MONTHYEARML0407602942004-02-29029 February 2004 G20040176/LTR-04-0146, LTR-04-0147, LTR-04-0148 - Ltr. from Bernard Cooper, Loren W. Kramer, and Jane Newton Re Request Independent Safety Assessment of Vermont Yankee Project stage: Request ML0414605692004-05-27027 May 2004 G20040176/LTR-04-0146 - Bernard Cooper Ltr. Re. Request Independent Safety Assessment of Vermont Yankee Plant Project stage: Other ML0414605702004-05-27027 May 2004 G20040176/LTR-04-0148 - Jane Newton Ltr. Re. Request Independent Safety Assessment of Vermont Yankee Plant Project stage: Other ML0414600762004-05-27027 May 2004 G20040176/LTR-04-0147 - Loren Kramer Ltr. Re. Request Independent Safety Assessment of Vermont Yankee Plant Project stage: Other ML0721401472007-08-0808 August 2007 Correction to Amendment 147 TS Pages Regarding Steam Generator Tube Integrity Project stage: Other ML0721904992007-08-0808 August 2007 Correction to Amendment No. 147 Technical Specification Pages Regarding Steam Generator Tube Integrity Project stage: Other 2004-05-27
[Table View] |
|
---|
Category:Letter
MONTHYEARBVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 IR 07200059/20234012023-10-0505 October 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2023401 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20230012023-08-15015 August 2023 Northstar Nuclear Decommissioning Company, Llc., Vermont Yankee Nuclear Power Station, - NRC Inspection Report 05000271/2023001 BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000271/20220022023-02-22022 February 2023 Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station - NRC Inspection Report No. 05000271/2022002 BVY 23-003, Pre-Notice of Disbursement from Decommissioning Trust2023-01-31031 January 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-030, Documentary Evidence of Performance Bond2022-12-30030 December 2022 Documentary Evidence of Performance Bond ML22347A2792022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 IR 05000271/20224012022-12-15015 December 2022 NRC Inspection Report No. 05000271/2022401, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont (Letter Only) BVY 22-028, Re Proof of Financial Protection2022-11-28028 November 2022 Re Proof of Financial Protection BVY 22-027, Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station2022-11-11011 November 2022 Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station BVY 22-026, Pre-Notice of Disbursement from Decommissioning Trust2022-10-31031 October 2022 Pre-Notice of Disbursement from Decommissioning Trust ML22273A1492022-10-0404 October 2022 Review of Decommissioning Funding Status 2022 BVY 22-025, Pre-Notice of Disbursement from Decommissioning Trust2022-10-0404 October 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-023, Pre-Notice of Disbursement from Decommissioning Trust2022-09-0101 September 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-022, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-22022 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-16016 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-020, Pre-Notice of Disbursement from Decommissioning Trust2022-08-0101 August 2022 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20220012022-08-0101 August 2022 NRC Inspection Report No. 05000271/2022001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont BVY 22-019, Pre-Notice of Disbursement from Decommissioning Trust2022-07-0606 July 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-013, Notification of Revised Decommissioning Cost Estimate2022-06-17017 June 2022 Notification of Revised Decommissioning Cost Estimate 2024-01-04
[Table view] |
Text
May 27, 2004 Mr. Loren W. Kramer 14 Oak Street Greenfield, MA 01301
Dear Mr. Kramer:
I am responding on behalf of the Nuclear Regulatory Commission (NRC) to your letter dated March 3, 2004, regarding the request by Entergy Nuclear Operations, Inc. (Entergy) to amend Vermont Yankee Nuclear Power Stations (Vermont Yankee) license to increase power by 20 percent. In your letter, you noted that the facilities at Vermont Yankee were not sufficiently hardened to protect against attacks. You also expressed concerns about the age and structural integrity of Vermont Yankee as it relates to the requested power uprate, and asked that the NRC deny Entergys request, or at least conduct a comprehensive independent safety assessment prior to approval.
