June 22, 2004 Mr. Dennis L. Koehl Site Vice-President Point Beach Nuclear Plant Nuclear Management Company, LLC 6590 Nuclear Road Two Rivers, WI 54241-9516

SUBJECT:

POINT BEACH NUCLEAR POWER PLANT - CHANGES TO PREVIOUSLY ANNOUNCED NRC INSPECTIONS

Dear Mr. Koehl:

On March 4, 2004, the NRC issued an annual assessment letter covering the period from January 1, 2003, to December 31, 2003. This letter contained a preliminary schedule of NRC inspections planned at that time from March 1, 2004, through September 30, 2005. As discussed in the March 4 annual assessment letter, Point Beach remained within the Multiple/Repetitive Degraded cornerstone column (column IV) of the NRC Action Matrix.

Because of the performance issues that resulted in Point Beach being in column IV of the Action Matrix, we planned on closely monitoring your actions to improve overall plant performance through normal and expanded baseline inspections and special inspections.

One of the regulatory areas of concern at Point Beach is the Emergency Preparedness program. As part of our monitoring of your improvement initiatives in the Emergency Preparedness area, we have planned for two expanded baseline inspections scheduled to be conducted on August 2 - 6 and September 20 - 24, 2004.

The scheduled dates of these inspections have been discussed with your staff. An overview of detailed inspection activities will be provided to you prior to the inspections. If you have questions regarding these inspections please contact me at (630) 829-9627.

D. Koehl In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Patrick L. Louden, Chief Projects Branch 7 Division of Reactor Projects Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc: F. Kuester, President and Chief Executive Officer, We Generation J. Cowan, Executive Vice President Chief Nuclear Officer D. Cooper, Senior Vice President, Group Operations J. McCarthy, Site Director of Operations D. Weaver, Nuclear Asset Manager Plant Manager Regulatory Affairs Manager Training Manager Site Assessment Manager Site Engineering Director Emergency Planning Manager J. Rogoff, Vice President, Counsel & Secretary K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin State Liaison Officer

DOCUMENT NAME: C:\ORPCheckout\FileNET\ML041740752.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII RIII NAME MKunowski KRiemer*SO for PLouden DATE 06/22/04 06/22/04 06/22/04 OFFICIAL RECORD COPY

D. Koehl ADAMS Distribution: