MONTHYEARML0620000282006-07-13013 July 2006 June 2006 Operating Report for Virgil C. Summer RC-06-0094, April 2006 Monthly Operating Report for Virgil C. Summer Nuclear Station2006-05-0909 May 2006 April 2006 Monthly Operating Report for Virgil C. Summer Nuclear Station RC-06-0073, March 2006 Monthly Operating Report for V.C. Summer Nuclear Station2006-04-0606 April 2006 March 2006 Monthly Operating Report for V.C. Summer Nuclear Station ML0607505692006-03-13013 March 2006 February 2006 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0601703262006-01-11011 January 2006 December 2005 Monthly Operating Report for V C Summer Unit 1 ML0534703312005-12-0606 December 2005 November 2005 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0532101872005-11-14014 November 2005 October 2005 Monthly Operating Report for Virgil C. Summer RC-05-0163, September 2005 Monthly Operating Report for Virgil C Summer Nuclear Station2005-10-0707 October 2005 September 2005 Monthly Operating Report for Virgil C Summer Nuclear Station RC-05-0145, August 2005 Monthly Operating Report for Virgil C. Summer Nuclear Station2005-09-12012 September 2005 August 2005 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0522902682005-08-10010 August 2005 July 2005 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0519903442005-07-13013 July 2005 June 2005 Monthly Operating Report for Virgil C. Summer Nuclear Station RC-05-0056, March 2005 Monthly Operating Report for Virgil C. Summer Nuclear Station2005-04-0606 April 2005 March 2005 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0507001212005-03-0909 March 2005 February 2005 Monthly Operating Report for the Virgil C Nuclear Station Unit 1 RC-05-0022, January 2005 Monthly Operating Report for the Virgil C. Summer Nuclear Station Unit 12005-02-0404 February 2005 January 2005 Monthly Operating Report for the Virgil C. Summer Nuclear Station Unit 1 ML0501201382005-01-0707 January 2005 December 2004 Monthly Operating Report, Virgil C. Summer Nuclear Station ML0434100782004-12-0202 December 2004 November 2004 Monthly Operating Report for Virgil C Summer Nuclear Station Unit 1 ML0431402432004-11-0505 November 2004 October 2004 Monthly Operating Report for the Virgil C. Summer Nuclear Station Unit No. 1 ML0428800242004-10-0707 October 2004 September 2004 Monthly Operating Report for Virgil C Summer Nuclear Station ML0426003382004-09-0909 September 2004 August 2004 Monthly Operating Report for Virgil C Summer Nuclear Station RC-04-0125, July 2004 Monthly Operating Report for Virgil C. Summer Nuclear Station, Unit 12004-08-0909 August 2004 July 2004 Monthly Operating Report for Virgil C. Summer Nuclear Station, Unit 1 ML0420302872004-07-15015 July 2004 June 2004 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0416705222004-06-0808 June 2004 May 2004 Monthly Operating Report for Virgil C Summer RC-04-0084, April 2004 Monthly Operating Report for Virgil C. Summer Unit 12004-05-12012 May 2004 April 2004 Monthly Operating Report for Virgil C. Summer Unit 1 ML0411108772004-04-13013 April 2004 March 2004 Monthly Operating Report for Virgil C. Summer ML0407103052004-03-0404 March 2004 February 2004 Monthly Operating Report for Virgil C. Summer Nuclear Station RC-04-0029, January 2004 Monthly Operating Report for Virgil C. Summer Unit 12004-02-0606 February 2004 January 2004 Monthly Operating Report for Virgil C. Summer Unit 1 ML0401602802004-01-13013 January 2004 December 2003 Monthly Operating Report