From: David Pelton
NRC Region 1
To: Joseph Furia
NRC Region 1
References
FOIA/PA-2004-0267
Download: ML042330090 (1)


Text

I I

-Pelton, David From:

Pelton, David, Sent:

Thursday, July 31, 2003 9:24 AM To:

'JTF@NRC.GOV'

Subject:

FW: Clean Step Off Pad Transition

-- Original Message---

From: Morgan, Mike Sent: Wednesday, July 30, 2003 15:36 To: VTY - All Users

Subject:

Clean Step Off Pad Transition To all VY Employees who access the Radiation Controlled Area On Thursday August 7 Vermont Yankee will begin replacing our current contaminated step-off pads with clean side step-off pads to align ourselves with rest of the industry. The new step off pads will be white with black lettering. The replacement of the pads will be done in two steps to ease personnel with the transition. The following is the transition schedule for the step off pad implementation.

On August 7, clean step off pads will be placed adjacent to the existing contaminated step -

off pads at entrances to contaminated areas not behind locked high radiation doors.

On August 7, clean step off pads will be place at the entrances to contaminated areas in locked high radiation areas. To minimize radiation exposures, the contaminated step-off pad will be removed.

On August 29, all off the remaining contaminated step-off pads will be removed from the contaminated area exits.

Although the conversion to clean step - off pads is a big change at VY, the affect on your day to day visits to the RCA should be minimal. The sequence for removing your protective clothing at a clean step off pad is nearly identical to the ones use at contaminated pads so getting use to undressing at the new step - off pads should come quickly. To help you with the transition follow the link below to the RP Department Web site. Once there, click on the link for Removing Protective Clothing at a Clean Step Off Pad Tutorial Link and use your computer's mouse to see a power point presentation which illustrates the proper method of protective clothing removal.

If you have any question concerning the step off pad transition contact a member of RP Supervision.

httD:/hvww.vtv.enterov.com/Deoartments/Radttion Protection/

Sincerely, Supervisor, Radiation Control Entergy Vermont Yankee 1a

P0 Box 157 Vernon, Vermont 05354 mmorga3@entergy.com (802)258-5551 This e-mail and any of its attachments may contain Entergy Corporation proprietary information, which is privileged, confidential, or subject to copyright belonging to the Entergy Corporation family of Companies.

This e-mail is intended solely for the use of the individual or entity to which it is addressed.

If you are not the intended recipient of this e-mail, you are hereby notified that any dissemination, distribution, copying, or action taken in relation to the contents of and attachments to this e-mail is strictly prohibited and may be unlawful.

If you have received this e-mail in error, please notify the sender immediately and permanently delete the original and any copy of this e-mail and any printout. Thank You.

2