FENOC FirstEnergy Nuclear Operating Company Akron, Ohio 4430S Low W Myers 330-384-3733 Chief Operating Officer Fax: 330-384-3799 July 15, 2004 PY-CEI/NRR-2759L United States Nuclear Regulatory Commission Document Control Desk Washington, D.'C. 20555..
-Perry Nuclear Power Plant
-a Docket No. 50-440 Response to Regulatory Issue Summaries 2000-20, Importance of Industry Providing NRC Advance Notice of Intent'to Pursue License Renewal", and 2003-02, "Importance of Giving NRC Advance Notice of Intent to Pursue License Renewal" Ladies and Gentlemen:
The Nuclear Regulatory Commission (NRC) issued Regulatory Issue Summaries 2000-20 and 2003-02 to inform addressees of the importance of providing the NRC with advance notice of their plans for license renewal so the NRC staff can better plan and budget for the processing of renewal applications. This letter provides advance notification that the FirstEnergy Nuclear Operating Company plans to pursue license renewal for the Perry Nuclear Power Plant. It is anticipated that the license renewal application will be submitted in September 2010.
No regulatory commitments are contained within this letter. If you have questions or require additional information, please contact Mr. Vernon K. Higaki, Manager - Regulatory Affairs, at (440) 280-5294.
Very truly yours, cc:
NRC Prpject Manager
~*...
NRC Resident Inspector NRC Region IlIl
.