December 2003 Monthly Operating Report for Browns Ferry, Units 1, 2, and 3
ML040340235
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 01/12/2004
From: Abney T
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML040340235 (9)


Text

Tennessee Valley Authority, Post Office Box 2000, Decatur, Alabama 35609-2000 January 12, 2003 U.S. Nuclear Regulatory Commission ATTN:

Document Control Desk Mail Stop:

OWFN, P1-35 Washington, D.C. 20555-0001 Gentlemen:

In the Matter of

)

Docket Nos. 50-259 Tennpssee Valley Authority

)

.50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN).-

DECEMBER 2003 MONTHLY OPERATING:REPORT The enclosure provides the December 2003 Monthly Operating Report (MOR) as required by.BFN Technical Specifications, Section 5.6.4..

If y6u have any questions concerning this report, please call me at (256) 729-2636.

Si cerely, T. E. Ab Manager of Lic si g:

and In ry Aff irs Enclocre cc:

page Pawted on cdW paw

U.S. Nuclear Regulatory Commission Page 2 January 12, 2003 Enclosure cc (Enclosure):

(Via NRC Electronic Distribution)

Mr. Kahtan N. Jabbour, Senior Project U.S. Nuclear Regulatory Commission One White Flint, North (MS.08G9).

Office of Nuclear Reactor Regulation 11555 Rockville Pike Rockville,.Maryland 20852-2738 NRC Resident Inspector Browns Ferry Nuclear Plant

.;10833 Shaw Road

. -Athens, Alabama 35611-6970 Regional Administrator U.S. Nuclear Regu-latory.,.Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street., S.W., Suite.-23T85.

Atlanta, Georgia 30303-8931 Manager

U.S. Nuclear Regulatory Commission Page 3 January 12, 2003 DTL:JEW:BAB Enclosure cc (Enclosure):

D. K. Baker, BR 3H-C A. S. Bhatnagar, PAB 1E-BFN M. J. Burzynski, BR 4X-C J. E. Maddox, LP 6A-C D. C. Olcsvary, LP 6A-C C. M. Root, PAB IG-BFN J. R. Rupert, NAB IA-BFN K. W. Singer, LP 6A-C M. D. Skaggs, POB 2C-BFN E. J. Vigluicci ET llA-K NSRB Support, LP 5M-C EDMS-K S:lic/submit/subs/MORdecember2003.doc

ENCLOSURE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)

MONTHLY OPERATING REPORT DECEMBER 2003 UNIT 1 DOCKET NUMBER 50-259 LICENSE NUMBER DPR-33 UNIT 2 DOCKET NUMBER 50-260 LICENSE NUMBER DPR-52 UNIT 3 DOCKET NUMBER 50-296 LICENSE NUMBER DPR-68

6 OPERATING DATA REPORT Docket No.

50-259 Unit Name BFN Unit 1 Date January 6, 2004 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period December 2003

1.

Design Electrical Rating (Net MWe):

1065

2.

Maximum Dependable Capacity (MWe-Net) 0 Month Yr-to-Date Cumulative*

3.

Number of Hours Reactor was Critical

4.

Hours Generator On-Line

5.

Unit Reserve Shutdown Hours

6.

Net Electrical Energy Generated (MWh) 0 0

59521 0

0 58267 0

0 0

0 0

53,796,427

  • Excludes hours under Administration Hold (June 1, 1985 to Present)

OPERATING DATA REPORT Docket No.

50-260 Unit Name BFN Unit 2 Date January 6, 2004 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period December 2003

1.

Design Electrical Rating (Net MWe):

2.

Maximum Dependable Capacity (MWe-Net) 1120 1118

3.

Number of Hours Reactor was Critical

4.

Hours Generator On-Line

5.

Unit Reserve Shutdown Hours

6.

Net Electrical Energy Generated (MWh)

Month Yr-to-Date Cumulative 744 7927 156,334 744 7889 153,651 0

0 0

847,394 8,369,222 153,521,948 E-2

OPERATING DATA REPORT Docket No.

50-296 Unit Name BFN Unit 3 Date January 6, 2004 Completed By J. E. Wallace Telephone (256) 729-7874 Reporting Period December 2003

1. Design Electrical Rating (Net MWe):
2.

Maximum Dependable Capacity (MWe-Net) 1120 1118

3.

Number of Hours Reactor was Critical

4.

Hours Generator On-Line

5.

Unit Reserve Shutdown Hours

6.

Net Electrical Energy Generated (MWh)

Month Yr-to-Date Cumulative 744 8476 113,724 744 8463 112,286 0

0 0

843,110 9,325,733 115,308,603 E-3

)

UNIT SHUTDOWNS REPORT MONTH: DECEMBER 2003 DOCKET NO:

UNIT NAME:

DATE:

COMPLETED BY:

50-259 BFN-1 January 6, 2004 J. E. Wallace (osM O79Q '7A Administrative hold to resolve various TVA and 1

.1 ___________

1 __________

1 1Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 2 Ntethlod 1-Manual 2-Manual Trip/Scram 3-Automatic Trip/Scram 4-Continuation Outage 5-Other (Explain)

SUMMARY

Unit 1 has been on administrative hold since June 1, 1985.

E-4

I UNIT SHUTDOWNS REPORT MONTH: DECEMBER 2003 DOCKET NO:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

hi Prevent mecirrer 50-260 BFN-2 January 6, 2004 J. E. Wallace (256) 729-7874 N/A I ______________

I ___________

I __________

1.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

iReason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 2 IMetliod 1-Manual 2-Manual Trip/Scram 3-Automatic Trip/Scram 4-Continuation Outage 5-Other (Explain)

SUMMUARY:

Unit 2 has operated at or near 100 percent available power E-5

UNIT SHUTDOWNS REPORT MONTH: DECEMBER 2003 DOCKET NO:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

50-296 BFN-3 January 6, 2004 J. E. Wallace (256) 729-7874 1Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Rcgulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 2 INlethod 1-Manual 2-Manual Trip/Scram 3-Automatic Trip/Scram 4-Continuation Outage 5-Olher (Explain)

SUMMARY

Unit 3 has operated at or near 100 percent available power.