Orders Modifying License for Revised Design Basis Threat and for Training and Physical Fitness Enhancements Applicable to Security Force Personnel (TAC Nos. MB9293 and MB9397)
ML032970135
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 11/19/2003
From: Marsh L
NRC/NRR/DLPM
To: Clemens R
Omaha Public Power District
Fretz R, NRR/DLPM, 415-1324
References
TAC MB9293, TAC MB9397
Download: ML032970135 (4)


Text

November 19, 2003 Mr. Richard P. Clemens Division Manager, Nuclear Assessments Omaha Public Power District 444 South 16th Street Mall Omaha, NE 68102-2247

SUBJECT:

ORDERS MODIFYING LICENSE FOR REVISED DESIGN BASIS THREAT AND FOR TRAINING AND PHYSICAL FITNESS ENHANCEMENTS APPLICABLE TO SECURITY FORCE PERSONNEL (TAC NOS. MB9293 AND MB9397)

Dear Mr. Clemens:

On April 29, 2003, the U.S. Nuclear Regulatory Commission (NRC or the Commission) issued Orders modifying the operating license for Fort Calhoun Station, Unit 1 to: (1) require compliance with a revised design basis threat (DBT); (2) implement new security force personnel training and physical fitness requirements; and (3) prescribe compensatory measures related to fitness-for-duty enhancements applicable to security force personnel.

When it issued the Orders, the Commission recognized that you voluntarily and responsibly implemented additional security measures following the events of September 11, 2001.

However, as part of the Commissions review of the security and safeguards program, the Commission determined that enhancements to the DBT, as currently specified in Title 10 of the Code of Federal Regulations (10 CFR), Section 73.1(a), were required. The NRC further determined that security force personnel tactical and firearms proficiency, physical fitness, and fitness-for-duty requirements needed to be enhanced. The Commission also concluded that, based on the current threat environment, these Orders were to be effective immediately.

The Orders require responses and actions within specified time frames. This letter addresses your response to the Orders pertaining to the revised DBT and the new security force personnel training and physical fitness requirements. The Commission replied to your response to the fitness-for-duty Order in separate correspondence, dated July 10, 2003.

Section III.A.1 of the Order implementing new security force personnel training and physical fitness requirements states that licensees must comply with the new requirements described in the Order, except to the extent that more stringent requirements are set forth in the licensees security plan and security training and qualifications plan.Section III.A.1 of the DBT Order requires licensees to submit revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, based on the revised DBT, to the Commission for review and approval no later than April 29, 2004. The Order requires licensees to implement the revised physical security plans, revised safeguards contingency plans, and revised security force personnel training and qualification plans no later than October 29, 2004.Section IV of both Orders noted that, in accordance with

R. Clemens 10 CFR 2.202, licensees must submit an answer to the Orders and may request a hearing on the Orders, within thirty-five (35) days of the date of the Orders and, where good cause is shown, consideration would be given to extend the time to request a hearing.

The Orders also required licensees to notify the Commission within thirty-five (35) days if:

(1) the licensee was unable to comply with the requirements specified in the attachments to the Orders; (2) compliance with the requirements is unnecessary; (3) implementation of any of the requirements would result in a violation of the provisions of any Commission regulation of the facility license; or (4) implementation of any of the requirements described in the attachments to the Orders would adversely impact safe operation of the facility.Section III.C.1 of the security force personnel training and physical fitness Order required licensees to submit to the Commission, within thirty-five (35) days of the date of the Order, a schedule for achieving compliance with each requirement described in Attachment 2 to the Order.

By letters dated June 3, 2003, you submitted responses to the Orders for the Fort Calhoun Station. In your responses, you indicated that you consented to the DBT and security force personnel training Orders and did not request a hearing. The NRC staff has reviewed your responses, and finds that you have satisfied the thirty-five (35) day reporting requirements for both Orders.

In your response to the DBT Order, you also requested that the NRC provide clarification of five DBT-related issues described in the safeguards attachment to a letter from Mr. Colvin, President and CEO of the Nuclear Energy Institute, to Chairman Diaz dated May 16, 2003. By letter dated September 25, 2003, the NRC provided you a copy of Chairman Diazs response to Mr. Colvin, dated July 18, 2003, which clarified the five DBT-related issues.

