UNITED STATES NUCLEAR REGULATORY COMMISSION 0

WASHINGTON, D.C. 2055540001 January 30, 2004 LICENSEE:

Nuclear Management Company, LLC (NMC)

FACILITY:

Point Beach, Units 1 and 2

SUBJECT:

SUMMARY

OF MEETING BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION (NRC) STAFF AND NUCLEAR MANAGEMENT COMPANY, LLC (NMC) REPRESENTATIVES TO DISCUSS THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION On January 20, 2004, the NRC staff met with members of Nuclear Management Company, LLC (NMC) in a public meeting to discuss NMC's plan for submitting a license renewal application (LRA) for the Point Beach Nuclear Plant, Units 1 and 2. The list of attendees is provided in, and the meeting agenda is provided in Enclosure 2.

NMC representatives discussed the features of the Point Beach Nuclear Plant, LRA format, and their approach in applying "NUREG-1 801, Generic Aging Lessons Learned (GALL) Report," for identification of plant components consistent with GALL programs. A significant topic discussed at the meeting was pressurized thermal shock (PTS). The NMC representatives stated that they have an exemption request under staff review for the use of a revised PTS calculation methodology based on the B&W proposed "Master Curve." The NMC representatives stated that they would rely on the approval of this methodology for the PTS calculations of the Point Beach reactor vessels for license renewal. The NMC representatives stated that NMC plans to submit the renewal application to the NRC on February 27, 2004. The slides that were presented in the meeting are provided in Enclosure 3.

