Letter Sequence RAI |
---|
|
|
MONTHYEARML0402204892004-01-28028 January 2004 University of Missouri at Columbia - Request for Additional Information License Amendment on Definitions, Limiting Conditions for Operations and Reporting Requirements Project stage: RAI 2004-01-28
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000186/20242022024-11-0404 November 2024 The Curators of the University of Missouri – U.S. Nuclear Regulatory Commission Safety Inspection Report 05000186/2024202 IR 05000186/20244102024-11-0404 November 2024 The Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Security Inspection Report No. 05000186/2024410 (Public) 05000186/LER-2024-003, University of Missouri Research Reactor, Specification Deviation from Technical Specification 3.2.g.212024-10-25025 October 2024 University of Missouri Research Reactor, Specification Deviation from Technical Specification 3.2.g.21 ML24281A1322024-10-0404 October 2024 University of Missouri - Notification of NIST Award 60NANB23D160 NEPA Catex ML24270A0992024-10-0101 October 2024 Examination Confirmation Letter No. 50-186/Ol-25-01, University of Missouri - Columbia ML24142A1432024-08-27027 August 2024 Examination Result Letter No. 50-186/OL-24-02, University of Missouri - Columbia ML24142A1422024-08-27027 August 2024 Examination Report Letter No. 50-186/OL-24-02, University of Missouri - Columbia ML24184A1132024-07-0202 July 2024 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.10.d IR 05000186/20242012024-05-29029 May 2024 The Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2024201 05000186/LER-2024-001, Written Communication as Required by by LER 2024-001-00 for University of Missouri Research Reactor Technical Specification 6.6.c(3) Re Deviation from Technical Specification 3.1 0.d2024-05-23023 May 2024 Written Communication as Required by by LER 2024-001-00 for University of Missouri Research Reactor Technical Specification 6.6.c(3) Re Deviation from Technical Specification 3.1 0.d ML24081A1332024-04-0202 April 2024 University of Missouri-Columbia (MURR) – Change of Facility Project Manager ML24064A1922024-03-0101 March 2024 Federal Funding for the Conversion of the University of Missouri-Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel ML24044A1162024-03-0101 March 2024 Examination Confirmation Letter No. 50-186/OL-24-02, University of Missouri-Columbia ML24059A4412024-02-28028 February 2024 Univ. of Missouri - Columbia - Submittal of Annual Operating Report Technical Specification 6.6.e IR 05000186/20232022023-12-12012 December 2023 The Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2023202 ML23198A0222023-08-29029 August 2023 Examination Report Letter No. 50-186/OL-23-02, University of Missouri - Columbia ML23198A0232023-08-29029 August 2023 Examination Result Letter No. 50-186/OL-23-02, University of Missouri-Columbia ML23221A1172023-08-0303 August 2023 Written Communication as Specified by 10 CFR 50.4(b)(4) Regarding the Submittal of the Physical Security Plan for the University of Missouri Research Reactor as a Part of the Process to Renew Amended Facility Operating License R-103 ML23213A0592023-08-0101 August 2023 Written Communication as Specified by University of Missouri Research Reactor Technical Specification 6.6.2(d) Regarding a Permanent Change in the Facility Organization Involving the Executive Director IR 05000186/20232012023-07-31031 July 2023 The Curators of the University of Missouri – U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2023201 ML23186A2132023-07-31031 July 2023 Examination Confirmation Letter No. 50-186/OL-23-03, University of Missouri - Columbia 05000186/LER-2023-003, University of Missouri - Columbia Research Reactor, Written Communication as Required Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.b2023-06-0606 June 2023 University of Missouri - Columbia Research Reactor, Written Communication as Required Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.b ML23124A0422023-05-0808 May 2023 Examination Confirmation Letter 50-186/OL-23-02, University of Missouri - Columbia ML23103A0742023-04-10010 April 2023 University of Missouri, Columbia Research Reactor, Shipment of Radioactive Material Shipment Identifier MURR 23-01 Highway Route Controlled Quantity ML23024A2772023-04-0707 April 2023 Cover Letter for the Security Inspection Report for the University of Missouri (Public) - October 2022 ML23089A3162023-03-29029 March 2023 Letter Notifying Univ. of Missouri That Us Dept. of Energy Funding Will Not Be Available in Fiscal Year 2023 to Complete the Conversion of MURR to LEU Fuel ML23087A1142023-03-29029 March 2023 Examination Results Letter No. 50-186/OL-23-01, University of Missouri - Columbia ML23087A1132023-03-29029 March 2023 Examination Report No. 50-186/OL-23-01, University of Missouri-Columbia ML23055B1372023-02-24024 February 2023 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e IR 05000186/20222022023-02-23023 February 2023 The Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2022202 - Cover Letter and Enclosure ML23031A0132023-02-14014 February 2023 Examination Confirmation Letter No. 50-186/OL-23-01, University of Missouri-Columbia ML23017A2072023-01-13013 