'7 43 November 4, 2003 DOCKETED UNITED STATES OF AMERICA USNRC NUCLEAR REGULATORY COMMISSION November 12, 2003 (11:25AM)
BEFORE THE COMMISSION OFFICE OF SECRETARY RULEMAKINGS AND ADJUDICATIONS STAFF In the Matter of.
)
~Docket No. 50-336-OLA-2 Dominion Nuclear Connecticut, Inc.
)
)
(Millstone Power Station,
)
Unit No. 2)
)
ANSWER OF DOMINION NUCLEAR CONNECTICUT, INC.
TO MOTION OF CONNECTICUT COALITION AGAINST MILLSTONE FOR RECONSIDERATION OF CLI-03-14 On November 3, 2003, the Connecticut Coalition Against Millstone ("CCAM")
filed with the Nuclear Regulatory Commission ("Commission") a "Motion for Reconsideration" of the Commission's recent decision in this matter, CLI-03-14.1 It is well established that reconsideration petitions must establish an error in a Commission decision, based on an elaboration or refinement of an argument already made, an overlooked controlling decision or principle of law, or a factual clarification. See, e.g., Dominion Nuclear Conn., Inc. (Millstone Nuclear Power Station, Units 2 & 3), CLI-02-1, 55 NRC 1, 2 (2002); Central Elec. Pover Coop.
(Virgil C. Summer Nuclear Station, Unit 1), CLI-81-26, 14 NRC 787, 790 (1981). Petitions for reconsideration "should not be used merely to 're-argue matters that the Commission already
[has] considered' but rejected." Millstone, CLI-02-1, 55 NRC at 2; citing Advanced Medical Systems, Inc. (One Factory Row, Geneva, Ohio 44041), CLI-93-24,38 NRC 187, 188 (1993).
See Dominion Nuclear Conn., Inc. (Millstone Power Station, Unit 2), CLI-03-14, 58 NRC _ (slip op. Oct. 23, 2003).
Ie(/n
-5sEcy C
s E c 1
Contrary to these longstanding precedents, CCAM has not pointed to any factual or legal error in CLI-03-14, and merely restates, without "elaboration or refinement," the conclusory and meritless arguments that it has previously made before both the Commission and the Licensing Board in this proceeding. Such arguments do not merit reconsideration under 10 C.F.R. § 2.771.
Respectfully submitted, David A. Repka Brooke D. Poole WINSTON & STRAWN LLP 1400 L Street, NW Washington, D.C. 20005-3502 Lillian M. Cuoco Dominion Resources Services, Inc.
Millstone Power Station Rope Ferry Road Waterford, CT 06385 Counsel for DOMINION NUCLEAR CONNECTICUT, INC.
Dated in Washington, D.C.
this 4th day of November 2003 2
N UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of:
Dominion Nuclear Connecticut, Inc.
(Millstone Power Station, Unit No. 2)
)
)
)
)
)
)
Docket No. 50-336-OLA-2 CERTIFICATE OF SERVICE I hereby certify that copies of "ANSWER OF DOMINION NUCLEAR CONNECTICUT, NC. TO MOTION OF CONNECTICUT COALITION AGAINST MILLSTONE FOR RECONSIDERATION OF CLI-03-14" in the captioned proceeding have been served on the following by electronic mail, this 4th day of November 2003. Additional service has also been made this same day by deposit in the United States mail, first class, as shown below.
Nils J. Diaz, Chairman U.S. Nuclear Regulatory Commission Mail Stop 0-16C1 Washington, DC 20555-0001 Jeffrey S. Merrifield, Commissioner U.S. Nuclear Regulatory Commission Mail Stop 0-16CI Washington, DC 20555-0001 Administrative Judge Ann M. Young, Chair Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop T-3F23 Washington, DC 20555-0001 e-mail: amyenrc.gov Edward McGaffigan, Commissioner U.S. Nuclear Regulatory Commission Mail Stop 0-16C1 Washington, DC 20555-0001 Office of Commission Appellate Adjudication U.S. Nuclear Regulatory Commission Mail Stop 0-16C1 Washington, DC 20555-0001 Administrative Judge Richard F. Cole Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop T-3F23 Washington, DC 20555-0001 e-mail: rfcl~nrc.gov 1
Administrative Judge Thomas S. Elleman Atomic Safety and Licensing Board Panel 5207 Creedmoor Road, #101 Raleigh, NC 27612 e-mail: ellemaneeos.ncsu.edu Nancy Burton, Esq.
147 Cross Highway Redding Ridge, CT 06876 e-mail: nancyburtonesqeaol.com Office of the Secretary U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Rulemakings and Adjudications Staff (original + two copies) e-mail: HEARINGDOCKET~nrc.gov Ann P. Hodgdon, Esq.
Office of the General Counsel Mail Stop O-15D21 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 e-mail: OGCMailCenter(0nrc.gov aphenrc.gov David A. Repka Counsel for DNC, Inc.
2 DC:330897.1