ML041480285
| ML041480285 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 02/25/2004 |
| From: | Anthony Mendiola Office of Nuclear Reactor Regulation |
| To: | Diane Jackson, Mohammed Shuaibi, Weaver D Office of Nuclear Regulatory Research |
| References | |
| FOIA/PA-2004-0140 | |
| Download: ML041480285 (4) | |
Text
ra ltu.G-I ay avem-a s.w.Vs I ala.
VLu.
J L.Fu 1 %imatI.2 WPUaLO a.__..
Page 1 1 From:
To:
Date:
Subject:
- c. Anthony Mendiola a (I
Deborah Jackson; Doug Weaver; Mohammed Shualbi 02/25/2004 5:34PM Fwd: DBesse Daily Status Update Here is the Davis-Besse daily status update as of 4:00 pm (EST) on February 25, 2004.
Key Items of Note:
The plant Is In Mode 3 maintaining Normal Operating Pressure/Normal Operating Temperature.
(NOPINOT - 532 F12155 psig). The licensee expects to maintain the plant In these conditions until restart.
The licensee Is currently tracking outstanding activities that need to be completed prior to restart
[Mode 2/11. There are approximately 12 restart Items.
NRC Commissioner TA briefing on Davis-Besse was held today.
The plant entered a 72-hour TS Action Statement for Auxiliary Feedwater Train I on February 25 at 1:30 a.m. A check valve In the cooling water flowpath to the pump's suction failed to fully seat during testing. The licensee has assembled a problem solving team.
The licensee has several other equipment problems which are being addressed through problem solving teams. These are a nitrogen leak on 13.8 kV startup supply transformer "01," abnormal vibration levels on the control rod drive motor generator set, and a problem with 13.8 kV breaker HAAE4 (closes but trips).
I will update this information for you In the morning.
- Thanks, Tony CC:
Carl Lyon; James Shea; John Stang; Jon Hopkins; William Ruland infom, cif-i, thfis record was deleted ill Mer 1wt the Freedom of Information Act, ezermptions5 FGIA-
--N
Anthony Mendiola - DBesse Daily Status Update Page 1 From:
Dave Passehl To:
DB0350; Geoffrey Grant; James Caldwell Date:
02/25/2004 4:12PM
Subject:
DBesse Daily Status Update Attached.
Anthony Mendiola 25-05.WPD Page 1i SENSl;FZ<FO tON - FOR OFFJCIALS&[M
?
DAVIS-BESSE RESTART STATUS This Information Is current as of 4:00 pm (EST) on February 25, 2004.
The plant is In Mode 3 maintaining Normal Operating PressurelNorrnal Operating Temperature.
(NOP/NOT - 5320F1/2155 psig). The licensee expects to maintain the plant In these conditions until restart.
LICENSEE ACTIVITIES PRIOR TO RESTART The licensee is currently tracking outstanding activities that need to be completed prior to restart
[Mode 211]. There are approximately 12 restart items.
Corrective Actions:
6 Condition Reports:
2 Field Work:
I Surveillance Tests:
I NRC ACTIVITIES PRIOR TO RESTART
-On February 25 a Commissioner TA briefing on Davis-Besse Is scheduled.
Below Is a simplified time line that describes the significant NRC and licensee activities and milestones that are necessary for NRC to authorize restart.
These tentative dates are predicated upon the licensee successfully completing NRC pre-restart activities and demonstrating acceptable operating performance.
Key Agency decision points are annotated with asterisks (**) In the timeline below.
The outcome of each decision point could materially alter the timing and substance of the rest of the schedule.
The details of these activities are described In three Internal NRC documents: the Davis-Besse Oversight Panel Process Plan, the Davis-Besse Restart Communications Plan and the Davis-Besse Restart Punch Ust.
Panel briefing for Commissioners' TAs 5
Panel Issues restart recommendation to Jim Caldwell Jim Caldwell Issues draft Order to licensee (for affirmation/hearing declination)
Licensee affirms conditions of Order and declines hearing Finalize restart authorization letter and Order (letter to be signed by Jim Caldwell; will authorize restart and transmit the Order - Order to be signed by Jim Dyer)
Implement Restart Communications Plan (1-day Enforcement Notification)
Up+Issue restart authorization letter and Order Implement restart Inspection plan SERSI 7
W OROFF3. USE ONLY
Anthony Mendiola 25-05.WPD Page 2 l SENSIT O RMAIO CHALLENGES THAT THE LICENSEE IS CURRENTLY ADDRESSING The plant entered a 72-hour TS Action Statement for Auxiliary Feedwater Train I on February 25 at 1:30 a.m. A check valve in the cooling water flowpath to the pump's suction failed to fully seat during testing. The licensee has assembled a problem solving team.
The licensee has several other equipment problems which are being addressed through problem solving teams. These are a nitrogen leak on 13.8 kV startup supply transformer "01, abnormal vibration levels on the control rod drive motor generator set, and a problem with 13.8 kV breaker HAAE4 (closes but trips).
LICENSEE ACTIVITIES FOLLOWING RESTART AUTHORIZATION The following sequence of events were taken from a licensee Level I schedule.
NRC approval for restart Enter operational Mode 2 (reactor startup)
Reactor critical -Zero power physics testing Enter Mode 1 (greater than 5% power)
Readiness and effectiveness review prior to synch to the grid Synch to the grid Readiness and effectiveness review prior to exceeding 50% power Reactor at 100% power SENSITI INFORMATIONFOR OFFICIAL USE 0 IUo"