February 20, 2004 LICENSEE:
Calvert Cliffs Nuclear Power Plant, Inc.
FACILITY:
Calvert Cliffs Nuclear Power Plant, Unit No. 1
SUBJECT:
SUMMARY
OF DECEMBER 15, 2003, CATEGORY 1 MEETING WITH CALVERT CLIFFS NUCLEAR POWER PLANT, INC. TO DISCUSS THE LICENSEES PLAN FOR THE UNIT NO. 1 REACTOR PRESSURE VESSEL HEAD INSPECTION AS REQUIRED BY THE ORDER DATED FEBRUARY 11, 2003 (TAC NO. MC1585)
On December 15, 2003, a public meeting was held between the Nuclear Regulatory Commission (NRC), and representatives of Calvert Cliffs Nuclear Power Plant, Inc., (CCNPPI or the licensee) at NRC Headquarters, One White Flint North, 11545 Rockville Pike, Rockville, MD. The purpose of the meeting was to discuss the licensees plan for the CCNPP Unit 1 reactor vessel head inspection during the spring 2004 refueling outage.
This inspection will be in response to the NRC Order dated February 11, 2003. Enclosure 1 is a list of the meeting attendees, and Enclosure 2 is a copy of the licensees slides presented at the meeting. One member of the public was in attendance.
Licensee personnel said that Unit 1 and Unit 2 reactor vessel heads have similar nozzle configuration. The inspection plan approach for the Unit 1 reactor vessel head will be the same as was done on Unit 2 during the inspection of March 2003. A total of 74 penetrations including 8 in-core instruments nozzles, 1 head vent nozzle and 65-control element drive mechanism nozzles will be inspected. The inspection will provide 100 percent visual examination of the top of the vessel head including 360 around each penetration. A leak path assessment of the visual examination will be performed by lifting the insulation panels sufficiently to provide access by a probe. Ultrasonic (UT) inspection will be performed for all alloy 600 penetration material. Where UT cannot be performed, eddy current testing (ET) will be performed to the extent possible. ET will be performed on the HV nozzle.
The licensee submitted a relaxation request to the February 11, 2003, Order by letter of January 30, 2004. This request is similar to the relaxation request that was submitted for Unit 2 in February 2003. This will more than likely be before the NRC staff will be publishing a revision of the Order.
/RA/
Guy S. Vissing, Senior Project Manager, Section 1 Project Directorate 1 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-317
Enclosures:
- 1. List of Attendees
- 2. Licensee Handouts cc w/encls: See next page Unit 2 in February 2003. This will more than likely be before the NRC staff will be publishing a revision of the Order.
/RA/
Guy S. Vissing, Senior Project Manager, Section 1 Project Directorate 1 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-317
Enclosures:
- 1. List of Attendees
- 2. Licensee Handouts cc w/encls: See next page DISTRIBUTION:
PUBLIC TMarsh AHiser CBixler, Rgn 1 PDI-1 Reading CHolden TChan GVissing RLaufer BBateman OGC SLittle EReichelt ACRS TMensah NRay JCollins RDavis WKoo ADAMS Accession Number: ML040490224 OFFICE PDI-1/PM PDI-1/LA PDI-1/SC NAME GVissing SLittle PTam for RLaufer DATE 2/20/04 2/19/04 2/20/04 OFFICIAL RECORD COPY
Enclosure 1 ATTENDANCE LIST DECEMBER 15, 2003 NAME ORGANIZATION Bob Hardies Constellation Energy George Khouri Constellation Energy Mike Milbradt NRC Terence Chan NRC Eric Reichelt NRC Robert Davis NRC John Haydin CCNPP - Constellation Energy Jay Collins NRC Rich Laufer NRC Daniel Horner McGaw-Hill Allen Hiser NRC Jon Kirkwood Constellation Energy Pat Furio Constellation Energy William Koo NRC Guy Vissing NRC
Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 cc:
President Calvert County Board of Commissioners 175 Main Street Prince Frederick, MD 20678 James M. Petro, Esquire Counsel Constellation Energy Group, Inc.
750 East Pratt Street, 5th floor Baltimore, MD 21202 Jay E. Silberg, Esquire Shaw, Pittman, Potts, and Trowbridge 2300 N Street, NW Washington, DC 20037 Mark Geckle Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685 Mr. Richard I. McLean, Manager Nuclear Programs Power Plant Research Program Maryland Dept. of Natural Resources Tawes State Office Building, B3 Annapolis, MD 21401 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Kristen A. Burger, Esquire Maryland Peoples Counsel 6 St. Paul Centre Suite 2102 Baltimore, MD 21202-1631 Patricia T. Birnie, Esquire Co-Director Maryland Safe Energy Coalition P.O. Box 33111 Baltimore, MD 21218 Mr. Loren F. Donatell NRC Technical Training Center 5700 Brainerd Road Chattanooga, TN 37411-4017 Mr. George Vanderheyden, Vice President Calvert Cliffs Nuclear Power Plant, Inc.
Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702