1 ROBINSON NUCLEAR PLANT LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Safety evaluation report (SER) with open items issued 8/25/03 (two open items)
Completed optional final inspection 9/10/03 Received open item responses from applicant 9/16/03 Advisory Committee on Reactor Safeguards (ACRS) 9/30/03 Subcommittee meeting on SER with open items Final supplemental environmental impact statement (SEIS) issued 12/12/03 Issued SER 1/20/04
2 ROBINSON NUCLEAR PLANT LICENSE RENEWAL STATUS FUTURE ACTIVITIES ACRS Full Committee meeting 3/04 Staff recommendation to Director, NRR 4/12/04 Decision - Director, NRR 4/19/04
3 GINNA STATION LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Received safety request for additional information (RAI) responses 6/12/03 Issued draft SEIS 6/25/03 Completed scoping inspection 6/27/03 Public meeting on draft SEIS 8/6/03 Issued SER with open items 10/9/03 Completed aging management review (AMR) inspection 10/22/03 ACRS Subcommittee on SER with open items 11/4/03
4 GINNA STATION LICENSE RENEWAL STATUS FUTURE ACTIVITIES Issue final SEIS 2/6/04 Issue SER 3/8/04 ACRS Full Committee meeting on SER 4/04 Staff recommendation to Director, NRR 5/28/04 Decision - Director, NRR 6/4/04
5 SUMMER LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Issued draft SEIS 7/11/03 Completed aging management program audit for GALL programs 7/17/03 Completed AMR inspection 8/22/03 Public meeting on draft SEIS 8/26/03 Issued initial SER (no open items) 10/9/03 Received applicant comments on initial SER 11/5/03 Completed the optional final inspection 11/20/03 ACRS Subcommittee meeting on initial SER 12/3/03
6 SUMMER LICENSE RENEWAL STATUS FUTURE ACTIVITIES Issue final SEIS 2/28/04 Issue SER 3/11/04 ACRS Full committee meeting on SER 5/04 Staff recommendation to Director, NRR 6/4/04 Decision - Director, NRR 6/11/04
7 DRESDEN, UNITS 2 AND 3 QUAD CITIES, UNITS 1 AND 2 LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Received safety RAI responses 10/3/03 Completed AMP Audit 10/22/03 Completed AMR inspection 10/17/03 Issued draft SEIS - Quad Cities 11/4/03 Dresden 12/2/03 Public meetings on draft SEIS - Quad Cities 12/16/03 Dresden 1/14/04
8 DRESDEN, UNITS 2 AND 3 QUAD CITIES, UNITS 1 AND 2 LICENSE RENEWAL STATUS FUTURE ACTIVITIES Issue SER with open items 2/16/04 ACRS Subcommittee meeting on SER with open items 4/13/04 Receive SER open item responses 4/16/04 Issue final SEISs 7/9/04 Issue SER 7/26/04
9 FARLEY, UNITS 1 AND 2 LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Received application 9/15/03 Published Federal Register Notice (FRN) for receipt and availability 10/6/03 Published FRN for acceptance 10/30/03 Published FRN for opportunity for hearing 11/5/03 Completed first Generic Aging Lessons Learned Report (GALL) 11/7/03 audit (aging management programs)
Completed scoping and screening methodology audit 11/21/03 Completed second GALL audit (aging management review) 12/18/03 Completed environmental scoping meeting 1/8/04
10 FARLEY, UNITS 1 AND 2 LICENSE RENEWAL STATUS FUTURE ACTIVITIES Conduct exit meeting for GALL program audits 2/04 Issue environmental RAIs 2/25/04 Conduct scoping and screening inspection 5/10/04 Issue draft SEIS 8/13/04 Conduct public meeting to discuss SEIS 9/23/04 Issue SER with open items 10/15/04
11 ARKANSAS NUCLEAR ONE, UNIT 2 LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Received application 10/15/03 Published FRN for receipt and availability 10/24/03 Conducted public information session near site 11/18/03 Published FRN for acceptance and opportunity for hearing 11/24/03 Completed first GALL audit (aging management programs) 12/5/03 Published FRN environmental scoping meeting 12/22/03 Deadline for filing hearing request and petitions for intervention 12/24/03
12 ARKANSAS NUCLEAR ONE, UNIT 2 LICENSE RENEWAL STATUS FUTURE ACTIVITIES Conduct scoping and screening methodology audit 1/23/04 Conduct environmental scoping meeting 2/3/04 Complete second GALL audit (aging management review) 2/13/04 Conduct scoping and screening inspection 3/1/04 Issue environmental RAIs 3/26/04 Issue draft SEIS 9/3/04 Conduct public meeting to discuss draft SEIS 10/19/04 Issue SER with open items 11/5/04
13 COOK, UNITS 1 AND 2 LICENSE RENEWAL STATUS RECENT ACCOMPLISHMENTS Received Application 11/3/03 Published FRN for Receipt and Availability 11/10/03 Conducted public information session near site 11/20/03 Published FRN for acceptability and opportunity for hearing 12/10/03 Completed first GALL audit (aging management programs) 12/19/03 Completed scoping and screening methodology audit 1/16/04
14 COOK, UNITS 1 AND 2 LICENSE RENEWAL STATUS FUTURE ACTIVITIES Complete second GALL audit (aging management review) 3/5/04 Conduct environmental scoping meeting 3/9/04 Issue environmental RAIs 5/5/04 Issue draft SEIS 9/24/04 Conduct public meeting to discuss draft SEIS 11/3/04 Issue SER with open items 12/21/04