Text
Stephen A. Byrne Senior Vice President, Nuclear Operations 803.345.4622 A SCANA COMPANY November 3, 2003 Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555 Attention: Director, Office of Resource Management Ladies and Gentlemen:
Subject:
VIRGIL C. SUMMER NUCLEAR STATION DOCKET NO. 50/395 OPERATING LICENSE NO. NPF-12 OCTOBER MONTHLY OPERATING REPORT Enclosed is the October 2003 Monthly Operating Report for the Virgil C. Summer Nuclear Station Unit No. 1. This submittal is made in accordance with the requirements of Technical Specifications, Section 6.9.1.10.
If there are any questions, please call me at your convenience.
Very truly yours, Stephen A. Byrne SAB/mbb Attachment C:
J. B. Archie T. G. Eppink (w/o Attachment)
R. J. White L. A. Reyes K. R. Cotton T. D. Gatlin NRC Resident Inspector K. M. Sutton Paulette Ledbetter W. R. Higgins INPO Records Center J&H Marsh & McLennan William G. Wendland (ANI)
Pat Haught (Westinghouse)
C. W. Adams NSRC RTS (0-L-99-0350-1)
File (818.03-1, RR 4100)
DMS (RC-03-0228)
,-.----T
!J'E0([
SCE&G I Virgil L.Summer Nuclear Station
- P.O. Box 8B. Jenkinsyille, South Carolina 29065.T(803)345.5209.wwwwscna.nom
T'.
Director, Office of Resource Management October Monthly Operating Report RC-03-0228 Page 1 of 4 ATTACHMENT I AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 501395 UNIT V. C. SUMMER I DATE November 1, 2003 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 October 2003 AVERAGE DAILY POWER LEVEL DAY DAY I
2 3
4 5
6 7
8 9
10 11 12 13 14 15 16 (Mwe-Net) 977 978 977 978 979 981 974 855 824 766 0
0 0
0 0
0 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 AVERAGE DAILY POWER LEVEL (Mwe-Net) 0 0
0 0
0 0
0 0
0 0
0 0
0 0
0
Director, Office of Resource Management October Monthly Operating Report RC-03-0228 Page 2 of 4 ATTACHMENT II OPERATING DATA REPORT DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE November 1, 2003 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 OPERATING STATUS 1
Reporting Period:
Gross Hours in Reporting Period:
2 Currently Authorized Power Level (MWt):
Max. Depend. Capacity (MWe-Net):
Design Electrical Rating (MWe-Net):
3 Power Level to Which Restricted (If Any) (MWe-Net):
4 Reasons for Restrictions:
October 2003 744 2900 966 972.7 N/A N/A THIS MONTH YR TO DATE CUMULATIVE 5
6 7
8 9
10 11 12 13 14 15 16 17 18 Number of Hours Reactor Critical Reactor Reserve Shutdown Hours Hours Generator On Line Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MWH)
Gross Electrical Energy (MWH)
Net Electrical Energy Generated (MWH)
Reactor Service Factor Reactor Availability Factor Unit Service Factor Unit Availability Factor Unit Capacity Factor (Using MDC)
Unit Capacity Factor (Using Design)
Unit Forced Outage Rate 242.7 0.0 240.2 0.0 664724 232330 222954 32.6 32.6 32.3 32.3 31.0 30.8 0.0 6725.4 0.0 6716.7 0.0 19399542 6812930 6547773 92.2 92.2 92.1 92.1 92.9 92.3 1.1 145874.7 0.0 143987.1 0.0 390229323 132038819 126198472 83.9 83.9 82.8 82.8 79.8 78.7 3.0 19 Shutdowns Scheduled Over Next 6 Months (Type, Date, & Duration of Each):
Refueling Outage, October 11, 2003, 37 Days 20 If Shutdown at End of Report Period, Estimated Date of Startup: 11/17/03 21 Units in Test Status (Prior to Commercial Operation):
N/A
Director, Office of Resource Management October Monthly Operating Report RC-03-0228 Page 3 of 4 ATTACHMENT III UNIT SHUTDOWNS AND POWER REDUCTION DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE November 1, 2003 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 September 2003 NO.
DATE TYPE DURATION REASON METHOD CORRECTIVE ACTION/COMMENTS 2
10/11/2003 S
503.8 C
1 Complete Refueling I
REASON A: Equipment Failure B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error H: Other (Explain) 2 METHOD 1: Manual 2: Manual Trip/Scram 3: Automatic Trip/Scram 4: Continuation (Use Initial Date) 5: Power Reduction (Duration 0.0) 9: Other (Explain)
SUMMARY
Director, Office of Resource Management October Monthly Operating Report RC-03-0228 Page 4 of 4 ATTACHMENT IV NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO. 50/395 UNIT V. C. SUMMER I DATE November 1, 2003 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 September 2003 At the beginning of the month the plant was operating at 100% power. Power was reduced to 85% on October 8th @ 06:44 to support main steam safety valve testing. On October 11 h @ 00:10 the 14t refueling outage began with the opening of the main generator breaker. Reactor shut down was completed and mode 3 entered at 02:43 on the 11'h. The plant remained shut down for the remainder of the month.