ML042880458

From kanterella
Jump to navigation Jump to search

Technical Specification Pages Re one-time Extension of Containment Type a Leak Test Interval
ML042880458
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 10/13/2004
From:
NRC/NRR/DLPM
To:
Banerjee M, NRR/DLPM, 415-2277
Shared Package
ml042520436 List:
References
TAC MC1796, TAC MC1797
Download: ML042880458 (2)


Text

Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.11 Safety Function Determination Pronram (SFDP) (continued)

b. A loss of safety function exists when, assuming no concurrent single failure, and assuming no concurrent loss of offsite power or loss of onsite diesel generators), a safety function assumed in the accident analysis cannot be performed. For the purpose of this program, a loss of safety function may exist when a support system is inoperable, and:
1. A required system redundant to system(s) supported by the inoperable support system is also inoperable; or
2. A required system redundant to system(s) in turn supported by the inoperable supported system is also inoperable; or
3. A required system redundant to support system(s) for the supported systems described in b.1 and b.2 above is also inoperable.
c. The SFDP identifies where a loss of safety function exists.

If a loss of safety function is determined to exist by this program, the appropriate Conditions and Required Actions of the LCO in which the loss of safety function exists are required to be entered. When a loss of safety function is caused by the inoperability of a single Technical Specification support system, 'the appropriate Conditions and Required Actions to enter are those of the support system.

5.5.12 Primary Containment Leakage Rate Testing Program

a. This program shall establish the leakage testing of the primary containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option 8, as modified by approved exemption. This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Testing Program," dated September 1995, as modified by the following exceptions:
1. NEI 94 1995, Section 9.2.3: The first Unit 2 Type A test performed after the February 28, 1996, Type A test shall be performed no later than February 27, 2011.

(continued)

Dresden 2 and 3 5.5-11 Amendment No.210/202

Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.12 Primary Containment Leakage Rate Testing Program (continued)

2. NEI 94 1995, Section 9.2.3: The first Unit 3 Type A test performed after the July 14, 1994, Type A test shall be performed no later than July 13, 2009.
b. The peak calculated primary containment internal pressure for the design basis loss of coolant accident, Pa, is 43.9 psig.
c. The maximum allowable primary containment leakage rate, La, at Pa, is 1.6% of primary containment air weight per day.
d. Leakage rate acceptance criteria are:
1. Primary containment overall leakage rate acceptance criterion is < 1.0 La. During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are s 0.60 La for the combined Type B and Type C tests, and < 0.75 La for Type A tests.
2. Air lock testing acceptance criteria is the overall air lock leakage rate is < 0.05 La when tested at 2 Pa.
e. The provisions of SR 3.0.3 are applicable to the Primary Containment Leakage Rate Testing Program.

5.5.13 Battery Monitoring and Maintenance Program This Program provides for restoration and maintenance, based on the recommendations of IEEE Standard 450-1995, "IEEE Recommended Practice for Maintenance, Testing, and Replacement of Vented Lead-Acid Batteries for Stationary Applications," including the following:

a. Actions to restore battery cells with float voltage

< 2.13 V, and

b. Actions to equalize and test battery cells that had been discovered with electrolyte level below the minimum established design limit.

Dresden 2 and 3 5.5-12 Amendment No. 210/202