2-24 Rev. 2