ML040300171

From kanterella
Jump to navigation Jump to search
Correction to Technical Specifications Pages 3/4 8-23 Through 3/4 8-37
ML040300171
Person / Time
Site: Millstone Dominion icon.png
Issue date: 02/26/2004
From: Nerses V
NRC/NRR/DLPM/LPD1
To: Christian D
Dominion Nuclear Connecticut
Nerses V, NRR//DLPM, 415-1484
Shared Package
ML040360070 List:
References
Download: ML040300171 (5)


Text

February 26, 2004 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 3 - CORRECTION TO TECHNICAL SPECIFICATIONS PAGES 3/4 8-23 THROUGH 3/4 8-37

Dear Mr. Christian:

During the comparison review of the U.S. Nuclear Regulatory Commission (NRC) Technical Specification (TS) Authority File to a copy of the Millstone Power Station, Unit No. 3 TSs provided by your staff, it was identified that pages 3/4 8-23 through 3/4 8-37 were deleted from your TSs but were still included in the NRC Authority File.

By application dated July 24, 1990, you had requested the deletion of pages 3/4 8-24 through 3/4 8-37 because previous text is being moved forward and pages which were left intentionally blank were being removed. Amendment No. 64, dated March 9, 1992, was issued to address this application and moved TS 3.8.4.2.1 from page 3/4 8-28 to 3/4 8-21, TS 3.8.4.2.2 from page 3/4 8-32 to 3/4 8-22, and TS 3.8.4.3 from page 3/4 8-37 to 3/4 8-23; however it did not discuss the removal of pages 3/4 8-24 through 3/4 8-37. Page 3/4 8-23 was subsequently removed by Amendment No. 121, dated November 29, 1995.

This letter is issued to provide a record for the removal of pages 3/4 8-24 through 3/4 8-37. It is understood that the Millstone Power Station, Unit No. 3 TSs already indicated that these pages have been removed. We apologize for any inconvenience this may have caused.

Sincerely,

/RA/

Victor Nerses, Senior Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-423 cc w/encls: See next page

Millstone Power Station Unit 3 cc:

Lillilan M. Cuoco, Esquire Senior Counsel Dominion Resources Services, Inc.

Rope Ferry Road Waterford, CT 06385 Edward L. Wilds, Jr., Ph.D.

Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT 06106-5127 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 First Selectmen Town of Waterford 15 Rope Ferry Road Waterford, CT 06385 Mr. P. J. Parulis Manager - Nuclear Oversight Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. W. R. Matthews Senior Vice President - Nuclear Operations Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. John Markowicz Co-Chair Nuclear Energy Advisory Council 9 Susan Terrace Waterford, CT 06385 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terrys Plain Road Simsbury, CT 06070 Senior Resident Inspector Millstone Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357 Mr. G. D. Hicks Director - Nuclear Station Safety and Licensing Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870 Mr. William D. Meinert Nuclear Engineer Massachusetts Municipal Wholesale Electric Company Moody Street P.O. Box 426 Ludlow, MA 01056 Mr. J. Alan Price Site Vice President Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. Chris Funderburk Director, Nuclear Licensing and Operations Support Dominion Resources Services, Inc.

5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. David W. Dodson Licensing Supervisor Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385

Millstone Power Station Unit 3 cc:

Mr. S. E. Scace Assistant to the Site Vice President Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. M. J. Wilson Manager - Nuclear Training Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. A. J. Jordan, Jr.

Director - Nuclear Engineering Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. S. P. Sarver Director - Nuclear Station Operations and Maintenance Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385

February 26, 2004 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 3 - CORRECTION TO TECHNICAL SPECIFICATIONS PAGES 3/4 8-23 THROUGH 3/4 8-37

Dear Mr. Christian:

During the comparison review of the U.S. Nuclear Regulatory Commission (NRC) Technical Specification (TS) Authority File to a copy of the Millstone Power Station, Unit No. 3 TSs provided by your staff, it was identified that pages 3/4 8-23 through 3/4 8-37 were deleted from your TSs but were still included in the NRC Authority File.

By application dated July 24, 1990, you had requested the deletion of pages 3/4 8-24 through 3/4 8-37 because previous text is being moved forward and pages which were left intentionally blank were being removed. Amendment No. 64, dated March 9, 1992, was issued to address this application and moved TS 3.8.4.2.1 from page 3/4 8-28 to 3/4 8-21, TS 3.8.4.2.2 from page 3/4 8-32 to 3/4 8-22, and TS 3.8.4.3 from page 3/4 8-37 to 3/4 8-23; however it did not discuss the removal of pages 3/4 8-24 through 3/4 8-37. Page 3/4 8-23 was subsequently removed by Amendment No. 121, dated November 29, 1995.

This letter is issued to provide a record for the removal of pages 3/4 8-24 through 3/4 8-37. It is understood that the Millstone Power Station, Unit No. 3 TSs already indicated that these pages have been removed. We apologize for any inconvenience this may have caused.

Sincerely,

/RA/

Victor Nerses, Senior Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-423 cc w/encls: See next page DISTRIBUTION:

PUBLIC OGC PDI-2 R/F VNerses GHill (2)

CRaynor BMcDermott, RI Tech Branch DRoberts ADAMS Accession Numbers: Letter: ML040300171 OFFICE PDI-2/PM PDI-2/LA PDI-2/(A)SC NAME VNerses CRaynor DRoberts DATE 02/17/04 02/17/04 02/18/04 OFFICIAL RECORD COPY

CORRECTIONS TO TECHNICAL SPECIFICATION PAGES BASED ON NRC STAFF REVIEW OF THE LICENSE AUTHORITY FILE FOR MILLSTONE POWER STATION, UNIT 3 DOCKET 50-423 Remove the following pages in the technical specifications.

Remove Insert 3/4 8-23 3/4 8-24 3/4 8-25 3/4 8-26 3/4 8-27 3/4 8-28 3/4 8-29 3/4 8-30 3/4 8-31 3/4 8-32 3/4 8-33 3/4 8-34 3/4 8-35 3/4 8-36 3/4 8-37