Category:Letter
MONTHYEARIR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000318/LER-2023-004, Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-16016 January 2024 Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-002, Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-0808 January 2024 Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 ML23318A4722023-11-14014 November 2023 Supplement to License Amendment Request to Adopt TSTF-59-A ML23317A1032023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23310A0442023-11-0707 November 2023 Project Manager Assignment IR 05000317/20230402023-11-0202 November 2023 95001 Supplemental Inspection Report 05000317/2023040 and Follow-Up Assessment Letter IR 05000317/20230032023-11-0101 November 2023 Integrated Inspection Report 05000317/2023003 and 05000318/2023003 IR 05000317/20230902023-10-26026 October 2023 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317/2023090 ML23289A1202023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23279A1202023-10-0606 October 2023 Response to NRC Inspection Report and Preliminary White Finding IR 05000317/20230502023-09-29029 September 2023 Special Inspection Report 05000317/2023050 and Preliminary White Finding and Apparent Violation ML23272A1032023-09-29029 September 2023 Condition Prohibited by Technical Specifications Due to Inoperable Nuclear Instrumentation at Very Low Power IR 05000317/20234012023-09-18018 September 2023 Cyber Security Inspection Report 05000317/2023401 and 05000318/2023401 ML23254A0012023-09-0505 September 2023 Registration of Use of Casks to Store Spent Fuel IR 05000317/20230052023-08-31031 August 2023 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2023005 and 05000318/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23241A8412023-08-29029 August 2023 Response to Request for Additional Information - Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping ML23240A3872023-08-28028 August 2023 Senior Reactor and Reactor Operator Initial License Examinations ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration ML23219A1662023-08-16016 August 2023 Request for Additional Information Regarding Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping (EPID: L-2023-LLR-0006) - Non-proprietary ML23228A1002023-08-15015 August 2023 Notification of Readiness for NRC 95001 Inspection ML23188A0402023-08-0808 August 2023 Issuance of Amendment Nos. 346 and 324 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML23214A1572023-08-0707 August 2023 Correction to the Renewed Facility Operating License Page 3 in Amendment No 345 IR 05000317/20230022023-08-0303 August 2023 Integrated Inspection Report 05000317/2023002 ML23188A0512023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 336 and 314 ML23186A0372023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 340 and 318 IR 05000317/20233012023-07-12012 July 2023 Initial Operator Licensing Examination Report 05000317/2023301 and 05000318/2023301 IR 05000317/20230122023-07-10010 July 2023 Commercial Grade Dedication Report 05000317/2023012 and 05000318/2023012 ML23180A2362023-06-29029 June 2023 Correction of Errors on Technical Specification Pages RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators ML23156A6752023-06-20020 June 2023 Request for Withholding Information from Public Disclosure for Proposed Alternative to the Requirements for Repair/Replacement of Saltwater System Buried Piping 2024-02-01
[Table view] Category:Licensee 30-Day Written Event Report
MONTHYEARML19045A2422019-02-13013 February 2019 Reactor Vessel Level Monitoring System Special Report ML14114A5462014-04-23023 April 2014 CFR 50.46 30-day Report for Changes to the Emergency Core Cooling System Performance Analysis ML14080A3072014-03-20020 March 2014 10 CFR 50.46 30-day Report and Annual Report for Changes to the Emergency Core Cooling System Performance Analysis ML13115A2792013-04-22022 April 2013 10 CFR 50.46 30-day Report and Annual Report for Changes to the Emergency Core Cooling System Performance Analysis ML1212203062012-04-30030 April 2012 CFR 50.46 30-day Report and Annual Report for Changes to the Emergency Core Cooling System Performance Analysis ML12094A1002012-03-29029 March 2012 Submittal of Containment Water Level Indication Special Report ML12024A3912012-01-19019 January 2012 CFR 50.46 30-day Report for Changes to the Emergency Core Cooling System Performance Analysis ML1006105262010-02-22022 February 2010 LER Calvert Cliffs, Special Report: Noncompliance with Effluent Limitations ML0818206982008-06-30030 June 2008 Containment Tendon Surveillance - 30 Day Report ML0510200112005-04-0606 April 2005 10 CFR 50.46 30-Day Report for Changes to the Plant Emergency Core Cooling System Performance Analysis ML0424501002004-08-25025 August 2004 Units I & 2 - Special Report: National Pollutant Discharge Elimination System Discharge Permit 02-DP-01 87 2019-02-13
[Table view] Category:Written Event Report (30 or 60 day)