go

~~~"- /RA/

Michael J ProjecMnager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-266 and 50-301

Enclosures:

As stated cc w/encl: See next page

Point Beach Nuclear Plant, Units 1 and 2 cc:

Jonathan Rogoff, Esquire Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Mr. Richard R. Grigg President and Chief Operating Officer Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 Manager, Regulatory Affairs Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Mr. Jeffery Kitsembel Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Douglas E. Cooper Senior Vice President - Group Operations Palisades Nuclear Plant Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, Ml 49043 Mr. Fred Emerson Nuclear Energy Institute 1776 I Street, NW., Suite 400 Washington, DC 20006-3708 Mr. Alfred J. Cayia Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241

ATTENDANCE LIST NRC STAFF MEETING WITH NUCLEAR MANAGEMENT COMPANY, LLC (NMC)

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 JANUARY 20, 2004 Name Russ Wells Pat Burke Dominic So Robert Vincent Jim Knorr Roger Newton Hansraj Ashar Ken Chang Jack Cushing Bill Dam Johnny Eads Joe Golla Mark Hartzman Steve Hoffman Stacey Imboden Peter J. Kang Pao-Tsin Kuo Samson Lee Chang Li Y.C. Li Mark Lintz Michael Morgan Neil Ray Deirdra Spaulding Jim Strnisha Ram Subbaratnam Steven West Organization Constellation Nuclear Management Company, LLC (NMC), Monticello Nuclear Management Company, LLC (NMC), Palisades Nuclear Management Company, LLC (NMC), Palisades Nuclear Management Company, LLC (NMC), Pt. Beach Nuclear Management Company, LLC (NMC), Pt. Beach NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC NRC

AGENDA NRC MEETING WITH NUCLEAR MANAGEMENT COMPANY CONCERNING LICENSE RENEWAL APPLICATION FOR POINT BEACH NUCLEAR PLANT UNITS 1 AND 2 JANUARY 20, 2004 (Times are approximate)

1. Introduction of license renewal participants 2:00 p.m. - 2:05 p.m.
2. Original license expiration and plant history 2:05 p.m. - 2:15 p.m.
3. Introduction of the Point Beach renewal application 2:15 p.m. - 2:50 p.m.
4. Related licensing subjects 2:50 p.m. - 3:00 p.m
5. Plant schedule for next two years.

3:00 p.m. - 3:15 p.m.

6. Potential review tool availability 3:15 p.m. - 3:25 p.m.
7. NRC review schedule 3:25 p.m. - 3:35 p.m.
8. Questions 3:35 p.m. - 3:45 p.m.
9. Discussion of final submittal configuration - needs of the NRC 3:45 p.m. - 3:55 p.m.
10. Public participation 3:55 p.m. - 4:00 p.m.

PUBLIC MEETING SLIDES

1/19/2004 Agenda PBNP License Renewal Application NRC/NMC

1)

Introduction of License Renewal Participants 2:00 p.m. - 2:05 p.m.

2)

Original License Expiration and Plant History 2:05 p.m. - 2:15 p.m.

3)

Introduction of Point Beach Application 2:15 p.m. - 2:50 p.m.

4)

Related licensing subjects 2:50 p.m. - 3:00 p.m

5)

Plant schedule for next two years.

3:00 p.m. - 3:15 p.m.

6)

Potential review tool availability 3:15 p.m.- 3:25 p.m.

7)

NRC Review Schedule for PBNP LRA 3:25 p.m. - 3:35 p.m.

8)

Questions 3:35 p.m. - 3:45 p.m.

9)

DiscussIon of final submittal configuration needs of the NRC 3:45 p.m. - 3:55 p.m.

10) Public Questions 3:55 pm - 4:00 p.m.

2 I

1/19/2004 Point Beach History Unit 1 License Expiration October 5, 2010 Unit 2 License Expiration March 8, 2013 Original design with 20 MWe Combustion Turbine and 2 EDGs Spent fuel pool re-racks 1976 and 1979 TMI Modifications 1980 - 1985 3

Point Beach History (Continued)

Unit 1 New Steam Generators -1982 Replaced # 1, 2, 3 and 5 Feedwater Heaters 1986 Replaced all Turbine Condenser Tubing 1986 Reactor Coolant Up flow Modification for Both Units Late 1980s New Low Pressure Turbine Rotors with Integral Hubs 1990 2 New Safety Related Station Batteries Installed 1990 4

2

1/19/2004 Point Beach History (Continued)

Dry Fuel Storage Option Licensed - 1993 Unit 2 New Steam Generators - 1996 2 Additional Safety Related Diesels Installed -1995 Baffle Barrel Bolt Replacement Unit 2.- 1997 Standardized Technical Specifications - 2001 5

Point Beach History (Continued)

Modified Water Intake Structure - 2001 Service Water System Upgrade - 2002 Additional Vessel Material Sample Installed in Unit 2

- 2002 Stabilized and Abandoned the Retention Pond -2002 6

3

1/19/2004 Point Beach Nuclear Plant License Renewal Application Use of Standard Format with enhanced level of detail and cross referencing in electronic form Section 1 (31 Pages) o Administrative section O

Legal discussions o Acronym list 7

Point Beach Nuclear Plant License Renewal Application (Continued)

Section 2 (283 Pages) o System descriptions o

System function descriptions O

Links to FSAR o

Links to Drawings O

Lists of component types and intended functions 4

1/19/2004 Point Beach Nuclear Plant License Renewal Application (Continued)

Section 3 Aging Management Review Results (489 Pages) (Definition of "Consistent With")

O Tables Follow New Standard Format o

Plant Specific Notes in Table 2 o