for Virgil C. Summer, Unit 1 RC-03-0245, November 2003 Monthly Operating Report for Virgil C. Summer Nuclear Station Unit 12003-12-0808 December 2003 November 2003 Monthly Operating Report for Virgil C. Summer Nuclear Station Unit 1 RC-03-0230, October 2003 Monthly Operating Report for Virgil C. Summer2003-11-0606 November 2003 October 2003 Monthly Operating Report for Virgil C. Summer ML0331701822003-11-0303 November 2003 October 2003 Monthly Operating Report for Virgil C. Summer, Unit 1 ML0329405832003-10-13013 October 2003 September 2003 Monthly Operating Report for Virgil C. Summer, Unit 1 ML0326009132003-09-0909 September 2003 August 2003 Monthly Operating Report for Virgil C. Summer ML0322503472003-08-0505 August 2003 July 2003 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0320604752003-07-0707 July 2003 June 2003 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0316814012003-06-0909 June 2003 May 2003 Monthly Operating Report for Virgil C. Summer ML0314100322003-05-0808 May 2003 April 2003 Monthly Operating Report for Virgil C. Summer Nuclear Station, Unit 1 RC-03-0080, March 2003 Monthly Operating Report for Virgil C. Summer, Unit 12003-04-0303 April 2003 March 2003 Monthly Operating Report for Virgil C. Summer, Unit 1 RC-03-0055, February 2003 Monthly Operating Report for Virgil C. Summer Nuclear Station2003-03-0707 March 2003 February 2003 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0304303742003-02-0606 February 2003 January 2003 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0301501162003-01-0606 January 2003 December 2002 Monthly Operating Report for Virgil C. Summer Unit 1 ML0235201562002-12-0606 December 2002 November 2002 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0232501432002-11-12012 November 2002 October 2002 Monthly Operating Report for Virgil C. Summer Nuclear Station RC-02-0173, September 2002 Monthly Operating Report for South Carolina Electric & Gas Co2002-10-14014 October 2002 September 2002 Monthly Operating Report for South Carolina Electric & Gas Co ML0226305332002-09-10010 September 2002 August 2002 Monthly Operating Report for Virgil C. Summer Unit 1 ML0223102602002-08-12012 August 2002 July 2002 Monthly Operating Report for Virgil C. Summer Nuclear Station, Unit 1 ML0220003402002-07-11011 July 2002 June 2002 Monthly Operating Report for Virgil C Summer Nuclear Station ML0217700422002-06-13013 June 2002 May 2002 Monthly Operating Report for Virgil C. Summer Nuclear Station ML0214303262002-05-0707 May 2002 April 2002 Monthly Operating Report for Virgil C. Summer Nuclear Station, Unit 1 ML0211303402002-04-0909 April 2002 March 2002 Monthly Operating Report for Virgil C. Summer Nuclear Station, Unit 1 ML0208405812002-03-13013 March 2002 February 2002 Monthly Operating Report for Virgil C. Summer Nuclear Station, Unit 1 2006-07-13
[Table view] |
Text
Stephen A. Byrne Senior Vice President, Nuclear Operations 803.345.4622 A SCANA COMPANY April 13, 2004 Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555 Attention: Director, Office of Resource Management
Dear Sir / Madam:
Subject:
VIRGIL C. SUMMER NUCLEAR STATION DOCKET NO. 50/395 OPERATING LICENSE NO. NPF-12 MARCH MONTHLY OPERATING REPORT Enclosed is the March 2004 Monthly Operating Report for the Virgil C. Summer Nuclear Station Unit No. 1. This submittal is made in accordance with the requirements of Technical Specifications, Section 6.9.1.10.
If there are any questions, please call me at your convenience.
