MONTHYEARGO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) ML22278B0972022-10-0505 October 2022 Fourth Ten-Year Interval Inservice Inspection Program Relief Request 4ISl-11 GO2-21-107, In-Service Inspection Summary Report for the Twenty-Fifth Refueling (R25)2021-08-26026 August 2021 In-Service Inspection Summary Report for the Twenty-Fifth Refueling (R25) GO2-21-020, General Station - Fourth Ten-Year Interval Inservice Inspection (ISI) Program 4ISI-10, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2021-03-0101 March 2021 General Station - Fourth Ten-Year Interval Inservice Inspection (ISI) Program 4ISI-10, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI GO2-20-146, Erratum to Fourth Ten-Year Inservice Inspection (ISI) Program Relief Request 4ISI-092020-11-17017 November 2020 Erratum to Fourth Ten-Year Inservice Inspection (ISI) Program Relief Request 4ISI-09 ML20114E2352020-04-22022 April 2020 Columbia,Fourth Ten-Year Interval Inservice Inspection Program Relief Request 4ISI-09 ML20057E9542020-02-26026 February 2020 Fourth Ten-Year Interval Inservice Inspection Program Relief Request 4ISI-08 GO2-19-127, In-Service Inspection Summary Report for the Twenty-Fourth Refueling Outage (R24)2019-09-11011 September 2019 In-Service Inspection Summary Report for the Twenty-Fourth Refueling Outage (R24) GO2-17-153, Inservice Inspection Summary Report for the Twenty-Third Refueling Outage (R23)2017-09-12012 September 2017 Inservice Inspection Summary Report for the Twenty-Third Refueling Outage (R23) GO2-16-068, Re-Submittal of Fourth Ten-Year Interval Inservice Inspection (ISI) Program Relief Request 4ISI-072016-04-26026 April 2016 Re-Submittal of Fourth Ten-Year Interval Inservice Inspection (ISI) Program Relief Request 4ISI-07 GO2-16-008, Fourth Ten-Year Interval Inservice Inspection (ISI) Program Relief Request 4ISIS-042016-02-0404 February 2016 Fourth Ten-Year Interval Inservice Inspection (ISI) Program Relief Request 4ISIS-04 GO2-15-157, Fourth Ten-Year Interval Inservice Inspection (ISI) Program Request 4ISI-022015-12-10010 December 2015 Fourth Ten-Year Interval Inservice Inspection (ISI) Program Request 4ISI-02 GO2-15-136, In-Service Inspection Summary Report for the Twenty-Second Refueling Outage (R22)2015-09-22022 September 2015 In-Service Inspection Summary Report for the Twenty-Second Refueling Outage (R22) GO2-15-055, Submittal of Fourth 10-Year Inservice Testing (IST) Program Plan2015-04-23023 April 2015 Submittal of Fourth 10-Year Inservice Testing (IST) Program Plan GO2-15-024, Withdrawal of Inservice Inspection (ISI) Program Request 3ISI-162015-02-18018 February 2015 Withdrawal of Inservice Inspection (ISI) Program Request 3ISI-16 GO2-14-152, Erratum for Relief Requests for the Fourth Ten-Year Interval Inservice Testing Program2014-10-23023 October 2014 Erratum for Relief Requests for the Fourth Ten-Year Interval Inservice Testing Program GO2-14-017, Inservice Inspection (ISI) Program Request 3 ISI-142014-02-0606 February 2014 Inservice Inspection (ISI) Program Request 3 ISI-14 GO2-13-133, In-Service Inspection Summary Report for the Twenty-First Refueling Outage (R21)2013-09-18018 September 2013 In-Service Inspection Summary Report for the Twenty-First Refueling Outage (R21) ML13249A1602013-08-28028 August 2013 Submittal of Revision 1 of the Third Ten-Year Interval Pump and Valve Inservice Testing (IST) Program Plan GO2-11-193, In-Service Inspection Summary Report for the Twentieth Refueling Outage (R20)2011-12-14014 December 2011 In-Service Inspection Summary Report for the Twentieth Refueling Outage (R20) GO2-09-134, Inservice Inspection Summary Report for Refueling Outage R-192009-09-22022 September 2009 Inservice Inspection Summary Report for Refueling Outage R-19 GO2-07-141, Inservice Inspection Summary Report for Refueling Outage R-182007-09-18018 September 2007 Inservice Inspection Summary Report for Refueling Outage R-18 ML0708707152007-03-22022 March 2007 Response to Request for Additional Information Regarding the Third Ten-Year Interval Inservice Testing Program ML0636201472006-12-14014 December 2006 Columbia Generating Station, Second Ten-Year Interval ISI Request 2ISI-32 GO2-06-062, Correction to Third Ten-Year Interval Inservice Inspection Program Plan2006-04-27027 April 2006 Correction to Third Ten-Year Interval Inservice Inspection Program Plan GO2-05-196, Submittal of the Third Ten-Year Interval Inservice Inspection Program Plan and 10 CFR 50.55a Requests 3ISI-01 Through 3ISI-072005-12-15015 December 2005 Submittal of the Third Ten-Year Interval Inservice Inspection Program Plan and 10 CFR 50.55a Requests 3ISI-01 Through 3ISI-07 ML0527103602005-09-15015 September 2005 Enclosure, Columbia Generating, Analytical Evaluation of Inservice Inspection Examination Results GO2-05-153, Analytical Evaluation of Inservice Inspection Examination Results2005-09-15015 September 2005 Analytical Evaluation of Inservice Inspection Examination Results ML0525801582005-09-0606 September 2005 Inservice Inspection Summary Report for Refueling Outage R-17 GO2-04-065, Request to Incorporate ASME Code Case N-663 in Columbia'S Second Ten-Year Interval Inservice Inspection Program Plan2004-04-0808 April 2004 Request to Incorporate ASME Code Case N-663 in Columbia'S Second Ten-Year Interval Inservice Inspection Program Plan GO2-03-147, Inservice Inspection Summary Report for Refueling Outage R-162003-09-16016 September 2003 Inservice Inspection Summary Report for Refueling Outage R-16 2023-09-06
