Public Meeting Between USNRC Oversight Panel and FirstEnergy Nuclear Operating Company October 7, 2003
2 Davis-Besse Oversight Panel - Public Meeting October 2003 PURPOSES OF THIS MEETING
- Inform the Public of the NRCs Oversight Panel Activities
- Discuss Licensees Progress on Implementing the Return to Service Plan
3 Davis-Besse Oversight Panel - Public Meeting October 2003 AGENDA
- Introduction and Opening Remarks
- Summary of September 10th Public Meetings
- Discussion of Significant NRC Activities Since September 10th Public Meeting
- Licensee Presentation on the Status of Their Return to Service Plan
- Adjourn NRC meeting with FENOC
<break>
- Public Comments and Questions of NRC
- Adjourn Meeting
4 Davis-Besse Oversight Panel - Public Meeting October 2003
SUMMARY
OF SEPTEMBER 10, 2003 PUBLIC MEETING Topics Discussed
- Plant Response to Loss of Transmission Grid
- Plant Status
- Closure of Technical Issues
- Operational Readiness Assessment Plan
- Quality Assurance Oversight
- Actions to Anchor Long-Term Improvement
- Transcripts of the September 10, 2003 meetings will be available on our web site. http://www.nrc.gov/
5 Davis-Besse Oversight Panel - Public Meeting October 2003 SIGNIFICANT NRC ACTIVITIES SINCE SEPTEMBER 10 PUBLIC MEETING
- Issued Integrated Inspection Report 03-017
- Conducted Public Meeting with FENOC on Safety Culture October 1, 2003
- Confirmatory Action Letter Updated
6 Davis-Besse Oversight Panel - Public Meeting October 2003 CONTINUING NRC ACTIVITIES
- Safety Culture / Safety Conscious Work Environment Inspection
- Normal Operating Pressure (NOP) Inspection
- Resident Inspection
- Restart Checklist
7 Davis-Besse Oversight Panel - Public Meeting October 2003 UPCOMING NRC ACTIVITIES Public Meeting to Discuss the Results of the Corrective Action Team Inspection and System Health Inspection Public Meeting at NRC Headquarters to Discuss the High Pressure Injection Pump Design Modifications Review of Inaccurate / Incomplete Required Records and Submittals Inspection Restart Readiness Assessment Team Inspection Backlog Inspection
8 Davis-Besse Oversight Panel - Public Meeting October 2003 PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION PORT CLINTON, OHIO October 7th, 2003, 7:00 pm EDT Purpose of Meeting:
Inform the Public of the NRCs Oversight Panel Activities
9 Davis-Besse Oversight Panel - Public Meeting October 2003
- Brief Public With Results of Afternoon Meeting with FENOC
- Receive Comments and Questions From Public To ensure we hear all comments, please limit comments or questions to 5 minutes each. We will follow the format from previous meetings where we start with local members of the public.
GOALS