FPL Florida Power & Light Company, 6501 S. Ocean Drive, Jensen Beach, FL 34957 August 10, 2004 L-2004-182 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re:
St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 Monthly Operating Report Pursuant to Technical Specification 6.9.1.6, and the guidance of Generic Letter 97-02, attached are the July 2004 Operating Data Report, Summary of Operating Experience Report, and Unit Shutdowns for St. Lucie Units 1 and 2.
Please contact us should there be any questions regarding this information.
Very truly yours, WJ/KWF Attachment an FPL Group company
L-2004-182 Attachment Page 1 of 2 OPERATING DATA REPORT DOCKET NO.
50 UNIT NAME St DATE Au COMPLETED BY K.
TELEPHONE (77 REPORTING PERIOD:
-335
. Lucie 1 gust 05, 2004 R. Boller
- 72) 467-7465 July 2004
- 1.
Design Electrical Rating
- 2. Maximum Dependable Capacity (MWe.Net) 830.00 839.00
- 3. Number of Hours the Reactor was Critical
- 4. Number of Hours Generator On-line
- 5. Reserve Shutdown Hours
- 6.
Net Electrical Energy Generated (MWHrs)
This Month 744.00 744.00 0.00 633,723.00 Yr-to-Date 4,314.30 4,271.40 0.00 3,602,937.00 Cumulative 197,858.30 195,981.70 0.00 160,703,884.0 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action S: Scheduled (Hours)
Down 2 Comments
SUMMARY
- St. Lucie Unit I operated in Mode 1 for the entire month of July. In accordance with Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or safety valves during the report period.
I 2
Reason:
A Equipment Failure (Explain)
B Maintenance or Test C
Refueling D
Regulatory Restriction E
Operator Training & License Examination F
Administration G
Operational Error (Explain)
H Other (Explain)
Method:
I Manual 2
Manual Trip/Scram 3
Automatic Trip/Scram 4
Continuation 5
Other (Explain)
L-2004-1 82 Attachment Page 2 of 2 OPERATING DATA REPORT DOCKET NO.
50 UNIT NAME St DATE Au COMPLETED BY K.
TELEPHONE
(_
REPORTING PERIOD:
-389
. Lucie 2 gust 05,2004 R. Boller
- 72) 467-7465 July 2004
- 1. Design Electrical Rating
- 2. Maximum Dependable Capacity (MWe-Net) 830.00 839.00
- 3. Number of Hours the Reactor was Critical
- 4. Number of Hours Generator On-line
- 5. Reserve Shutdown Hours
- 6. Net Electrical Energy Generated (MWHrs)
This Month 744.00 744.00 0.00 627,852.00 Yr-to-Date 5,111.00 5,111.00 0.00 4,329,792.00 Cumulative 161,147.57 159,233.47 0.00 131,376,768.0 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No.
Date 5: Scheduled (Hours)
Reason 1 Down 2 Comments
SUMMARY
- St. Lucie Unit 2 operated in Mode 1 for the entire month of July. In accordance with Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or safety valves during the report period.
1 2
Reason:
A Equipment Failure (Explain)
B Maintenance or Test C
Refueling D
Regulatory Restriction E
Operator Training & License Examination F Administration G
Operational Error (Explain)
H Other (Explain)
Method:
I Manual 2
Manual Trip/Scram 3
Automatic Trip/Scram 4
Continuation 5
Other (Explain)