Ve, yours or fA `t/ 4 phnA. B mre SAB/mbb Attachment c: J. B. Archie INPO Records Center T. G. Eppink (w/o Attachment) J&H Marsh & McLennan R. J. White William G. Wendland (ANI)
L. A. Reyes Pat Haught (Westinghouse)
K. R. Cotton C. W. Adams T. D. Gatlin NSRC NRC Resident Inspector RTS (0-L-99-0350-1)
K. M. Sutton File (818.03-1, RR 4100)
Paulette Ledbetter DMS (RC-04-0065)
W. R. Higgins SCE&G I Virgil C.Summer Nuudear Station
- T(803) 345.5209 *www.scana.com
Director, Office of Resource Management March Monthly Operating Report RC-04-0065 Page 1 of 4 ATTACHMENT I AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE April 5, 2004 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 March 2004 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (Mwe-Net) (Mwe-Net) 1 987 17 987 2 986 18 985 3 986 19 987 4 986 20 987 5 985 21 987 6 987 22 986 7 987 23 987 8 987 24 987 9 988 25 987 10 986 26 986 11 986 27 988 12 982 28 987 13 982 29 987 14 986 30 602 15 986 31 0 16 988
Director, Office of Resource Management March Monthly Operating Report RC-04-0065 Page 2 of 4 ATTACHMENT II OPERATING DATA REPORT DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE April 5, 2004 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 OPERATING STATUS 1 Reporting Period: March 2004 Gross Hours in Reporting Period: 744 2 Currently Authorized Power Level (MWt): 2900 Max. Depend. Capacity (MWe-Net): 966 Design Electrical Rating (MWe-Net): 972.7 3 Power Level to Which Restricted (If Any) (MWe-Net): N/A 4 Reasons for Restrictions: N/A THIS MONTH YR TO DATE CUMULATIVE 5 Number of Hours Reactor Critical 711.7 2151.7 148956.2 6 Reactor Reserve Shutdown Hours 0.0 0.0 0.0 7 Hours Generator On Line 711.7 2151.7 146987.1 8 Unit Reserve Shutdown Hours 0.0 0.0 0.0 9 Gross Thermal Energy Generated (MWH) 2062025 6234091 398850146 10 Gross Electrical Energy (MWH) 729270 2205970 135082829 11 Net Electrical Energy Generated (MWH) 700919 2120177 129122970 12 Reactor Service Factor 95.7 98.5 83.9 13 Reactor Availability Factor 95.7 98.5 83.9 14 Unit Service Factor 95.7 98.5 82.8 15 Unit Availability Factor 95.7 98.5 82.8 16 Unit Capacity Factor (Using MDC) 97.5 100.5 79.8 17 Unit Capacity Factor (Using Design) 96.9 99.8 78.8 18 Unit Forced Outage Rate 4.3 1.5 3.0 19 Shutdowns Scheduled Over Next 6 Months (Type, Date, & Duration of Each):
None 20 If Shutdown at End of Report Period, Estimated Date of Startup: 04/13/04 21 Units in Test Status (Prior to Commercial Operation): N/A
Director, Office of Resource Management March Monthly Operating Report RC-04-0065 Page 3 of 4 ATTACHMENT III UNIT SHUTDOWNS AND POWER REDUCTION DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE April 5, 2004 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 March 2004 NO. DATE TYPE DURATION REASON METHOD CORRECTIVE ACTION/COMMENTS 1 03/30/2004 F 32.3 A 3 Repair C Reactor Coolant Pump seal injection line.
1 REASON A: Equipment Failure B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error H: Other (Explain) 2 METHOD 1: Manual 2: Manual Trip/Scram 3: Automatic Trip/Scram 4: Continuation (Use Initial Date) 5: Power Reduction (Duration 0.0) 9: Other (Explain)
SUMMARY
Director, Office of Resource Management March Monthly Operating Report RC-04-0065 Page 4 of 4 ATTACHMENT IV NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE April 5, 2004 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 March 2004 V. C. Summer Station began the month at 100% power and operated there until 03/30/04. At 14:10 on the 3 0 th a plant shutdown began to support repairs to the C Reactor Coolant Pump seal injection line. This seal injection line was identified as the source of pressure boundary leakage, which required a plant shutdown in accordance with Tech Spec 3.4.6.2. During this shutdown at 15:16 the main turbine was manually tripped due to high bearing vibration. At 15:21 the reactor automatically tripped due to lo-lo level in the C steam generator. The plant remained shutdown for the remainder of the month.