March 4, 2004

Mr. Christopher M. Crane

President and Chief Nuclear Officer

Exelon Nuclear

Exelon Generation Company, LLC

4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

CLINTON POWER STATION

CONFIRMATION OF INITIAL OPERATOR LICENSE EXAMINATIONS

Dear Mr. Skolds:

In a letter dated September 26, 2003, your staff responded to NRC Regulatory Issue Summary

(RIS) 2003-14, "Preparation and Scheduling of Operator Licensing Examinations," for all Exelon

Nuclear Stations. This letter responds to the request for initial license examinations at Clinton

Power Station, Unit 1.

Initial license examinations were requested during the weeks of June 6 and June 13, 2005, and

during the week of August 27, 2007. Because of a heavy work load, the examination requested

for June 6 and June 13 was rescheduled to the weeks of July 11 and July 18, 2005, per a

telephone conversation between Mr. D. McNeil of my staff and Mr. T. Shortell, Clinton Station

Training Director. That examination has been scheduled and a chief examiner assigned to that

examination. The examination requested for August 2007 will be scheduled as we approach

that date.

On-site validation of the examinations will occur at Clinton Power Station approximately

3 weeks before the examination administration date. In the unlikely event that we are unable to

support the examination during the scheduled weeks, we will inform you immediately upon

discovery of such conditions and make arrangements to administer the examinations at a

mutually acceptable date.

As indicated in your RIS response letter, your staff will develop the examinations. Your letter

also indicated that you are training 13 candidates for the examination in July 2005. Please

inform us if the number of candidates decreases below 10 as this will impact the examination

schedule.

C. Crane

-2-

A supplementary letter will be sent to the training department approximately 120 days prior to

the initial examination informing them of the chief examiners name. The letter will also outline

examination security expectations, list the materials required by the NRC to conduct the

examination, reconfirm the examination dates, and reconfirm the number of candidates you

have in the training program. If you have any questions concerning this information, please

contact Mr. B. Palagi of my staff at 630-829-9611.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS

is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Roger D. Lanksbury, Chief

Operations Branch

Division of Reactor Safety

Docket No. 50-461

License No. NPF-62

cc:

Site Vice President - Clinton Power Station

Clinton Power Station Plant Manager

Regulatory Assurance Manager - Clinton

Chief Operating Officer

Senior Vice President - Nuclear Services

Vice President - Operations Support

Vice President - Licensing and Regulatory Affairs

Manager Licensing - Clinton and LaSalle

Senior Counsel, Nuclear, Mid-West Regional Operating Group

Document Control Desk - Licensing

C. Crane

-2-

A supplementary letter will be sent to the training department approximately 120 days prior to

the initial examination informing them of the chief examiners name. The letter will also outline

examination security expectations, list the materials required by the NRC to conduct the

examination, reconfirm the examination dates, and reconfirm the number of candidates you

have in the training program. If you have any questions concerning this information, please

contact Mr. B. Palagi of my staff at 630-829-9611.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS

is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Roger D. Lanksbury, Chief

Operations Branch

Division of Reactor Safety

Docket No. 50-461

License No. NPF-62

cc:

Site Vice President - Clinton Power Station

Clinton Power Station Plant Manager

Regulatory Assurance Manager - Clinton

Chief Operating Officer

Senior Vice President - Nuclear Services

Vice President - Operations Support

Vice President - Licensing and Regulatory Affairs

Manager Licensing - Clinton and LaSalle

Senior Counsel, Nuclear, Mid-West Regional Operating Group

Document Control Desk - Licensing

DOCUMENT NAME: G:\\DRS\\ML040650758.wpd

To receive a copy of this document, indicate in the box "C" = Copy w/o attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE

RIII:DRS

RIII:DRS

RIII:DRS

RIII:DRS

NAME

MABies:sd

BPalagi

RDLanksbury

DATE

02/24/04

11/24/03

03/04/04

OFFICIAL RECORD COPY

C. Crane