Regarding your concern about the plants structural integrity in the case of an attack, the NRC has sought to ensure continued adequate protection of the Nations nuclear power plants since the unprecedented events of September 11, 2001. The NRC has worked in close coordination with other Federal agencies (including the Federal Emergency Management Agency, the Department of Defense, the Department of Homeland Security, the Department of Energy, the Federal Bureau of Investigation, and the Federal Aviation Administration), as well as with State governments, and the nuclear industry. We believe the enhancements to nuclear power plant security after the events of September 11, 2001, and the NRCs continuing oversight provide assurance for the continued safe operation of commercial nuclear facilities, including Vermont Yankee, in the current threat environment. In addition, even before the terrorist attacks on September 11, 2001, nuclear power plants were considered among the best defended and most hardened facilities of the Nations critical infrastructure.
You also raised concern about the age and condition of Vermont Yankee. Consistent with NRC regulations, Vermont Yankee was granted a 40-year operating license in 1972. NRC requires plant operators to continuously test and monitor the condition of safety equipment and to keep equipment in top condition. NRC has also required licensees to correct design deficiencies that could impact plant safety. While Vermont Yankee has been in operation since 1972, over the years, the licensee has replaced equipment and performed overhauls of other plant equipment.
Where appropriate, the licensee has also upgraded or installed new equipment to replace or supplement original systems.
Regarding your concern for the need of an independent safety assessment at Vermont Yankee, I am enclosing, for your information, a letter that we sent to the Public Service Board on May 4, 2004, explaining the NRCs approach in addressing this issue. The NRC plans to use an improved engineering inspection at Vermont Yankee, as described in the enclosure. The NRC staff has concluded that a detailed technical review, combined with inspections prescribed by the reactor oversight process, as enhanced by a new engineering inspection, is the most effective means for our staff to determine whether Vermont Yankee can safely operate under
Mr. Kramer uprated power conditions. The NRC will not approve the Vermont Yankee uprate, or any proposed change to a plant license, unless the NRC staff can conclude that the proposed change will be executed in a manner that assures the publics health and safety.
I believe the enclosed information, which describes our review and inspection procedure, along with our plans for a new engineering inspection process, will assist in addressing your concerns regarding the safety of the Vermont Yankee Nuclear Power Station. Additional information about the on-going review process is also available on our NRC website at:
www.nrc.gov/reactors/plant-specific-items/vermont-yankee-issues.html Thank you for your concern and interest in NRC activities.
Sincerely,
/RA/
Cornelius F. Holden, Director Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
Enclosure:
Letter to the Vermont Public Service Board
Mr. Kramer uprated power conditions. The NRC will not approve the Vermont Yankee uprate, or any proposed change to a plant license, unless the NRC staff can conclude that the proposed change will be executed in a manner that assures the publics health and safety.
I believe the enclosed information, which describes our review and inspection procedure, along with our plans for a new engineering inspection process, will assist in addressing your concerns regarding the safety of the Vermont Yankee Nuclear Power Station. Additional information about the on-going review process is also available on our NRC website at:
www.nrc.gov/reactors/plant-specific-items/vermont-yankee-issues.html Thank you for your concern and interest in NRC activities.
Sincerely,
/RA/
Cornelius F. Holden, Director Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
Enclosure:
Letter to the Vermont Public Service Board DISTRIBUTION:
PUBLIC RidsEdoMailCenter SBurns/KCyr, OGC RidsOcaMailCenter LReyes RidsNrrWpcMail SECY (LTR-04-0146)
SCollins RidsNrrAdptKJohnson RidsNrrPMREnnis WKane HMiller, Rgn I CBixler, Rgn I CPaperiello AHowe NRR Mail Room (G20040176)
PNorry RidsNrrDlpmLpdICHolden RidsOgcRp WDean RidsNrrPMBPham RidsOpaMail RidsNrrOdJDyer RidsNrrLACRaynor RidsRgnIMailCenter RidsNrrAdptBSheron PDI-2 Section Reading File RidsNrrPMAMcMurtray Package No.: ML041460066 Incoming No.: ML040760294 Response No.: ML041460076 OFFICE PDIV-2/PM PDI-2/LA PDI-1/PM VY/SC PDI/PD NAME BPham SLittle DSkay AHowe CHolden DATE 5/26/04 5/26/04 5/26/04 5/26/04 5/27/04 OFFICIAL RECORD COPY