[Table view] Category:Letter type:GO
MONTHYEARGO2-24-088, Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-24024 September 2024 Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements GO2-24-082, Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-10010 September 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-070, Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program2024-07-29029 July 2024 Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program GO2-24-063, Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan2024-07-15015 July 2024 Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan GO2-24-057, Notice of Readiness for Supplemental Inspection2024-06-19019 June 2024 Notice of Readiness for Supplemental Inspection GO2-24-056, Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing2024-06-11011 June 2024 Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing GO2-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-13013 May 2024 2023 Annual Radiological Environmental Operating Report GO2-24-050, Annual Environmental Operating Report2024-04-30030 April 2024 Annual Environmental Operating Report GO2-24-042, 2023 Annual Radioactive Effluent Release Report2024-04-22022 April 2024 2023 Annual Radioactive Effluent Release Report GO2-24-044, Voluntary Response to Regulatory Issue Summary 2024-012024-04-11011 April 2024 Voluntary Response to Regulatory Issue Summary 2024-01 GO2-24-034, Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan2024-03-20020 March 2024 Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan GO2-24-041, Level of Financial Protection - Annual Reporting Requirement2024-03-12012 March 2024 Level of Financial Protection - Annual Reporting Requirement GO2-24-036, Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate2024-03-11011 March 2024 Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate GO2-24-039, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462024-03-11011 March 2024 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing GO2-24-014, Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-23-035, Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-03-0909 March 2023 Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling GO2-23-019, Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-012023-02-0808 February 2023 Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-01 GO2-22-131, Guarantee of Payment of Deferred Premium2022-12-19019 December 2022 Guarantee of Payment of Deferred Premium GO2-22-122, Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-11-28028 November 2022 Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-076, Status of License Renewal Commitments2022-10-31031 October 2022 Status of License Renewal Commitments GO2-22-110, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactor2022-10-17017 October 2022 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactor GO2-22-096, Supplement to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-10-0404 October 2022 Supplement to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b 2024-09-24
[Table view] |
Text
ENERGY NORTH WEST PO. Box 968 a Richland, Washington 99352-0968 April 8, 2004 G02-04-065 10 CFR 50.55a U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555
Subject:
COLUMBIA GENERATING STATION, DOCKET NO. 50-397; 10 CFR 50.55a REQUEST TO INCORPORATE ASME CODE CASE N-663 IN COLUMBIA'S SECOND TEN-YEAR INTERVAL INSERVICE INSPECTION PROGRAM PLAN
Dear Sir or Madam:
Pursuant to 10 CFR 50.55a(a)(3)(i), Energy Northwest herein requests the NRC to approve the use of an alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section Xl requirements for examination of Class 1 Examination Category B-F and Class 2, Examination Category C-F-2 welds at Columbia Generating Station (Columbia). The Attachment to this letter contains Energy Northwest's 10 CFR 50.55a request to use ASME Code Case N-663 for Columbia. The proposed alternative would prevent unnecessary weld inspections and reduce radiological dose while maintaining an acceptable level of safety and quality for examination of the affected welds in accordance with 10 CFR 50.55a(a)(3)(i).
