->~~~^Exekrn.

Exelon Nuclear Limerick Generating Station P.O. Box 2300 Pottstown, PA 19464 www.exeloncorp.com Nuclear T.S. 6.9.1.6 March 10, 2004 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Limerick Generating Station, Units 1 and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353 Subject.-

-7 MonthlyOperatifig Report for February 2004 Attached is the monthly operating report for Limerick Units 1 and 2 for the month of February 2004 forwarded pursuant to Technical Specification 6.9.1.6 and the guidance of NRC Generic Letter 97-02. The attached monthly operating report data has also been entered into the INPO Consolidated Database for the month of February 2004 for Units 1 and 2.

If you have any questions or require additional information, please do not hesitate to contact us.

Sincerely, Bryan C. Hanson Plant Manager-LGS Attachments cc:

H. Miller, Administrator, Region I, USNRC

-- A. -Burritt, LGS USNRC Senior Resident Inspector I

bcc:

R. DeGregorio - GML 5-1 B. Hanson - GML 5-1 C. Mudrick - SSB 3-1 E. Kelly - SSB 3-1 K. Kemper - SSB 2-4 S. Gamble - SSB 2-4 R. McCall - SSB 2-3 J. Toro - SMB 1-2 G. Lee - SSB 3-1 J. Grimes - KSA 2N D. Dyckman (PABRP) SSB 2-4

Unit:

Limerick 1 Docket No:

50-352 Date:

3/10104 Completed by: Greg Lee Telephone:

(610) 718-3707 A.

OPERATING DATA REPORT REPORTING PERIOD-February 2004 Design Electrical Rating (MWe-Net) 1191.00 Maximum Dependable Capacity (MWe-Net) 1134.00 l Month T Year to Date I Cumulative Hours Reactor Critical (Hours) 696.00 1,440.00 140,006.47 Hours Generator On-Line (Hours) 696.00 j 1,440.00 j 138,021.20 Unit Reserve Shutdown Hours (Hours) 0.00 0.00 1 0.00 Net Electrical Energy (MWh) 728,691.00 1,590,914.00 143,417,203.00 B.

UNIT SHUTDOWN No.

Date Type Generator Reason Method Corrective Actions/Comments

_(YY-6mmdd)

Off-lide- - -- - --..

Duration (hrs)

None During February SU R20041

SUMMARY

Unit 1 began the month of February 2004 at 99.3% of rated thermal power (RTP). Throughout the month, unless specified below, when the unit operated less than 100% RTP, it was due to end-of-cycle coastdown.

On February 3d at 1201 hours0.0139 days <br />0.334 hours <br />0.00199 weeks <br />4.569805e-4 months <br />, reactor power was reduced from 98.4% RTP to 94.6% RTP to remove the 5B feedwater heater from service. At 1427 hours0.0165 days <br />0.396 hours <br />0.00236 weeks <br />5.429735e-4 months <br />, reactor power was restored to 99.6% RTP.

On February 18 at 2208 hours0.0256 days <br />0.613 hours <br />0.00365 weeks <br />8.40144e-4 months <br />, reactor power was reduced from 94.5% RTP to 60.9% RTP to remove the 5C feedwater heater and 1A reactor feed pump from service, and power suppression testing.

On February 22nd at 2035 hours0.0236 days <br />0.565 hours <br />0.00336 weeks <br />7.743175e-4 months <br />, reactor power was restored to 92.6% RTP.

Unit 1 ended the month of February 2004 at 90.6% RTP.

Type Reason Method F-Forced A-Equipment Failure (Explain) 1-Manual S-Scheduled B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Continuation E-Operator Training/License Examination 5-Other(Explain)

F-Administrative G-Operational Error (Explain)

H-Other (Explain)

C.

SAFETY/RELIEF VALVE OPERATION Date Valves No. & Type of Plant Condition Description of Event Actuated Actuation None During February 2004

Unit:

Limerick 2 Docket No:

50-353 Date:

3/10/04 Completed by: Greg Lee Telephone:

(610) 718-3707 A.

OPERATING DATA REPORT REPORTING PERIOD-February2004 I Design Electrical Rating (MWe-Net) 1191.00 I Maximum Dependable Capacity (MWe-Net) l 1134.00 l Month I Year to Date I Cumulative Hours Reactor Critical (Hours) 696.00 1,440.00 115,890.10 Hours Generator On-Line (Hours) 696.00 1,440.00 114,127.72 Unit Reserve Shutdown Hours (Hours) 0.00 0.00 0.00 Net Electrical Energy (MWh) 820,505.00 1,689,127.00 122,710,493.00 B. UNITSHUTDOWN-No.

Date Type Generator Reason Method Corrective Actions/Comments (yymmdd)

Off-line Duration

( h r s )_

None during February

_ _ _ _2 0 0 4

SUMMARY

Unit 2 began the month of February 2004 at 99.9%/6 of rated thermal power (RTP).

On February 3I at 2203 hours0.0255 days <br />0.612 hours <br />0.00364 weeks <br />8.382415e-4 months <br />, reactor power was reduced from 99.9% RTP to 81.4% RTP for quarterly MSIV and TSV testing and channel bow testing.

On February j4 th at 2338 hours0.0271 days <br />0.649 hours <br />0.00387 weeks <br />8.89609e-4 months <br />, reactor power was restored to 100.0 % RTP.

Unit 2 ended the month of February 2004 at 99.9% RTP.

Type Reason Method F-Forced A-Equipment Failure (Explain) 1-Manual S-Scheduled B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Continuation E-Operator Training/License Examination 5-Other (Explain)

F-Administrative G-Operational Error (Explain)

H-Other (Explain)