January 2023 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 6.1.f ML22349A0422022-12-0808 December 2022 Written Communication as Specified in 10 CFR 50.54(b)(5) Regarding Changes to the University of Missouri-Columbia Research Reactor Facility Emergency Plan Without Prior Commission Approval Pursuant to 10 CFR 50.54(q)(3) ML22314A2102022-11-0909 November 2022 Written Communication as Required by Technical Specification 6.6.d(2), Other Reports, Regarding a Change in University of Missouri-Columbia Research Reactor Organization Involving the Reactor Facility Director ML22304A0042022-10-27027 October 2022 University of Missouri - Columbia, Shipment of Radioactive Material, Highway Route Controlled Quantity ML22291A0322022-10-14014 October 2022 University of Missouri Written Communication as Required by 10 CFR 73, Appendix G Regarding a Deviation from the MURR Physical Security Plan ML22290A0042022-10-12012 October 2022 University of Missouri-Columbia Research Reactor, Reportable Event Report Pursuant to 20.2201(a)(ii) Regarding Loss of Licensed Material During Shipment IR 05000186/20222012022-06-14014 June 2022 The Curators of the University of Missouri - U.S. NRC Routine Inspection Report No. 05000186/2022201 ML22158A0792022-06-0606 June 2022 Submittal of Revised Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML22097A0592022-04-0707 April 2022 Approval for Spent Nuclear Fuel Highway Route Application - NRC Route No. 182D - Docket Number 050-0186 ML22088A0782022-03-25025 March 2022 Univ. of Missouri, Federal Funding for the Conversion of the Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel IR 05000186/20212032022-03-0202 March 2022 The Curators of the University of Missouri U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2021203 ML22056A5162022-02-25025 February 2022 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML22038A6012022-02-0808 February 2022 Acceptance for Spent Nuclear Fuel Highway Route Application NRC No. 182D-Docket No. 050-0186 ML22013B1412022-01-21021 January 2022 Examination Confirmation Letter No. 50-186-OL-22-02, University of Missouri-Columbia ML21327A3042021-11-23023 November 2021 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.f.6 05000186/LER-2021-004, University of Missouri Research Reactor, Deviation from Technical Specification 3.2.g.102021-11-23023 November 2021 University of Missouri Research Reactor, Deviation from Technical Specification 3.2.g.10 ML21298A1972021-10-25025 October 2021 University of Missouri-Columbia Research Reactor - Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.g.6 ML21253A2482021-09-23023 September 2021 Examination Confirmation Letter No. 50-186/OL-22-01, University of Missouri Columbia ML21221A3252021-08-0909 August 2021 University of Missouri-Columbia Research Reactor, Written Communication as Required by Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specifications 3.2.a 2024-08-27
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML17284A0432017-11-0101 November 2017 University of Missouri at Columbia - Request for Additional Information License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Research Reactor (CAC A11010/05000186/L-2017- ML17234A7332017-09-0707 September 2017 University of Missouri at Columbia - Request for Additional Information License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Research Reactor ML16239A4252016-09-0707 September 2016 University of Missouri at Columbia - Request for Additional Information Regarding the Proposed Technical Specifications for the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor ML16216A1222016-08-24024 August 2016 University of Missouri at Columbia - Request for Additional Information Financial Information for Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor ML16083A0252016-03-23023 March 2016 University of Missouri at Columbia - Clarifications Needed to Nuclear Regulatory Commission Staff Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 ML16028A2552016-02-0808 February 2016 University of Missouri at Columbia; Request for Additional Information Updated Financial Information for Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor (Tac No. Me1580) ML16008A9052016-01-12012 January 2016 MURR Iodine La RAI Proprietary Determination Letter ML15337A1752015-12-17017 December 2015 University of Missouri at Columbia Clarifications Needed to NRC Staff Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor ML15307A0752015-11-19019 November 2015 Enclosuuniversity of Missouri at Columbia - Attachment Public Request for Additional Information ML15307A0732015-11-19019 November 2015 University of Missouri at Columbia - Cover Letter Request for Additional Information Regarding the License Amendment Request to Modify the Technical Specifications to Produce Radiochemical Sodium Iodine at the University of Missouri at Colu ML15280A3142015-10-28028 October 2015 University of Missouri at Columbia Research Reactor Request for Additional Information Regarding the Proposed Technical Specifications for the Murr License Renewal Review ML15098A6482015-04-17017 April 2015 University of Missouri at Columbia - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor