Presentation Slides from April 6, 2004, LTP Submittal Overview Meeting with Yankee Atomic Electric Company
ML041830113
Person / Time
Site: Yankee Rowe
Issue date: 04/06/2002
From:
Yankee Atomic Electric Co
To:
NRC/FSME
References
-RFPFR
Download: ML041830113 (16)


Text

Yankee Atomic Electric Company LTP Submittal Overview Meeting with USNRC April 6, 2004 1

Discussion Topics m Update of Decommissioning Progress m LTP-Related Submittals

- Hydrogeologic Report

  • Related Activities - 2004
  • Future Communications with NRC 2

Update of Decommissioning Progress During Operations I r

\\i 1

Currently 3

Update of Decommissioning m Building Demolition o Turbine Building Monolith o Waste Warehouse o Safe Shutdown Building

.1 o Fuel Transfer Enclosure o Plant Vent Stack Progress 4

Update of Decommissioning Activities i Cutting of the Metal Vapor Container I1 5

Timeline of LTP Activities f rS FSS (0undw03 ftg at Slte (512003)1 inabal Sd Sensitviy jCak Submitta J(W43 Section 6 Appendices 1(2I1012004)

I N RC LTP FodItkup Dose Modeling I m W20)

P

,Ioi c,

Rpt' Soil and bunading Vocupancy OvUL I

land Area Factors Caks (1/19/2004)

I Sep--02 Speclal Tqi' g(6/

2 0 03)I RC Dose Modellig Mtg Tech Rpt on Dose Integrtion Parameter 1(111122004)

I NRC Cal 1(3WA0)

VIoumretrc C~onorete Cale.

(3142004)

IGroundwater CompendiumI

(<5t19 2003)

I Ilnbrii Groundwater RptI P12=0n04)

I 6

Co I

License Termination Plan

  • General Information
  • Summary of Historical Site Assessment ii Identification of survey areas iD Initial classification of survey areas Li Radionuclides of interest L Known groundwater information L Areas of additional investigation
  • Subsurface areas
  • Groundwater
  • Remaining Decommissioning Activities and Remediation Plans 7

License Termination Plan (Con't)

  • Dose Modeling Methodology
  • Criteria, scenarios, and codes used
  • Calculations sent separately
  • Input/output details provided in appendices
  • Final Status Survey Methodology
  • Follows MARSSIM
  • Groundwater and subsurface considerations
  • Financial Information
  • Supplement to the Environmental Report 8

Dose Modeling Calculations

  • Calculations provided:
  • For soil and building surfaces:
  • Parameter sensitivity
  • Parameter values
  • DCGLs
  • Area Factors
  • For concrete:
  • Correlate residual radioactivity and dose
  • Establish DCGL corresponding to 0.5 mrem/yr

- LTP Section 6 Appendices Summarize Information from CaIcs (Inputs and Results) for Soil and Building Surfaces 9

Historical Site Assessment C Basis Document for Site Characterization and Survey Area Classification

  • Describes:

0 Operational history and impacts o Events and spills o Potential for subsurface contamination o Past remediation efforts o Underground systems

  • Summarizes:

o Historical sample data o Statistics on open land area data (SOF, mean, median, std dev)

  • Includes CD with Scanned References (Organized by Survey Area) 10

Hydrogeologic Report of 2003 Supplemental Investigaton

  • Supplements "3rd Quarter Interim Groundwater Report"
  • Summarizes Well Drilling Methods and Construction
  • Identifies Local Stratigraphy
  • Discusses Hydraulic Gradient and Groundwater Flow
  • Identifies Sample Analyses Performed
  • Gamma spec L Tritium and gross alpha/beta
  • Hard-to-detects (including transuranics)
  • Discusses Sample Analyses Results u Tritium only plant-related radionuclides identified
  • Provides Updated Tritium Plume Maps
  • Describes Three-Dimensional Investigation 11

Shallow Tritium Plume (Nov. 2003) 12

Intermediate Tritium Plume (Nov. 2003) 13

I Three-Dim-ensional Investigation D

D ifut r4 12M UMWNT IL f VIA NovV

'23 m Ca.OnRnT COCA)

(MMACAM DEWS 5

8nf 3U 5' S1lUU CONEMRA1N lox

.1E

~

ESAS0mG WONIT0iG FRL SW11, SATUMEW

=07 locoVONMNG IELLSINJG C

NOT DETECTED AT A DEEC1TC*

UNIT OF 20W pC H*o*QCMns frD. D' Jtwyk-0 i m 14 CQ L-

Related Activiti es - 2004

  • FSS Activities u Assembling FSS staff o Developing FSS plans and procedures o Considering methodology to survey excavations m Site Closure Project Plan
  • PCB Remediation of Sherman Reservoir
  • Continued Stakeholder and Community Outreach 15

Future Communications with NRC m Regular Meetings m Periodic Calls

  • Early Identification of Concerns
  • Path to Close Issues Before RAI Issuance 16