SRP Section Questions Covered in Table I or Text o

Past Precedence Information May be Available Later 9

Point Beach Nuclear Plant License Renewal Application (Continued)

Section 4 0

0 0

TLAA (99 Pages)

Detail with Results for each TLAA Some Analysis Under Review by NRC Some TLAA Exemptions Necessary 10 5

1/19/2004 Point Beach Nuclear Plant License Renewal Application (Continued)

Appendix A FSAR Supplement (51 Pages) o Existing FSAR Section Revisions o

New LR related FSAR section Program Descriptions TLAA Descriptions 11 Point Beach Nuclear Plant License Renewal Application (Continued)

Appendix B Program Details (248 Pages) o Inclusion of 10 Attribute Discussion for all Programs o

Inclusion of Consistent with GALL Details o

Program Commitments Identified 12 6

1/19/2004 Point Beach Nuclear Plant License Renewal Application (Continued)

Appendix Appendix 0

Appendix 0

0 0

C (Not Used)

D Technical Specification Changes None Identified E

Environmental Report (300 Pages)

Category 2 Evaluations New and Significant information SAMA 13 Point Beach Nuclear Plant License Renewal Application (Continued)

Other application considerations.

O Drawings and FSAR are provided as "for information" not on the docket. (They are included in the review CD copies with cross references hyperlinked throughout the application.)

O Other Review tools can be provided in a like manner.

14 7

1/19/2004 Related Licensing Subjects O Master Curve O Leak Before Break o Power Uprating El Annual Update Schedule or Exemption 15 Next Two Years at PBNP o Early March 2004 INPO E&A O March 27 - May 11, 2004 Unit 1 Refueling 28 o July 2004 SSDI Scheduled o No Fall 2004 Refueling o Fall 2004 Fire Protection O Spring 2005 Unit 2 Refueling 27 - Reactor Vessel Head replacement O Fall 2005 Unit 1 Refueling 29 - Reactor Vessel Head Replacement 16 8

1/19/2004 Potential Review Tool Availability o Component type Subject to an AMR vs.

Equipment ID o Full version of Program Basis Documents O Past precedence reviews - Availability 17 NRC Review Schedule o Pilot Plant Experience O PBNP LRA level of detail impact o Improve NRC review efficiency

- fewer site visits 18 9

1/19/2004 Questions?

19 Final Configuration Needs o CD formats for review copies o CD formats for ADAMS needs o Quantity of CDs, Paper copies of LRA o Quantity of Ancillary Material and format needed

  • Drawings - Paper and/or CDs FSAR - CD and or Paper
  • Additional Review tools needed and format CD and or Paper

.20 10

1/19/2004 Questions from the Public 21 11

January 30, 2004 LICENSEE:

Nuclear Management Company, LLC (NMC)

FACILITY:

Point Beach, Units 1 and 2

SUBJECT:

SUMMARY

OF MEETING BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION (NRC) STAFF AND NUCLEAR MANAGEMENT COMPANY, LLC (NMC) REPRESENTATIVES TO DISCUSS THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION On January 20, 2004, the NRC staff met with members of Nuclear Management Company, LLC (NMC) in a public meeting to discuss NMC's plan for submitting a license renewal application (LRA) for the Point Beach Nuclear Plant, Units I and 2. The list of attendees is provided in, and the meeting agenda is provided in Enclosure 2.

NMC representatives discussed the features of the Point Beach Nuclear Plant, LRA format, and their approach in applying "NUREG-1 801, Generic Aging Lessons Learned (GALL) Report," for identification of plant components consistent with GALL programs. A significant topic discussed at the meeting was pressurized thermal shock (PTS). The NMC representatives stated that they have an exemption request under staff review for the use of a revised PTS calculation methodology based on the B&W proposed "Master Curve." The NMC representatives stated that they would rely on the approval of this methodology for the PTS calculations of the Point Beach reactor vessels for license renewal. The NMC representatives stated that NMC plans to submit the renewal application to the NRC on February 27, 2004. The slides that were presented in the meeting are provided in Enclosure 3.

/RA/

Michael J. Morgan, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-266 and 50-301

Enclosures:

As stated DISTRIBUTION:

See next page Accession No: ML DOCUMENT NAME:G :\\RLEP\\License Renewal Section-A\\Morgan\\Pt. Beach\\Pt. Beach Pre-App Meeting Summary (Rev. 1).wpd OFFICE:

LA:RLEP PM:RLEP SC:RLEP NAME:

MMorgan415K SLee4-L-l DATE:

01/,-3D/04 IJ 01/2O0O4'/'

01/3D/04 OFFICIAL RECORD COPY

DISTRIBUTION: Dated: January 30. 2004 Accession No: ML HARD COPY RLEP RF Project Manager E-MAIL:

PUBLIC J. Craig D. Matthews F. Gillespie C. Grimes RidsNrrDe E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair S. Black B. Boger D. Thatcher R. Pettis G. Galletti C. Li J. Moore R. Weisman M. Mayfield A. Murphy S. Smith (srs3)

S. Duraiswamy Y. L. (Renee) Li RLEP Staff W. Ruland D. Spaulding L. Raghavan A. Vegel, Rill T. Mensah OPA