Energy Northwest requests approval of the request detailed in the Attachment prior to March 2005 to allow implementation in Columbia's refueling outage scheduled for spring of 2005.
10 CFR 50.55a REQUEST TO INCORPORATE ASME CODE CASE N-663 IN COLUMBIA'S SECOND TEN-YEAR INTERVAL INSERVICE INSPECTION PROGRAM PLAN Page 2 of 2 If you have any. questions or require additional information regarding this matter, please contact Ms. CL Perino, Licensing Manager, at (509) 377-2075.
Respectfully, DK Atkinson Vice President, Technical Services Mail Drop PE08
Attachment:
10 CFR 50.55a Request cc: BS Mallet - NRC - RIV BJ Benney - NRC - NRR NRC Sr. Resident Inspector - 988C RN Sherman - BPA/1399 TC Poindexter - Winston & Strawn
10 CFR 50.55a REQUEST TO INCORPORATE ASME CODE CASE N-663 IN COLUMBIA'S SECOND TEN-YEAR INTERVAL INSERVICE INSPECTION PROGRAM PLAN Attachment Page 1 of 3 10 CFR 50.55a Request Number 21SI-028 Proposed Alternative In Accordance with 10 CFR 50.55a(a)(3)(i)
-Alternative Provides Acceptable Level of Quality and Safety-ASME Code Components Affected American Society of Mechanical Engineers (ASME)Section XI Class 1 piping welds Examination Category B-F, Item Numbers B5.10 and B5.130 and Class 2 piping welds Examination Category C-F-2, Item Numbers C5.50 through C5.82.
Applicable Code Edition and Addenda
The applicable code is ASME Section XI 1989 Edition with no Addenda. Columbia Generating Station (Columbia) is in its second inservice inspection interval, third inspection period.
Applicable Code Requirements The ASME Section XI subarticles IWB-2500 and IWC-2500 require components to be examined as specified in Tables IWB-2500-1 and IWC-2500-1. These tables require subjecting a sampling of piping welds (as well as other components) to various types of non-destructive examinations (i.e., NDE, volumetric, and/or surface examinations).
Reason for Request
Code required surface examinations are applicable to the general population of B-F and C-F-2 welds. The proposed alternatives as described in Code Case N-663 would require surface examination of areas identified as susceptible to outside surface attack. Columbia is requesting adoption of Code Case N-663 in order to avoid unnecessary inspections and to reduce radiological dose. The Code Case N-663 methodology would provide these benefits while maintaining an adequate level of quality and safety for examination of the affected welds.
Proposed Alternative Energy Northwest proposes to use ASME Code Case N-663 in its entirety as an alternative to the surface examination requirements of Tables IWB-2500-1 and IWC-2500-1 for examination categories B-F and C-F-2. All areas of the subject welds identified as susceptible to outside surface attack will receive surface exams during the Columbia Generating Station Second Ten-Year Interval in accordance with Code Case N-663.
. 11I 10 CFR 50.55a REQUEST TO INCORPORATE ASME CODE CASE N-663 IN COLUMBIA'S SECOND TEN-YEAR INTERVAL INSERVICE INSPECTION PROGRAM PLAN Attachment Page 2 of 3 Basis for Use The subject item numbers in ASME Section XI require a volumetric and/or surface exam on selected piping welds to ensure that generic degradation mechanisms are not active on either the inside diameter or the Outside Diameter (O.D.). Currently, these welds are selected using deterministic criteria that are not based on the probability of exposure to degradation mechanisms. The ASME Code Case N-663 provides an alternative to the current ASME Section XI requirements for defining the number and location of surface examinations for piping components.