ML14324A7072014-12-0303 December 2014 Request for Additional Information Regarding the MURR License Renewal Review (Updated Info 11/19/2014) ML1210101092012-04-12012 April 2012 University of Missouri, Columbia - Request for Additional Information, License Amendment Dated August 24, 2011 Safety Limits ML1117515642011-07-0101 July 2011 University of Missouri - Columbia - Request for Additional Information License Amendment, Center Test Hole (TAC N0. ME1876) ML1035606622010-12-27027 December 2010 University of Missouri - Columbia - Request for Additional Information License Amendment Center Test Hole ML1011602662010-06-0101 June 2010 University of Missouri at Columbia - Request for Additional Information License Renewal, Safety Analysis Report, 45-Day Response Questions ML1011602442010-05-0606 May 2010 University of Missouri at Columbia - Request for Additional Information License Renewal, Safety Analysis Report, Complex Questions ML1010407262010-04-20020 April 2010 University of Missouri at Columbia, Request for Additional Information Regarding License Renewal, National Historic Preservation Act ML0936200962009-12-30030 December 2009 University of Missouri at Columbia, RAI, Environmental Report ML0936200822009-12-30030 December 2009 University of Missouri at Columbia, RAI, License Renewal References ML0917402832009-07-10010 July 2009 University of Missouri at Columbia - Request for Additional Information License Renewal ML0823907242008-08-26026 August 2008 University of Missouri at Columbia - Request for Additional Information License Amendment on Fueled Experiment Conditions ML0722203632007-08-10010 August 2007 University of Missouri at Columbia - Request for Additional Information License Amendment on Fueled Experiment Conditions (TAC MD 5782) ML0527104062005-10-0707 October 2005 RAI Letter - Security Measures - Butler ML0402204892004-01-28028 January 2004 University of Missouri at Columbia - Request for Additional Information License Amendment on Definitions, Limiting Conditions for Operations and Reporting Requirements ML0316401192003-06-23023 June 2003 Univ of Missouri - Columbia -- Request for Additional Information Security Plan 2017-09-07
[Table view] |
Text
January 28, 2004 Mr. Ralph Butler, Director Research Reactor Center University of Missouri-Columbia Research Park Columbia, MO 65211
SUBJECT:
UNIVERSITY OF MISSOURI AT COLUMBIA REQUEST FOR ADDITIONAL INFORMATION RE: LICENSE AMENDMENT ON DEFINITIONS, LIMITING CONDITIONS FOR OPERATIONS AND REPORTING REQUIREMENTS (TAC NO. MB7181)
Dear Mr. Butler:
We are continuing our review of your amendment request for Amended Facility License No. R-103 for the University of Missouri - Columbia Research Reactor which you submitted on December 16, 2002. During our review of your amendment request, questions have arisen for which we require additional information and clarification. Please provide responses to the enclosed request for additional information within 90 days of the date of this letter. In accordance with 10 CFR 50.30(b), your response must be executed in a signed original under oath or affirmation. Following receipt of the additional information, we will continue our evaluation of your amendment request.
If you have any questions regarding this review, please contact me at 301-415-1127.
Sincerely,
/RA/
Alexander Adams, Jr., Senior Project Manager Research and Test Reactors Section New, Research and Test Reactors Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No. 50-186
Enclosure:
As stated cc w/enclosure: Please see next page
University of Missouri-Columbia Docket No. 50-186 cc:
University of Missouri Associate Director Research Reactor Facility Columbia, MO 65201 A-95 Coordinator Division of Planning Office of Administration P.O. Box 809, State Capitol Building Jefferson City, MO 65101 Mr. Ron Kucera, Director Intergovernmental Cooperation and Special Projects Missouri Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102 Mr. Tim Daniel Homeland Security Suite 760 P.O. Box 809 Jefferson City, MO 65102 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611
January 28, 2004 Mr. Ralph Butler, Director Research Reactor Center University of Missouri-Columbia Research Park Columbia, MO 65211
SUBJECT:
UNIVERSITY OF MISSOURI AT COLUMBIA REQUEST FOR ADDITIONAL INFORMATION RE: LICENSE AMENDMENT ON DEFINITIONS, LIMITING CONDITIONS FOR OPERATIONS AND REPORTING REQUIREMENTS (TAC NO. MB7181)
Dear Mr. Butler:
We are continuing our review of your amendment request for Amended Facility License No. R-103 for the University of Missouri - Columbia Research Reactor which you submitted on December 16, 2002. During our review of your amendment request, questions have arisen for which we require additional information and clarification. Please provide responses to the enclosed request for additional information within 90 days of the date of this letter. In accordance with 10 CFR 50.30(b), your response must be executed in a signed original under oath or affirmation. Following receipt of the additional information, we will continue our evaluation of your amendment request.
If you have any questions regarding this review, please contact me at 301-415-1127.
