GRAND GULF NUCLEAR STATION INITIAL LICENSE OPERATOR EXAM EXAM OUTLINE REVIEW COMMENTS REVIEWED BY: MARK HAIRE
- 1. Items 2 and 3 on ES-201-2 Examination Outline Quality Checklist requires comparing this exam to the Audit; this will need to be accomplished during the week of validation since the Audit is not even written yet.
- 2. Items 8, 9, and 10 of ES-301-4 Simulator Scenario Quality Checklist cannot be verified from the information supplied by the licensee.
- 3. ES-301-5 Transient and Event Checklist Forms are not filled out in accordance with directions in that the event numbers from ES-D-1 for each evolution type are supposed to be indicated but are not.
- 4. No comments on the written exam outlines.
- 5. SRO-I form ES-301-1 Administrative Topics Outline topic A.2 does not look like it tests a job function of an SRO; licensee has already determined to change A.2 to something else related to operability determination.
- 6. There was disagreement between reviewer and licensee over whether SRO-U form ES-301-2 Individual Walk-Through Test Outline included the required ESF related evolution. The reviewer. Item 4 involves ADS (and ESF system) and Item 5 involves RCIC (also an ESF system), so the reviewer now agrees with the licensee that the requirement is met.
- 7. Two of the three scenarios deal with LOCA conditions, and only the spare scenario deals with a steam leak, so the reviewer requests that the spare replace one of the two LOCA scenarios. Licensee agreed to replace scenario 3 with the back-up and redesignate scenario 3 as the back-up.
- 8. Scenario-1: The fifth critical task listed reads Commence injection... through Shutdown Cooling when reactor level reaches -192 inches; should change when to before in that statement.
- 9. Scenario-2: Objective 7 uses the word failure twice; one of the two failure usages should be eliminated.
- 10. Scenario-2: The third critical task referencing second control rod drift should be eliminated. Licensee explained that, due to the loss of electrical bus earlier in the scenario, the applicants may see more control rods begin to drift, in which case a scram is the appropriate response.