January 2004 Monthly Operating Report for Perry, Unit 1
ML040490502
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 02/10/2004
From: Higaki V
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PY-CEI/NRR-2773L
Download: ML040490502 (3)


Text

-

Z.

FENOC Perry Nuclear Power Plant FENOC

~~~~~~~~~~~~~~~~

Center Road PO. Box 97 FirstEnergy Nuclear Operating Company Perry Ohio 44081 February 10, 2004 PY-CEI/NRR-2773L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C.

20555 Perry Nuclear Power Plant Docket No. 50440 License No. NPF-58 Monthly Operating Report Ladies and Gentlemen:

Attached is the January 2004 Monthly Operating Report for Perry Unit 1. Page I is the Operating Data Report and page 2 is the Unit Shutdowns Report. This report is submitted in accordance with Technical Specification 5.6.4 and Generic Letter 97-02, "Revised Contents of the Monthly Operating Report."

If you have questions or require additional information, please contact Ms. Toni Phelps at (440) 280-7660.

Very truly yours, Vernon K. Higaki Manager - Regulatory Affairs Attachment cc: NRC Region III Administrator NRC Project Manager NRC Resident Inspector

OPERATING DATA REPORT UNIT:

Perry DATE:

2/6/04 1.

2.

3.

4.

5.

6.

7.

Docket: 50-440 Unit Name:

Perry Nuclear Power Plant Reporting Period: January 2004 Utility

Contact:

T. Phelps Telephone: 440-280-7660 Design Electrical Rating (Net MWe):

Maximum Dependable Capacity (Net MWe):

1260 1235 8.

9.

10.

11.

Hours Reactor was Critical Hours Generator On-Line Unit Reserve Shutdown Hours Net Electrical Energy (MWeH)

This Month 744.0 744.0 0.0 onrv sro n ri-to-Date 744.0 744.0 0.0 oa nra n Cumul5tive 112.988.7 110.255.3 0.0 126.032,281.0 av -,vvo.v

zv -.vv.v Page 1

UNIT SHUTDOWNS REPORT MONTH - January 2004 DOCKET NO: 50-440 NAME: Perry Nuclear Power Plant DATE: 2/6/04 CONTACT: T. Phelps TELEPHONE: (440) 280-7660 I

I t

No.

Date Type Duration Reason Method Cause and Corrective Action to Prevent Recurrence I

Hours 2 1 3

1_

SUMMARY

The Perry Plant was on line the entire month of January.
1. TYPE:

F: Forced S: Scheduled

2. REASON:

A - Equipment Failure (explain)

B - Maintenance or Test C - Refueling D - Regulatory E - Operating Training &

License Examination F - Administrative G - Operational Error (explain)

H - Other (explain)

3. METHOD:

1 - Manual 2 - Manual Scram 3 - Automatic Scram 4-Continuation 5 - Other I

Page 2