Sincerely,
/RA/
Alexander Adams, Jr., Senior Project Manager Research and Test Reactors Section New, Research and Test Reactors Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No. 50-186
Enclosure:
As stated cc w/enclosure: Please see next page DISTRIBUTION:
PUBLIC RNRP\R&TR r/f PMadden TDragoun MMendonca AAdams JLyons OGC EHylton SHolmes CBassett WEresian PIsaac PDoyle DHughes KWitt RidsNrrDrip GHill (2) (T5-C3)
ADAMS ACCESSION NO.: ML040220489 TEMPLATE #: NRR-088 OFFICE RNRP:LA RNRP:PM RNRP:SC NAME EHylton:rdr AAdams PMadden DATE 01/ 23 /04 01/ 23 /04 01/ 26 /04 C = COVER E = COVER & ENCLOSURE N = NO COPY
OFFICIAL RECORD COPY REQUEST FOR ADDITIONAL INFORMATION UNIVERSITY OF MISSOURI RESEARCH REACTOR DOCKET NO. 50-186
- 1. In your application for LCO action requirements the statement is made that the purpose of the action requirement is to allow the reactor to be operated for a brief period of time while actions are being taken to place the reactor in a safe shutdown condition.
However the evaluation section of your application states that the purpose of the brief period of time is to allow restoration of an inoperable system or component to operable status, to allow restoration of parameters within specified limits, or to place the reactor in a safe shutdown mode. Please address this inconsistency in your application.
- 2. You state in your application that the specified time limits of the action requirements are applicable from the point in time it is identified that an LCO is not met. For each of the LCOs that you have proposed action requirements, what is the maximum time that the component could be inoperable before the component failure is identified? For components where the component failure is not immediately identified by the operator, what is the safety significance of having the component inoperable for the stated period of time without identification? Should these failures be reportable to NRC?
- 3. Most of your proposed action statements state that the purpose of the action statement is to provide time for prompt remedial action. However, your proposed TS 3.10 does not contain the wording limitation about prompt remedial action. Please clarify the intent of the action statements for proposed TS 3.10.
- 4. In your proposed changes to the definition of abnormal occurrences you changed the introduction of the definition from An abnormal occurrence is any of the following to An abnormal occurrence is any of the following which occurs during reactor operation.
The limitation of an abnormal occurrence to only during reactor operation is not consistent with ANS 15.1 section 6.6.2. For example, the NRC would want significant fuel cladding degradation to be reported, no matter when the problem occurs. Please justify your proposed TS.
- 5. Your proposed changes to TS 1.1.b. narrows abnormal occurrences from all TSs in your current TSs to LCOs established in section 3.0 in your proposed TSs. Please describe how records of violations, if they should occur, of surveillance requirements, design features and administrative controls that are not abnormal occurrences or reportable for other reasons, will be maintained and how NRC will be made aware of these violations.
- 6. Your proposed changes to TS 6.1.h. differ in some aspects from ANS-15.1. Your proposed TS 6.1.h.(1) does not contain the requirement give in ANS-15.1 section 6.6.1(2) to promptly report safety limits violations to management. Your proposed TSs 6.1.h.(2) and 6.1.h.(3) do not contain the requirement given in ANS-15.1 section 6.6.2(2) to promptly report releases of radiation above allowed limits and reportable occurrences to management. Your proposed TS 6.1.h.(3) does not contain the action contained in ANS-15.1 section 6.6.1(1) that reactor conditions shall be returned to normal or the reactor shutdown. Please address these differences by amending your proposed TSs to be consistent with ANS-15.1 or provide justification for the differences. Your
proposed TS 6.1.h. has initial notifications going to the NRC Operations Center. Please note that 10 CFR 50.36(7)(ii) also requires notification to the Administrator of the appropriate NRC Regional Office.
- 7. Please review your proposed replacement TS pages for changes not discussed in your amendment application in addition to those noted below. The following areas have text that is different between your replacement TS pages and your current TSs but have not been discussed in your application:
TS 3.3, page 1. TS Heading Safety System or Measuring Channel says Safety System of Measuring Channel in your replacement page.
TS 3.3, page 2. Pool Coolant Flow contains the limits for the 50% capacity heat exchanger leg. This has been eliminated in your replacement page. This change has been marked on your replacement page but not discussed and justified in your application.
TS 3.3, page 3. Footnote 1 in the TS states corresponding to the flow value in the table. while the replacement page states corresponding to the flow valve in the table.
TS 3.4, page 3, Regulating Blade Position. In the TS the number required has footnote (2) in all three operating modes. Your proposed replacement page does not have footnote (2) for the number required in Mode I.
TS 6.1.h.(5)(a)(1). You added a ) after the word characteristics.
Please address these changes and any other that you identify.
- 8. TS 6.1.c.(2) refers to an unreviewed safety question pursuant to 10 CFR 50.59.
Changes to 10 CFR 50.59 have eliminated the term unreviewed safety question.
Please consider revising this TS to be consistent with the revised 10 CFR 50.59.