The ASME Section XI Task Group on ISI Optimization, Report No. 92-01-01, "Evaluation of Inservice Inspection Requirements for Class 1, Category B-J Pressure Retaining Welds in Piping," dated July 1995, reported (with 50 units responding and a total of 9333 welds inspected) only 2 welds (0.02%) were found to have flaws detected by Section XI surface examinations. These flaws were induced during fabrication. In addition to the ASME task group report, several risk-informed Code cases have been developed for use on piping welds (e.g., ASME Code Cases N-560, N-577, and N-578). One of the methods for risk-informing piping examinations is described in Electric Power Research Institute (EPRI) TR-112657, Rev.
B-A, "Revised Risk-informed Inservice Inspection Evaluation Procedure." Table 4-1, "Summary of Degradation-Specific Inspection Requirements and Examination Methods," of the EPRI report lists the required degradation mechanisms to be evaluated in Class 1, 2, and 3 piping. It also identifies the risk-informed examination method required for each of these degradation mechanisms. The only degradation mechanism identified as requiring a surface examination is O.D. chloride cracking. These two initiatives prompted ASME to re-evaluate the value of surface examinations.
Code Case N-663 incorporates lessons learned from the risk-informed initiatives and industry examination experience into Section XI by requiring an evaluation to identify locations, if any, where a surface examination would be beneficial based on a generic piping degradation mechanism perspective. This evaluation would identify locations where O.D. degradation is most likely to occur by reviewing plant-specific programs, practices, and operating experience.
When the potential for degradation is identified, Code Case N-663 defines examination techniques, volumes, and frequencies. As such, application of the Code Case N-663 methodology will identify more appropriate locations for surface examination, if any, and eliminate examinations at locations where degradation is unlikely. Other ASME Section XI examination requirements for the subject piping welds, including volumetric examinations and pressure testing, will continue to be performed.
Code Case N-663 was approved by the ASME Boiler and Pressure Vessel Code Committee on September, 17, 2002, but has not yet been included in the most recent listing of NRC approved Code cases provided in Revision 13 of Regulatory Guide 1.147, "Inservice Inspection Code Case Acceptability - ASME Section XI Division 1."
10 CFR 50.55a REQUEST TO INCORPORATE ASME CODE CASE N-663 IN COLUMBIA'S SECOND TEN-YEAR INTERVAL INSERVICE INSPECTION PROGRAM PLAN Attachment Page 3 of 3 Compliance with the proposed alternative described above will provide an acceptable level of quality and safety for examination of the affected welds.
Duration of Proposed Alternative The proposed alternative will be implemented for the remainder of the second 10-year inservice inspection interval, or until Code Case N-663 is published in a future version of NRC Regulatory Guide (RG) 1.147, "Inservice Inspection Code Case Acceptability - ASME Section XI, Division 1," at which time the provisions of the Code Case N-663 conditions and limitations specified in RG 1.147 will be followed.
Precedents Similar requests have been granted to other licensees such as Entergy Operations, Inc.'s ANO-1, Grand Gulf, River Bend, and Waterford 3 plants (ref: TAC Nos. MB 6880, MB 6881, MB 6879, MB 6882, dated August 26, 2003, ADAMS Accession Number ML032390190)
References
- 1. American Society of Mechanical Engineers (ASME)Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components," 1989 Edition, No Addenda.
- 2. Title 10 of the Code of Federal Regulations, Part 50, Section 55a, Codes and Standards
- 3. ASME Section XI Task Group on ISI Optimization, Report No. 92-01-01, "Evaluation of Inservice Inspection Requirements for Class 1 Category B-J Pressure Retaining Welds in Piping," dated July 1995. (ADAMS Accession Number ML030910450, dated 3/14/2003)
- 4. ASME Code Case N-663, "Alternative Requirements for Classes 1 and 2 Surface Examinations,Section XI, Division 1."
- 5. NRC Regulatory Guide 1.147, Inservice Inspection Code Case Acceptability, ASME Section XI, Division 1, Revision 13, January 2004.
- 6. EPRI TR 112657, Revision B-A, Revised Risk-Informed Inservice Inspection Evaluation Procedure, Final Report, December 1999.