Task Order No. 017 Under Contract No. NRC-03-03-037
ML033000089
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 09/12/2003
From: King D
NRC/ADM/DCPM
To: Beckman V
Beckman & Associates
References
Job Code J3020, NRC-03-03-037
Download: ML033000089 (2)


Text

4

. "nC A7 p.

Sep 12 03 10:59a beckman associates i/'+-u c-.

zcr-i-e0J 20:09 RDM DCPM P.

C PEo~ UNITED STATES t Aims Act NUCLEAR REGULATORY COMMISSION

  • @ < WASHINGTON, D.C. 205S.O0o1 at, a,0SE S:P k 1 tonSE Beckman and Associates, Inc.

ATTN: Ms. Vicki Beckman 1071 State Route 136 Belle Vernon. PA 15012

SUBJECT:

TASK ORDER NO. 017 'OAVIS BESSE CORRECTIVE ACTION TEAM INSPECTION" UNDER CONTRACT NO. NRC-03-03-037

Dear Ms. Beckman:

This confirms the verbal authorization that was provided to Beckman and Associates, Inc.

(BAA), effective August 8, 2003, to begin work under the subject task order, with a temporary ceiling of $35,000.00.

In accordance with Section G.5, Task Order Procedures, of the subjoct contract. this letter definitizes the subject task order The effort shall be performed in accordance with the enclosed Statement of Work.

Task Order No. 017 shall be in effect from August 8, 2003. through September 15, 2003, with a cost ceiling of $82,454.15. The amount of $80,040:53 represents the estimated reimbursable costs, and the amount of $2.413.62 represents the fixed fee.

Accounting data for Task Order No. 017 is as follows:

B&R No.: 320-15-103-142 Job Code: J-3020 BOC: 252A.

APPN No.: 31X0200.320 FFS#: NRR03037017 Oblig. Armt.: $80,000.00 Incremental funds in the amount of $80,000.00 are being obligated under this task order. The obligated amount shall, at no time, exceed the task order ceiling. When, and if, the amount(s) paid and payable to the Conlractor hereunder shall equal the obligated amount the Contractor shall not be obligated to continue performance of the work unless and until the Contracting Officer shall increase the amount obligated with respect to this task order. Any work undertaken by the Contractor in excess of the obligated amount specified above is done so at the Contractor's sole risk.

The followin individuals ares idered10be essential to the successful performance for work hereunder. _. . The Contractor agrees that suc* personnel shall not be rmoved rom tne effourt-UiT= task order without compliance with Contract Clause H.4, Key Personnel.

The issuance of this task order does not emend any terms or conditions of the subject contract.

TFlADIRTr 11.11if LHIL -

I Anuannq liumt.1t1i ROM

. S'a 12 03 10: 59a beckman associates 724-872-6347 I ' rtr-1I1-2e03 2: 09 RDM DCPM

-P.

P.02 Your contacts during the course of this task order are:

Technical Matters: Donald P. Norkin Project Officer (301) 415-2954 Contractual Matters: Mona C. Selden Contract Specialist (301) 4S-7907 Acceptance of Task Order No. 017 should b made by having an official, authorized to bind your organization, execute three copies of this document in the space provided and return two copies to the Contract Specialist. You should retain the third copy for your records.

Sincerely Donald A. King, Contracting Officer Contract Management Center 1 Division of Contracts Office of Administration

Enclosure:

Statement of Work 017 NAME TITLE DATE