Notice of Significant Licensee Meeting with Nuclear Management Co., Re Predecisional Enforcement Conference
ML033580385
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 12/24/2003
From: Anton Vegel
Division Reactor Projects III
To:
References
EA-03-181
Download: ML033580385 (3)


Text

December 24, 2003 EA-03-181 NOTICE OF SIGNIFICANT LICENSEE MEETING THIS MEETING IS OPEN TO PUBLIC ATTENDANCE Name of Licensee: Nuclear Management Company, LLC Name of Facility: Point Beach Nuclear Plant, Units 1 and 2 Docket Nos: 50-266; 50-301 Date and Time of Meeting: 1:00 p.m. (CST), Tuesday, January 13, 2004 Location of Meeting: U. S. Nuclear Regulatory Commission Region III Office, Suite 255 801 Warrenville Road Lisle, Illinois Video Conference Location: U.S. Nuclear Regulatory Commission Room O-5B6, One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738

Contact:

Deirdre Spaulding, (301) 415-2928, e-mail:

DWS@nrc.gov Purpose of Meeting: The meeting is a predecisional enforcement conference to discuss an apparent violation associated with the licensee changing the Emergency Action Level scheme used at Point Beach such that it reduced the effectiveness of the Emergency Plan without requesting and receiving prior NRC approval. The meeting is being held to obtain information to assist the NRC in making an enforcement decision. The apparent violation is described in a letter to the licensee, dated December 2, 2003 (Accession No. ML033371234), which is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Category: This is a Category 1 meeting. The public is invited to observe this meeting and will have an opportunity to speak with the NRC after the business portion of the meeting, but before the meeting is adjourned.

Notice of Significant Licensee Meeting NRC Attendees: James Caldwell, Regional Administrator Steve Reynolds, Acting Director, Division of Reactor Projects Cindy Pederson, Director, Division of Reactor Safety Cindy Carpenter, Deputy Director, Division of Inspection Program Management, NRR Anton Vegel, Chief, Branch 7, Division of Reactor Projects Ken Riemer, Chief, Plant Support Branch, Division of Reactor Safety Others as designated Licensee Attendees: Douglas Cooper, Senior Vice-President Fred Cayia, Site Vice-President Renee Milner, Emergency Planning Manager Others as designated NOTE: Attendance at this meeting by NRC personnel should be made known to Mike Kunowski via e-mail (MAK3) or by telephone ((630) 829-9618) by COB on Friday, January 9, 2004.

Approved by: /RA by Patrick L. Louden for/

Anton Vegel, Chief Branch 7 Division of Reactor Projects

Notice of Significant Licensee Meeting Distribution:

F. Congel (FJC), Director, Office of Enforcement D. Dambly (DCD), Assistant General Counsel for Material Litigation and Enforcement, OGC B. Sheron (BWS), Associate Director for Projects Licensing and Technical Review, NRR L. Marsh (LBM), Director, Division of Licensing Project Management, NRR L. Raghaven (LXR1), NRR D. Weaver (DWW), Region III Coordinator, OEDO W. Ruland (WHR), Project Directorate, Division of Licensing Project Management, NRR D. Spaulding (DWS), Project Manager, Project Directorate, Division of Licensing and Project Management, NRR G. Grant (GEG), Director Regional Administrator, RIII S. Reynolds (SAR1), Acting Director, Division of Reactor Projects, RIII P. Hiland (PLH), Acting Deputy Director, Division of Reactor Projects, RIII C. Pederson (CDP1), Director, Division of Reactor Safety, RIII R. Caniano (RJC1), Deputy Director, Division of Reactor Safety, RIII DRP Branch Chief SRI, Point Beach DRS Branch Chiefs (RNG, DEH, RDL, KXR)

B. Clayton (HBC), Enforcement/Investigations Officer, RIII R. Lickus (RML2), State Liaison Officer, RIII PMNS RIII Public Affairs (VTM, RJS2)

J. Kweiser (JRK1), ORA P. Buckley (PLB1), ORA OEMAIL OEWEB