Submittal of Calculations Discussed During December 17, 2003, Regulatory Conference on Preliminary White Finding, NRC Integrated IR 055000440-03-006
ML033650368
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 12/23/2003
From: Kanda W
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, NRC/RGN-III
References
IR-03-006, PY-CEI/NRR-2758L
Download: ML033650368 (1)


Text

FENOC Perry Nuclear Power Plant 1">

10 Center Road FirstEnergy Nuclear Operating Company Perry, Ohio 44081 440-280-5579 William R. Kanda Fax: 440-280-8029 Vice President - Nuclear December 23, 2003 PY-CEI/NRR-2758L United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Perry Nuclear Power Plant Docket No. 50-440 Regulatory Conference on Preliminary White Finding (AV 05000440/2003006-03)

NRC Integrated Inspection Report 05000440/2003006 Ladies and Gentlemen:

Attached are calculations EA-254, Revision 0, "Emergency Service Water System Pump Shaft Coupling Failure Analysis" and PSA-039, Revision 1, "PSA Assessment for ESW Pump A Unavailability." These documents were discussed during a Regulatory Conference conducted on December 17, 2003 at Lisle, IL. The handout provided during the conference is also attached.

There are no regulatory commitments contained in this letter or its attachments. If you have questions or require additional information, please contact Mr. Vernon K. Higaki, Manager - Regulatory Affairs, at (440) 280-5294.

Very truly yours, alRiamR.

nda Attachments cc: NRC Project Manager NRC Resident Inspector NRC Region IlIl State of Ohio l ' Dsof