Transmittal of Revised Emergency Plan Implementing Procedures El-4.3, Revision 15
ML040980509
Person / Time
Site: Palisades Entergy icon.png
Issue date: 03/23/2004
From:
Consumers Energy
To: Mcknight J
Office of Nuclear Reactor Regulation
References
261740 EL-4.3, Rev 15
Download: ML040980509 (4)


Text

---

a Date Entered: Mar 23, 2004 TO: USNRC/WASHINGTON JMCKNIGHT Copy Number: 145

, TRANSMITAL NUMBER: 261740 H PROCEDURE NUMBER: El-4.3 TITLE: EMERGENCY OPERATIONS FACILITY ACTIVATION TRANSMITTAL: LISTED BELOW ARE NEW/REVISED PROCEDURES WHICH MUST BE IMMEDIATELY INSERTED INTO OR DISCARDED FROM YOUR PROCEDURE MANUAL.

Action Required Section or Description REMOVE AND DESTROY El-4.3, R/15, COVERSHEET AND DOCUMENT PAGES 3-4 REPLACE WITH El-4.3, R/15, COVERSHEET AND DOCUMENT PAGES 3-4 EDITORIAL SIGN, DATE, AND RETURN THEACKNOWLEDGEMENTFORM WITHIN 10 DAYS TO THE PALISADES PLANT DOCUMENT CONTROL SIGNATURE OR INITIALS DATE If applicable, REMOVE ALL travelers and marked up pages in front of this procedure.

P5

Procedure No El-4.3 Revision 15 Effective Date 3/23104 PALISADES NUCLEAR PLANT EMERGENCY IMPLEMENTING PROCEDURE I,

TITLE: EMERGENCY OPERATIONS FACILITY ACTIVATION Approved: DMOnken I 3/18104 Procedure Sponsor Date New Procedure/Revision Summary:

Editorial change to Revision 15 Specific Changes

PALISADES NUCLEAR PLANT Proc No El-4.3 EMERGENCY IMPLEMENTING PROCEDURE Revision 15 Page 3 of 4 TITLE: EMERGENCY-OPERATIONS FACILITY ACTIVATION 3.7 NRC FACILITY LIAISON Personnel who possess a broad knowledge of the Palisades Plant and can assist the NRC with securing pertinent information with regard to the emergency.

The responsibilities could include interfacing with plant management and/or facility lead personnel, ensuring timely updates of the emergency are made available, answering questions and concerns expressed by the NRC and ensuring NRC personnel have a smooth'transitioh into their assigned facility.

Personnel would be assigned on an' as needed basis and support the Technical Support Center, the Emergency Operations Facility and'the Joint Public Information, Center.

There is no specific ERO training required for this position.

4.0 INITIAL CONDITIONS AND/OR REQUIREMENTS 4.1 The EOF shall be activated at the alert or higher emergency classification. The EOF may be activated before this time at the option of the Site Emergency Director e (SED).

5.0 PROCEDURE USER ALERT REFERENCE USE PROCEDURE Refer to the procedure periodically to confirm that all procedure segments of an activity will be or are being performed. Where required, sign appropriate signi-off blanks to certify that all-segments are complete.

The attachments to this procedure define the responsibilities of the Emergency Operations Facility staff, and provides guidance on tasks to be performed.

Individuals assigned as team leaders or to specific identified roles should ensure the attachment checklists are utilized.

PALISADES NUCLEAR PLANT Proc No El-4.3 EMERGENCY IMPLEMENTING PROCEDURE Revision 15 Page 4 of 4 TITLE: EMERGENCY OPERATIONS FACILITY ACTIVATION-6.0 ATTACHMENTS 6.1 Attachment 1, "Emergency Operations Facility Director"--

Attachment 1.1, "Emergency Operations Facility Status Updates" 6.2 Attachment 2, "Emergency Operations Facility Communication Support Team" Attachment 2.1, "Emergency Telephone Numbers" Attachment 2.2, "Additional Emergency Support Request" 6.3 Attachment 3, "Emergency Operations Facility Health Physics Support Team" 6.4 Attachment 4, "Emergency Operations Facility Engineering Support Team" Attachment 4.1, "Additional Emergency Support Request" 6.5 Attachment 5, "Emergency Operations Facility Governmental Liaison" 6.6 Attachment 6, "Emergency Operations Facility Public Affairs" 6.7 Attachment 7, "Emergency Operations Facility Emergency Planner" 6.8 Attachment 8, "Emergency Operations Facility Administrative Support Team" V Attachment 8.1, "Emergency Operations Facility Floor Plan" Attachment 8.2, "Nuclear Management Company Emergency Response Sign In" 6.9 Attachment 9, "Security Officer Instructions" 6.10 Attachment 10, "Emergency Operations Facility Organization" 6.11 Attachment 11, "Mutual Assistance Agreement Between Detroit Edison, Nuclear Management Company, and Indiana Michigan Power Company" 7.0 SPECIAL REVIEWS' The scope of this procedure does not include activities that require a 50.59 review per Palisades Administrative Procedure 10.41, "Procedure and Policy Processes."

Therefore, changes to this procedure'do not require a 50.59 review.