Mid-Cycle Performance Review and Inspection Plan - Millstone Power Station Unit 2 and Unit 3
ML042440216
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 08/30/2004
From: Ronald Bellamy
NRC/RGN-I/DRP/PB6
To: Christian D
Dominion Resources
bellamy r r
References
Download: ML042440216 (7)


Text

August 30, 2004 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Resources 5000 Dominion Boulevard Glenn Allen, VA 23060-6711

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - MILLSTONE POWER STATION UNIT 2 AND UNIT 3

Dear Mr. Christian:

On August 4, 2004, the NRC staff completed its mid-cycle plant performance assessment of Millstone Power Station Unit 2 and Unit 3. The mid-cycle review for Millstone involved the participation of all technical divisions in evaluating performance for the first half of the calendar year 2004 assessment cycle. The process included a review of performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.

This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as "Proprietary Information in accordance with 10 CFR 2.390(d)(1)" will include the physical protection review and resultant inspection plan.

Plant performance at Unit 2 for the most recent quarter was within the Regulatory Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and the PI for Unplanned Scrams per 7000 Critical Hours exceeding the Green/White threshold. This PI first crossed the Green/White threshold during the first quarter of 2004 due to two unplanned scrams during the fourth quarter of 2003 and two unplanned scrams during the first quarter of 2004. The NRC staff sent an Assessment Follow-Up Letter, dated May 5, 2004, to inform you of your transition into the Regulatory Response Column of NRCs Action Matrix. A Supplemental Inspection is currently in progress to review your actions related to crossing this PI threshold.

Plant performance at Unit 3 for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct only reactor oversight process (ROP) baseline inspections at your facility through March 31, 2006.

The enclosed inspection plan details the inspections scheduled through March 31, 2006. The plan contains an inspection using Temporary Instruction (TI) 2515/159 "Review of Generic Letter 89-13, "Service Water System Problems Affecting Safety-Related Equipment." This TI is in

Mr. Dave A. Christian 2

response to the Davis-Besse Reactor Vessel Head Degradation Lessons-Learned Task Force and is being performed at a sampling of nuclear power plants across the country. The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last twelve months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5200 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Ronald R. Bellamy, Chief Projects Branch 6 Division of Reactor Projects Docket Nos.

50-336, 50-423 License Nos.

DPR-65, NPF-49

Enclosure:

Millstone Inspection/Activity Plan

Mr. Dave A. Christian 3

cc w/encl:

J. A. Price, Site Vice President - Millstone C. L. Funderburk, Director, Nuclear Licensing and Operations Support D. W. Dodson, Supervisor, Station Licensing L. M. Cuoco, Senior Counsel C. Brinkman, Manager, Washington Nuclear Operations W. Meinert, Massachusetts Municipal Wholesale Electric Company First Selectmen, Town of Waterford V. Juliano, Waterford Library J. Markowicz, Co-Chair, NEAC E. Woollacott, Co-Chair, NEAC E. Wilds, Director, State of Connecticut SLO Designee J. Buckingham, Department of Public Utility Control G. Proisio, Suffolk County Planning Dept.

R. Shadis, New England Coalition Staff G. Winslow, Citizens Regulatory Commission (CRC)

S. Comley, We The People D. Katz, Citizens Awareness Network (CAN)

R. Bassilakis, CAN J. M. Block, Attorney, CAN

Mr. Dave A. Christian 4

Distribution w/encl: VIA E-MAIL:

S. Collins, RA J. Wiggins, DRA C. Miller, OEDO J. Clifford, NRR V. Nerses, PM, NRR S. Wall, Backup, NRR S. Schneider, Senior Resident Inspector E. Bartels, Resident OA R. Bellamy, RI K. Jenison, RI T. Madden, OCA C. ODaniell, DRP D. Screnci, PAO W. Lanning, DRS R. Crlenjak, DRS J. Rogge, DRS L. Doerflein, DRS R. Conte, DRS R. Lorson, DRS J. White, DRS Region I Docket Room (with concurrences)

RidsNrrDipmlipb DOCUMENT NAME: S:\\ROP5 Mid-Cycle Review\\2004 Mid-Cycle Letters\\Millstone ROP-5 Mid-Cycle Letter FINAL.wpd After declaring this document An Official Agency Record it will/will not be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME Sschneider/KMJ for RBellamy/RRB DATE 08/26/04 08/30/04 OFFICIAL RECORD COPY