MONTHYEARML21022A4192021-01-22022 January 2021 Reactor Vessel Level Monitoring System and Wide Range Pressurizer Pressure System Special Report ML0510200112005-04-0606 April 2005 10 CFR 50.46 30-Day Report for Changes to the Plant Emergency Core Cooling System Performance Analysis ML0424501002004-08-25025 August 2004 Units I & 2 - Special Report: National Pollutant Discharge Elimination System Discharge Permit 02-DP-01 87 2021-01-22
[Table view] |
Text
4 X Kevin J. Nietmann 1650 Calvert Cliffs Parkway Plant General Manager Lusby, Maryland 20657 Calvert Cliffs Nuclear Power Plant 410 495-4101 Constellation Generation Group, LLC 410 495-4787 Fax Constellation Energy Group August 25, 2004 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION: Document Control Desk
SUBJECT:
Calvert Cliffs Nuclear Power Plant Unit Nos. I & 2; Docket Nos. 50-317 & 50-318 Special Report: National Pollutant Discharge Elimination System Discharge Permit 02-DP-01 87 Calvert Cliffs Nuclear Power Plant
REFERENCE:
(a) Calvert Cliffs Nuclear Power Plant, Appendix B, Environmental Protection Plan (Non-Radiological) Technical Specifications, Section 3.2.1 In accordance with Reference (a), Attachment (1), provides a copy of a Calvert Cliffs Nuclear Power Plant Report to the Maryland Department of the Environment. This report documents the discovery of a lack of monitoring for the auxiliary boiler blowdown effluent (monitoring point 103 A) between June 1, 2004, when the permit requirement became effective, and July 30, 2004, when the lack of monitoring was discovered.
The cause of the unanticipated discharge was determined to be an incorrect pump line-up (automatic vs.
manual). Revisions to site procedures will ensure compliance with the applicable monitoring frequency and analysis type.
Should you have questions regarding this matter, we will be pleased to discuss them with you.
Very truly yours for Kevin J. Nietmann Plant General Manager KJN/JTJ/bjd
Attachment:
Letter to Maryland Department of the Environment, dated August 4, 2004, NPDES Discharge Permit 02-DP-0187, Calvert Cliffs Nuclear Power Plant cc: J. Petro, Esquire S. J. Collins, NRC J. E. Silberg, Esquire Resident Inspector, NRC R. V. Guzman, NRC R. l. McLean, DNR I-,--
-1 e 2-.S-
ATTACHMENT (1)
Letter to Maryland Department of the Environment, dated August 4, 2004, NPDES Discharge Permit 02-DP-0187, Calvert Cliffs Nuclear Power Plant Calvert Cliffs Nuclear Power Plant, Inc.
August 25, 2004
1650 Calvert Cliffs Parkway Lusby, Maryland 20657 Constellation Calvert Cliffs Nuclear Power Plant A Member of the Constellation Energy Group August 4, 2004 Mr. Jack Bowen Maryland Department of the Environment Water Management Administration 1800 Washington Boulevard Baltimore, Maryland 21230 RE: NPDES Discharge Permit 02-DP-0187 Calvert Cliffs Nuclear Power Plant On July 30, 2004 Calvert Cliffs Nuclear Power Plant personnel identified that the auxiliary boiler blowdown effluent (Monitoring point 103 A) had been discharged Intermittently from the CCNPP site in Lusby, MD without monitoring as required by NPDES permit 02-DP-0187. This permit requires flow, total suspended solids, and oil and grease monitoring to be performed monthly, with pH to be monitored during each discharge from monitoring point 103 A. No monitoring was performed between June 1, 2004 when the permit requirement became effective, and July 30, 2004, when the lack of monitoring was discovered.
Approximately 5000 gallons of auxiliary boiler blowdown effluent was discharged to the Chesapeake Bay between June 1, 2004 and July 30, 2004. When plant staff identified that the discharges had occurred, the auxiliary boiler blowdown discharge was sampled for pH, total suspended solids, and oil and grease. Ail values .were within permit limits; oil and grease and total suspended solids results were both less than detectable concentrations. Based on the relatively small discharge volume and the satisfactory analysis results the impact of this discharge on public health and the waters of the state is negligible.
The cause of the unanticipated discharge was the auxiliary boiler blowdown tank discharge pump controls were in the 'automatic' positions when they should have been in the 'manual' position. This caused the tank to discharge whenever a set volume was reached without site personnel being aware of the discharge. Upon discovery the controls were immediately placed in the 'manual' position. A note has been placed on the controls to ensure they are not put back into the 'automatic' mode. Site procedures are being revised to require the auxiliary boiler blowdown tank discharge pump controls be maintained in the 'manual' position and to monitor each discharge as required by the permit.
If you have any questions, please contact Brenda Nuse at (410) 495-4913.
Sincerely gl-rj Kevin J. Nietmann Plant General Manager KJN/BDN cc: B.D. Nuse T.G. Ringger (CGG-ES)
. I .. .: