UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION RAS 7967 DOCKETED 06/21/04 ATOMIC SAFETY AND LICENSING BOARD SERVED 06/21/04 Before Administrative Judges:

Dr. Paul B. Abramson, Chairman Ann Marshall Young Dr. Richard F. Cole In the Matter of Docket Nos. 50-336-LR, 50-423-LR DOMINION NUCLEAR CONNECTICUT, INC. ASLBP No. 04-824-01-LR (Millstone Nuclear Power Station, Units 2 June 21, 2004 and 3)

ORDER (Initial Prehearing Conference Schedule)

In accord with the Licensing Boards June 8, 2004 Initial Prehearing Order, the participants are advised of the following information regarding the schedule for the initial prehearing conference in this proceeding:

Date: Wednesday, June 30, 2004 Starting Time: 9:00 a.m.

Location: Radisson Hotel New London 35 Governor Winthrop Boulevard New London, Connecticut The time for arguments by counsel in connection with the admissibility of the contentions of petitioner Connecticut Coalition Against Millstone (CCAM), which will be the principal focus of this prehearing conference, is allocated for each of Contentions I, II, and VI as follows:

CCAM: 10 minutes Dominion: 10 minutes NRC Staff: 5 minutes

and for each of Contentions III, IV, and V as follows:

CCAM: 20 minutes Dominion: 15 minutes NRC Staff: 10 minutes At the beginning of argument for each contention, CCAM will be asked to specify how much of its total allotted time it wishes to reserve for rebuttal.

In making their arguments, the participants should bear in mind that the Licensing Board will have read their pleadings. As such, they should focus their presentations on the critical points in controversy as those issues have emerged as a result of the various participant filings.

Additionally, the Board will consider at the prehearing conference all matters raised by the participants submissions filed prior to June 25, 2004, and will consider the record complete for its decision on CCAMs petition at the conclusion of this conference.

It is so ORDERED.

FOR THE ATOMIC SAFETY AND LICENSING BOARD1

/RA/

Dr. Paul B. Abramson, Chairman ADMINISTRATIVE JUDGE Rockville, Maryland June 21, 2004 1

Copies of this order were sent this date by internet e-mail transmission to counsel for (1) licensee Dominion Nuclear Connecticut, Inc.; (2) petitioner CCAM; and (3) the NRC Staff.

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )

)

DOMINION NUCLEAR ) Docket Nos. 50-336-LR and CONNECTICUT, INC. ) 50-423-LR

)

)

(Millstone Nuclear Power Station, )

Units 2 and 3) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing LB ORDER (INITIAL PREHEARING CONFERENCE SCHEDULE) have been served upon the following persons by U.S. mail, first class, or through NRC internal distribution.

Office of Commission Appellate Administrative Judge Adjudication Paul B. Abramson, Chair U.S. Nuclear Regulatory Commission Atomic Safety and Licensing Board Panel Washington, DC 20555-0001 Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Administrative Judge Administrative Judge Ann Marshall Young Richard F. Cole Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop - T-3 F23 Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 Catherine L. Marco, Esq. Nancy Burton, Esq.

Margaret J. Bupp, Esq. 147 Cross Highway Brooke D. Poole, Esq. Redding Ridge, CT 06876 Office of the General Counsel Mail Stop - O-15 D21 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

2 Docket Nos. 50-336/423-LR LB ORDER (INITIAL PREHEARING CONFERENCE SCHEDULE)

Lillian M. Cuoco, Esq. David R. Lewis, Esq.

Senior Counsel ShawPittman, LLP Dominion Resources Services, Inc. 2300 N Street, NW Rope Ferry Road Washington, DC 20037-1128 Waterford, CT 06385 Paul B. Eccard Robert A. Avena, Esq.

First Selectman, Town of Waterford Town Attorney for Waterford, CT 15 Rope Ferry Road Kepple, Morgan & Avena, P.C.

Waterford, CT 06385-2886 Box 3A Anguilla Park 20 South Anguilla Road Pawcatuck, CT 06379 Thomas V. Wagner Ralph Bunge AICP Planning Director NRC Proceedings Representative for Town of Waterford Waterford, CT 15 Rope Ferry Road 510 Carr Avenue Waterford, CT 06385 Rockville, MD 20850

[Original signed by Evangeline S. Ngbea]

Office of the Secretary of the Commission Dated at Rockville, Maryland, this 21st day of June 2004