Millstone Inspection / Activity Plan 07/01/2004 - 03/31/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 3 08/30/2004 10:36:38 Report 22 1

40801

- SELF ASSESSMENT AND CORRECTIVE ACTION Other Routine 01/10/2004 07/31/2004 Self-Assessment, Auditing, And Corrective Action At Permanently Shutdown Reactors IP 40801 1

1 83750

- OCCUPATIONAL RADIATION EXPOSURE Other Routine 01/10/2004 07/31/2004 Occupational Radiation Exposure IP 83750 1

4 7/19 EXM

- UNIT3 OPERATOR LICENSING INITIAL EXAM Not Applicable 06/28/2004 07/02/2004 MILLSTONE UNIT 3 INITIAL EXAM (5/1-5/04)

U01521 3

Not Applicable 07/19/2004 07/23/2004 MILLSTONE UNIT 3 INITIAL EXAM (5/1-5/04)

U01521 3

1 40801

- SELF ASSESSMENT AND CORRECTIVE ACTION Other Routine 06/01/2004 07/31/2004 Self-Assessment, Auditing, And Corrective Action At Permanently Shutdown Reactors IP 40801 1

1 62801

- MAINTENANCE AND SURVEILLANCE Other Routine 06/01/2004 07/31/2004 Organization, Management, And Cost Controls At Permanently Shutdown Reactors IP 36801 1

1 7112202

- PUB RAD SAFETY - RADWASTE Baseline Inspections 06/28/2004 07/02/2004 Radioactive Material Processing and Transportation IP 7112202 2, 3 1

95001

- WHITE PI - UNPLANNED SCRAMS Supplemental Program 08/23/2004 08/27/2004 Supplemental Inspection For One Or Two White Inputs In A Strategic Performance Area IP 95001 2

4 7111105T

- TRIENNIAL FIRE PROTECTION INSPECTION-U3 Baseline Inspections 07/26/2004 07/30/2004 Fire Protection IP 7111105T 3

Baseline Inspections 08/09/2004 08/13/2004 Fire Protection IP 7111105T 3

6 71002

- LICENSE RENEWAL - SCOPING License Renewal Inspectio 07/26/2004 07/30/2004 License Renewal Inspection IP 71002 2, 3 3

7111111B

- LO REQUAL PROGRAM UNIT 2 Baseline Inspections 10/04/2004 10/08/2004 Licensed Operator Requalification Program IP 7111111B 2

4 7111111B

- LO REQUAL INSPECTION UNIT 3 Baseline Inspections 10/25/2004 10/29/2004 Licensed Operator Requalification Program IP 7111111B 3

1 7111112B

- MAINTENANCE RULE Baseline Inspections 08/16/2004 08/20/2004 Maintenance Effectiveness IP 7111112B 2, 3 1

7111107B

- HEAT SINK U2 Baseline Inspections 08/30/2004 09/03/2004 Heat Sink Performance IP 7111107B 2

4 TI-159

- DAVIS BESSE ACTION-GL 89-13 REVIEW Safety Issues 08/30/2004 09/03/2004 Review of Generic Letter 89-13: Service Water System Problems Affecting Safety-Related Equipment IP 2515/159 2

7 7111401

- EXERCISE EVALUATION & EP PI VERIFICATION Baseline Inspections 09/13/2004 09/17/2004 Exercise Evaluation IP 7111401 2, 3 Baseline Inspections 09/13/2004 09/17/2004 Performance Indicator Verification IP 71151 2, 3 1

7112103

- OCC RAD SAFETY - INSTRUMENTS Baseline Inspections 09/13/2004 09/17/2004 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 2, 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Millstone Inspection / Activity Plan 07/01/2004 - 03/31/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 3 08/30/2004 10:36:38 Report 22 7

71002

- LICENSE RENEWAL - AGING MGMT License Renewal Inspectio 09/13/2004 09/17/2004 License Renewal Inspection IP 71002 2, 3 License Renewal Inspectio 09/27/2004 10/01/2004 License Renewal Inspection IP 71002 2, 3 3

3/21 EXM

- UNIT 2 OPERATOR LICENSING INITIAL EXAM Not Applicable 02/14/2005 02/18/2005 MILLSTONE, UNIT 2 INITIAL EXAM (12/1-5/04)

U01535 2

Not Applicable 03/21/2005 03/25/2005 MILLSTONE, UNIT 2 INITIAL EXAM (12/1-5/04)

U01535 2

1 7112203

- PUB RAD SAFETY - REMP Baseline Inspections 10/25/2004 10/29/2004 Radiological Environmental Monitoring Program IP 7112203 2, 3 6

7111121

- U2 SSDI Baseline Inspections 11/01/2004 11/05/2004 Safety System Design and Performance Capability IP 7111121 2

Baseline Inspections 11/15/2004 11/19/2004 Safety System Design and Performance Capability IP 7111121 2

1 7111107B

- HEAT SINK Baseline Inspections 02/07/2005 02/11/2005 Heat Sink Performance IP 7111107B 3

3 7111108P

- INSERVICE INSPECTION - U2 Baseline Inspections 04/11/2005 04/15/2005 Inservice Inspection Activities - PWR IP 7111108P 2

1 7112102

- OCC RAD SAFETY - ALARA Baseline Inspections 05/09/2005 05/13/2005 ALARA Planning and Controls IP 7112102 2

3 71111.05

- TRIENNIAL FIRE PROTECTION INSPECTION-U2 Baseline Inspections 05/23/2005 05/27/2005 Fire Protection IP 7111105T 2

Baseline Inspections 06/06/2005 06/10/2005 Fire Protection IP 7111105T 2

1 7112102

- OCC RAD SAFETY - ALARA Baseline Inspections 08/08/2005 08/12/2005 ALARA Planning and Controls IP 7112102 2, 3 1

7112201

- PUB RAD SAFETY - RETS Baseline Inspections 08/08/2005 08/12/2005 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 2, 3 1

7111117B

- MODS & 50.59 U2/3 Baseline Inspections 08/15/2005 08/19/2005 Evaluation of Changes, Tests, or Experiments IP 7111102 2, 3 Baseline Inspections 08/15/2005 08/19/2005 Permanent Plant Modifications IP 7111117B 2, 3 6

7111121

- SSDI - U3 Baseline Inspections 08/29/2005 09/02/2005 Safety System Design and Performance Capability IP 7111121 3

Baseline Inspections 09/12/2005 09/16/2005 Safety System Design and Performance Capability IP 7111121 3

1 7112101

- OCC RAD SAFETY - ACCESS Baseline Inspections 09/05/2005 09/09/2005 Access Control to Radiologically Significant Areas IP 7112101 2, 3 1

71114

- EP PROGRAM INSP & PI VERIFICATION Baseline Inspections 09/12/2005 09/12/2005 Emergency Action Level and Emergency Plan Changes IP 7111404 2, 3 Baseline Inspections 09/12/2005 09/12/2005 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 2, 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Millstone Inspection / Activity Plan 07/01/2004 - 03/31/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 3 of 3 08/30/2004 10:36:38 Report 22 1

71114

- EP PROGRAM INSP & PI VERIFICATION Baseline Inspections 09/12/2005 09/12/2005 Performance Indicator Verification IP 71151 2, 3 Baseline Inspections 09/12/2005 09/16/2005 Alert and Notification System Testing IP 7111402 2, 3 Baseline Inspections 09/12/2005 09/16/2005 Emergency Response Organization Augmentation Testing IP 7111403 2, 3 1

7111108P

- INSERVICE INSPECTION - U3 Baseline Inspections 10/17/2005 10/21/2005 Inservice Inspection Activities - PWR IP 7111108P 3

2 7111111B

- LO REQUAL PROGRAM INPSECTION Baseline Inspections 11/07/2005 11/11/2005 Licensed Operator Requalification Program IP 7111111B 3

1 71152B

- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections 02/13/2006 02/17/2006 Identification and Resolution of Problems IP 71152B 2, 3 Baseline Inspections 02/27/2006 03/03/2006 Identification and Resolution of Problems IP 71152B 2, 3 1

7112101

- OCC RAD SAFETY Baseline Inspections 02/27/2006 03/03/2006 Access Control to Radiologically Significant Areas IP 7112101 2, 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.