Stephen A. Byrne Senior Vice President, Nuclear Operations 803.345.4622 A SCANA COMPANY April 13, 2004 Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555 Attention: Director, Office of Resource Management
Dear Sir / Madam:
Subject:
VIRGIL C. SUMMER NUCLEAR STATION DOCKET NO. 50/395 OPERATING LICENSE NO. NPF-12 MARCH MONTHLY OPERATING REPORT Enclosed is the March 2004 Monthly Operating Report for the Virgil C. Summer Nuclear Station Unit No. 1. This submittal is made in accordance with the requirements of Technical Specifications, Section 6.9.1.10.
If there are any questions, please call me at your convenience.
Ve, yours phnA. B mre or fA
`t/
4 SAB/mbb Attachment c:
J. B. Archie T. G. Eppink (w/o Attachment)
R. J. White L. A. Reyes K. R. Cotton T. D. Gatlin NRC Resident Inspector K. M. Sutton Paulette Ledbetter W. R. Higgins INPO Records Center J&H Marsh & McLennan William G. Wendland (ANI)
Pat Haught (Westinghouse)
C. W. Adams NSRC RTS (0-L-99-0350-1)
File (818.03-1, RR 4100)
DMS (RC-04-0065)
SCE&G I Virgil C. Summer Nuudear Station
- P 0. Box 88
- Jenkinsville, South Carolina 29065
- T (803) 345.5209
- www.scana.com
Director, Office of Resource Management March Monthly Operating Report RC-04-0065 Page 1 of 4 ATTACHMENT I AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE March 2004 AVERAGE DAILY POWER LEVEL DAY DAY 1
2 3
4 5
6 7
8 9
10 11 12 13 14 15 16 (Mwe-Net) 987 986 986 986 985 987 987 987 988 986 986 982 982 986 986 988 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 50/395 V. C. SUMMER I April 5, 2004 W. H. BELL (803) 345-4389 AVERAGE DAILY POWER LEVEL (Mwe-Net) 987 985 987 987 987 986 987 987 987 986 988 987 987 602 0
Director, Office of Resource Management March Monthly Operating Report RC-04-0065 Page 2 of 4 ATTACHMENT II OPERATING DATA REPORT DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50/395 V. C. SUMMER I April 5, 2004 W. H. BELL (803) 345-4389 OPERATING STATUS 1
Reporting Period:
Gross Hours in Reporting Period:
2 Currently Authorized Power Level (MWt):
Max. Depend. Capacity (MWe-Net):
Design Electrical Rating (MWe-Net):
3 Power Level to Which Restricted (If Any) (MWe-Net):
4 Reasons for Restrictions:
March 2004 744 2900 966 972.7 N/A N/A THIS MONTH YR TO DATE CUMULATIVE 5
Number of Hours Reactor Critical 6
Reactor Reserve Shutdown Hours 7
Hours Generator On Line 8
Unit Reserve Shutdown Hours 9
Gross Thermal Energy Generated (MWH) 10 Gross Electrical Energy (MWH) 11 Net Electrical Energy Generated (MWH) 12 Reactor Service Factor 13 Reactor Availability Factor 14 Unit Service Factor 15 Unit Availability Factor 16 Unit Capacity Factor (Using MDC) 17 Unit Capacity Factor (Using Design) 18 Unit Forced Outage Rate 711.7 0.0 711.7 0.0 2062025 729270 700919 95.7 95.7 95.7 95.7 97.5 96.9 4.3 2151.7 0.0 2151.7 0.0 6234091 2205970 2120177 98.5 98.5 98.5 98.5 100.5 99.8 1.5 148956.2 0.0 146987.1 0.0 398850146 135082829 129122970 83.9 83.9 82.8 82.8 79.8 78.8 3.0 19 Shutdowns Scheduled Over Next 6 Months (Type, Date, & Duration of Each):
None 20 If Shutdown at End of Report Period, Estimated Date of Startup: 04/13/04 21 Units in Test Status (Prior to Commercial Operation):
N/A
Director, Office of Resource Management March Monthly Operating Report RC-04-0065 Page 3 of 4 ATTACHMENT III UNIT SHUTDOWNS AND POWER REDUCTION DOCKET NO.
50/395 UNIT V. C. SUMMER I DATE April 5, 2004 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 March 2004 NO.
DATE TYPE DURATION REASON METHOD CORRECTIVE ACTION/COMMENTS 1
03/30/2004 F
32.3 A
3 Repair C Reactor Coolant Pump seal injection line.
1 REASON A: Equipment Failure B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error H: Other (Explain) 2 METHOD 1: Manual 2: Manual Trip/Scram 3: Automatic Trip/Scram 4: Continuation (Use Initial Date) 5: Power Reduction (Duration 0.0) 9: Other (Explain)
SUMMARY
Director, Office of Resource Management March Monthly Operating Report RC-04-0065 Page 4 of 4 ATTACHMENT IV NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.
50/395 UNIT V. C. SUMMER I DATE April 5, 2004 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 March 2004 V. C. Summer Station began the month at 100% power and operated there until 03/30/04. At 14:10 on the 3 0th a plant shutdown began to support repairs to the C Reactor Coolant Pump seal injection line. This seal injection line was identified as the source of pressure boundary leakage, which required a plant shutdown in accordance with Tech Spec 3.4.6.2. During this shutdown at 15:16 the main turbine was manually tripped due to high bearing vibration. At 15:21 the reactor automatically tripped due to lo-lo level in the C steam generator. The plant remained shutdown for the remainder of the month.