Farley Inspection / Activity Plan 03/01/2004 - 09/30/2005 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 3 03/03/2004 10:32:11 Report 22 2
PB2-152
- RPV LOWER HEAD PENETRATIONS Safety Issues 03/13/2004 04/11/2004 Reactor Pressure Vessel Lower Head Penetration Nozzles (NRC Bulletin 2003-02)
2 PB2-153
- RX CONTAINMENT SUMP BLOCKAGE Safety Issues 03/13/2004 04/11/2004 Reactor Containment Sump Blockage (NRC Bulletin 2003-01)
1 EB2-ISI
- INSERVICE INSPECTION-U2 Baseline Inspections 03/22/2004 03/26/2004 Inservice Inspection Activities - PWR IP 7111108P 2
2 PB2-154
- SPENT FUEL MC&A Safety Issues 03/28/2004 06/26/2004 Spent Fuel Material Control and Accounting at Nuclear Power Plants IP 2515/154 1, 2 1
EB2-150
- RPV & VHP NOZZLES Safety Issues 03/29/2004 04/02/2004 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-0 IP 2515/150 2
5 LIC RENE
- FIRST LICENSE RENEWAL INSPECTION License Renewal Insp 05/10/2004 05/14/2004 License Renewal Inspection IP 71002 1, 2 2
PS-SEC
- SOUTH. NUC. CORP. ACCESS AUTH -BIRMINGHA Baseline Inspections 05/24/2004 05/28/2004 Access Authorization IP 7113001 1, 2 2
PS-SEC
- SECURITY Baseline Inspections 06/07/2004 06/11/2004 Access Authorization IP 7113001 1, 2 Baseline Inspections 06/07/2004 06/11/2004 Access Control IP 7113002 1, 2 Baseline Inspections 06/07/2004 06/11/2004 Performance Indicator Verification IP 71151 1, 2 1
PB2-FP
- FLOOD PROTECTION Baseline Inspections 07/12/2004 07/16/2004 Flood Protection Measures IP 7111106 1, 2 1
EB2-ISFS
- ISFSI PAD CONSTRUCTION Other Routine 07/19/2004 07/23/2004 On-Site Fabrication Of Components And Construction On An ISFSI IP 60853 1, 2 1
EB2-HS
- HEAT SINK Baseline Inspections 08/09/2004 08/13/2004 Heat Sink Performance IP 7111107B 1, 2 2
- REQUAL INSPECTION Baseline Inspections 08/09/2004 08/13/2004 Licensed Operator Requalification Program IP 7111111B 1, 2 2
- EMERGENCY EXERCISE Baseline Inspections 08/16/2004 08/20/2004 Exercise Evaluation IP 7111401 1, 2 Baseline Inspections 08/16/2004 08/20/2004 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 08/16/2004 08/20/2004 Performance Indicator Verification IP 71151 1, 2 4
LIC RENE
- SECOND LICENSE RENEWAL INSPECTION License Renewal Insp 09/13/2004 09/17/2004 License Renewal Inspection IP 71002 1, 2 License Renewal Insp 09/27/2004 10/01/2004 License Renewal Inspection IP 71002 1, 2 1
EB2 HEAD
- REACTOR HEAD REPLACEMENT Other Routine 09/27/2004 10/01/2004 Reactor Vessel Head Replacement Inspection IP 71007 1
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Farley Inspection / Activity Plan 03/01/2004 - 09/30/2005 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 3 03/03/2004 10:32:11 Report 22 2
PB2-152
- RPV LOWER HEAD PENETRATIONS Safety Issues 10/02/2004 10/28/2004 Reactor Pressure Vessel Lower Head Penetration Nozzles (NRC Bulletin 2003-02)
2 PB2-153
- RX CONTAINMENT SUMP BLOCKAGE Safety Issues 10/02/2004 10/28/2004 Reactor Containment Sump Blockage (NRC Bulletin 2003-01)
3 PS-RP
- RP OCCUPATION BL RX HEAD REPLACEMENT W-1 Other Routine 10/04/2004 10/08/2004 Reactor Vessel Head Replacement Inspection IP 71007 1, 2 Baseline Inspections 10/04/2004 10/08/2004 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 10/04/2004 10/08/2004 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 10/04/2004 10/08/2004 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 10/04/2004 10/08/2004 Performance Indicator Verification IP 71151 1, 2 1
EB2-ISI
- INSERVICE INSPECTION-U1 Baseline Inspections 10/11/2004 10/15/2004 Inservice Inspection Activities - PWR IP 7111108P 1
2 PS-RP
- RP OCCUPATION BL RX HEAD REPLACEMENT W-2 Other Routine 10/18/2004 10/22/2004 Reactor Vessel Head Replacement Inspection IP 71007 1, 2 Baseline Inspections 10/18/2004 10/22/2004 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 10/18/2004 10/22/2004 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 10/18/2004 10/22/2004 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 10/18/2004 10/22/2004 Performance Indicator Verification IP 71151 1, 2 2
OL PREP
- INITIAL EXAM PREP Not Applicable 12/06/2004 12/10/2004 FARLEY/EXAMS AT POWER FACILITIES V23227 1
3 OL EXAM
- INITIAL EXAM Not Applicable 01/10/2005 01/14/2005 FARLEY/EXAMS AT POWER FACILITIES V23227 1
4 EB1-TFP
- TRIENNIAL FIRE PROTECTION PRE-INSP VISIT Baseline Inspections 02/28/2005 03/04/2005 Fire Protection IP 7111105T 1, 2 4
EB1-TFP
- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 03/21/2005 03/25/2005 Fire Protection IP 7111105T 1, 2 Baseline Inspections 04/04/2005 04/08/2005 Fire Protection IP 7111105T 1, 2 1
BR2-FP
- FLOOD PROTECTION Baseline Inspections 06/26/2005 06/30/2005 Flood Protection Measures IP 7111106 1, 2 1
EB2-MODS
- MODIFICATIONS/10CFR50.59 Baseline Inspections 07/18/2005 07/22/2005 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 Baseline Inspections 07/18/2005 07/22/2005 Permanent Plant Modifications IP 7111117B 1, 2 4
EB2-PI&R
- BIENNIAL PI&R Baseline Inspections 08/08/2005 08/12/2005 Identification and Resolution of Problems IP 71152B 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Farley Inspection / Activity Plan 03/01/2004 - 09/30/2005 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 3 of 3 03/03/2004 10:32:11 Report 22 4
EB2-PI&R
- BIENNIAL PI&R Baseline Inspections 08/22/2005 08/26/2005 Identification and Resolution of Problems IP 71152B 1, 2 1
EB2-MR
- MAINTENANCE RULE Baseline Inspections 08/08/2005 08/12/2005 Maintenance Effectiveness IP 7111112B 1, 2 1
- EP INSPECTION Baseline Inspections 08/22/2005 08/26/2005 Alert and Notification System Testing IP 7111402 1, 2 Baseline Inspections 08/22/2005 08/26/2005 Emergency Response Organization Augmentation Testing IP 7111403 1, 2 Baseline Inspections 08/22/2005 08/26/2005 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 08/22/2005 08/26/2005 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2 Baseline Inspections 08/22/2005 08/26/2005 Performance Indicator Verification IP 71151 1, 2 1
EB2-ISI
- INSERVICE INSPECTION-U2 Baseline Inspections 09/19/2005 09/23/2005 Inservice Inspection Activities - PWR IP 7111108P 2
This report does not include INPO and OUTAGE activities.