Please contact Robert Fretz at 301-415-1324, if you have any other questions on these issues.

Sincerely,

/RA/

Ledyard B. Marsh, Director Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-285 cc: See next page

R. Clemens 10 CFR 2.202, licensees must submit an answer to the Orders and may request a hearing on the Orders, within thirty-five (35) days of the date of the Orders and, where good cause is shown, consideration would be given to extend the time to request a hearing.

The Orders also required licensees to notify the Commission within thirty-five (35) days if:

(1) the licensee was unable to comply with the requirements specified in the attachments to the Orders; (2) compliance with the requirements is unnecessary; (3) implementation of any of the requirements would result in a violation of the provisions of any Commission regulation of the facility license; or (4) implementation of any of the requirements described in the attachments to the Orders would adversely impact safe operation of the facility.Section III.C.1 of the security force personnel training and physical fitness Order required licensees to submit to the Commission, within thirty-five (35) days of the date of the Order, a schedule for achieving compliance with each requirement described in Attachment 2 to the Order.

By letters dated June 3, 2003, you submitted responses to the Orders for the Fort Calhoun Station. In your responses, you indicated that you consented to the DBT and security force personnel training Orders and did not request a hearing. The NRC staff has reviewed your responses, and finds that you have satisfied the thirty-five (35) day reporting requirements for both Orders.

In your response to the DBT Order, you also requested that the NRC provide clarification of five DBT-related issues described in the safeguards attachment to a letter from Mr. Colvin, President and CEO of the Nuclear Energy Institute, to Chairman Diaz dated May 16, 2003. By letter dated September 25, 2003, the NRC provided you a copy of Chairman Diazs response to Mr. Colvin, dated July 18, 2003, which clarified the five DBT-related issues.

Please contact Robert Fretz at 301-415-1324, if you have any other questions on these issues.

Sincerely,

/RA/

Ledyard B. Marsh, Director Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-285 cc: See next page DISTRIBUTION:

PUBLIC TMarsh DLPM Project Directors AHowell, Region IV OGC CHolden DLPM Section Chiefs PD Reading Files ACRS JClifford DLPM Project Managers GTracy, NSIR RFretz VNerses DLPM Licensing Assistants JPeralta, NSIR ADAMS Accession Number: ML032970135

  • See previous concurrence OFFICE PDI-2/LPM PDI-2/LA PDI-2/SC* NSIR/DNS* PDI/D* DLPM/D NAME RFretz CRaynor JClifford GTracy CHolden LMarsh DATE 11/13/03 11/13/03 10/30/03 11/03/03 11/07/03 11/07/03 OFFICIAL RECORD COPY

Ft. Calhoun Station, Unit 1 cc:

Winston & Strawn Mr. Richard P. Clemens ATTN: James R. Curtiss, Esq. Division Manager - Nuclear Assessments 1400 L Street, N.W. Omaha Public Power District Washington, DC 20005-3502 Fort Calhoun Station P.O. Box 550 Chairman Fort Calhoun, NE 68023-0550 Washington County Board of Supervisors P.O. Box 466 Mr. R. T. Ridenoure Blair, NE 68008 Division Manager - Nuclear Operations Omaha Public Power District Mr. John Kramer, Resident Inspector Fort Calhoun Station FC-2-4 Adm.

U.S. Nuclear Regulatory Commission Post Office Box 550 P.O. Box 310 Fort Calhoun, Nebraska 68023-0550 Fort Calhoun, NE 68023 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Ms. Sue Semerera, Section Administrator Nebraska Health and Human Services Systems Division of Public Health Assurance Consumer Services Section 301 Cententiall Mall, South P.O. Box 95007 Lincoln, NE 68509-5007 Mr. David J. Bannister, Manager Fort Calhoun Station Omaha Public Power District Fort Calhoun Station FC-1-1 Plant P.O. Box 550 Fort Calhoun, NE 68023-0550 Mr. John B. Herman Manager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550 Fort Calhoun, NE 68023-0550 Mr. Daniel K. McGhee Bureau of Radiological Health Iowa Department of Public Health 401 SW 7th Street, Suite D Des Moines, IA 50309