ML041410529

From kanterella
Jump to navigation Jump to search

G20040243/LTR-04-0201 - Honorable Rosenberg Ltr Independent Safety Audits for Vermont Yankee
ML041410529
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 05/21/2004
From: Holden C
NRC/NRR/DLPM/LPD1
To: Rosenberg S
State of MA, Senate
Ennis R, NRR/DLPM, 415-1420
Shared Package
ML041410400 List:
References
FOIA/PA-2005-0031, G20040243, LTR-04-0201, TAC MC2561
Download: ML041410529 (2)


Text

May 21, 2004 The Honorable Stan Rosenberg Massachusetts Senate State House Boston, MA 02133-1054

Dear Senator Rosenberg:

I am responding on behalf of the Nuclear Regulatory Commission (NRC) to your letter dated March 24, 2004, which was jointly endorsed by Representatives Stephen Kulik, Christopher Donelan, and Shaun Kelly, as well as Senator Andrea Nuciforo. In this letter, you expressed your collective concerns for the power uprate request at the Vermont Yankee Nuclear Power Station, and requested that the NRC conduct an independent engineering assessment of the facility, as also recently called for by the Vermont Public Service Board. You requested that this assessment be done prior to the NRC approval of any power uprate at Vermont Yankee.

The NRC sent a letter to the Vermont Public Service Board on May 4, 2004, in response to their request for an independent engineering assessment. To address your concerns, I am enclosing a copy of that letter for your information, which describes our plans to use an improved engineering inspection at Vermont Yankee. The NRC staff has concluded that the detailed technical review, combined with inspections prescribed by the reactor oversight process, as enhanced by a new engineering inspection, is the most effective method of determining whether Vermont Yankee could safely operate under uprated power conditions.

I believe the enclosed information, which describes our review and inspection procedure, along with our plans for a new engineering inspection, will assist in addressing your concerns regarding the power uprate of Vermont Yankee. Additional information about the on-going review process is also available on our NRC website at:

www.nrc.gov/reactors/plant-specific-items/vermont-yankee-issues.html Thank you for your interest and concern in NRC activities.

Sincerely,

/RA/

Cornelius F. Holden, Director Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation

Enclosure:

Letter to the Vermont Public Service Board

May 21, 2004 The Honorable Stan Rosenberg Massachusetts Senate State House Boston, MA 02133-1054

Dear Senator Rosenberg:

I am responding on behalf of the Nuclear Regulatory Commission (NRC) to your letter dated March 24, 2004, which was jointly endorsed by Representatives Stephen Kulik, Christopher Donelan, and Shaun Kelly, as well as Senator Andrea Nuciforo. In this letter, you expressed your collective concerns for the power uprate request at the Vermont Yankee Nuclear Power Station, and requested that the NRC conduct an independent engineering assessment of the facility, as also recently called for by the Vermont Public Service Board. You requested that this assessment be done prior to the NRC approval of any power uprate at Vermont Yankee.

The NRC sent a letter to the Vermont Public Service Board on May 4, 2004, in response to their request for an independent engineering assessment. To address your concerns, I am enclosing a copy of that letter for your information, which describes our plans to use an improved engineering inspection at Vermont Yankee. The NRC staff has concluded that the detailed technical review, combined with inspections prescribed by the reactor oversight process, as enhanced by a new engineering inspection, is the most effective method of determining whether Vermont Yankee could safely operate under uprated power conditions.

I believe the enclosed information, which describes our review and inspection procedure, along with our plans for a new engineering inspection, will assist in addressing your concerns regarding the power uprate of Vermont Yankee. Additional information about the on-going review process is also available on our NRC website at:

www.nrc.gov/reactors/plant-specific-items/vermont-yankee-issues.html Thank you for your interest and concern in NRC activities.

Sincerely,

/RA/

Cornelius F. Holden, Director Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation

Enclosure:

Letter to the Vermont Public Service Board DISTRIBUTION:

PUBLIC RidsEdoMailCenter NRR Mail Room RidsOcaMailCenter WTravers RidsNrrWpcMail SBurns, OGC SECY#04-0201 SCollins RidsNrrAdptKJohnson KCyr,OGC PLohaus WKane RidsNrrDlpmMViera HMiller, Rgn I CPaperiello RidsNrrDlpmLpdI-2JClifford NRR Mail Room #G20040243 PNorry RidsNrrDlpmLpdICHolden RidsOgcRp WDean RidsNrrPMBPham RidsOpaMail RidsNrrOdJDyer RidsNrrLACRaynor RidsRgnIMailCenter RidsNrrAdptBSheron PDI Section Reading File RidsNrrPMAMcMurtray Package: ML041410400 Incoming: ML040980386 Response: ML041410529

Enclosure:

ML041170438 OFFICE PDIV-2/PM PDI/LA LEAD PM PDI-2/SC PDI/PD NAME GTaylor/BPham SLittle DSkay AHowe CHolden DATE 5/20/04 5/20/04 5/20/04 5/20/04 5/21/04 OFFICIAL RECORD COPY