September 4, 2003 Mr. Michael Kansler, President Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601
SUBJECT:
RESPONSE TO ORDER FOR COMPENSATORY MEASURES RELATED TO ACCESS AUTHORIZATION (TAC NOS. MB7415, MB7423, MB7424, MB7450, AND MB7478)
Dear Mr. Kansler:
On January 7, 2003, the U.S. Nuclear Regulatory Commission (NRC or Commission) issued Orders to holders of licenses for operating nuclear power reactors, for the implementation of compensatory measures (CMs) related to access authorization. On January 27, 2003, Entergy Nuclear Operations, Inc., licensee for the James A. FitzPatrick Nuclear Power Plant, Indian Point Nuclear Generating Stations, Unit Nos. 2 and 3, Pilgrim Nuclear Power Station, and on behalf of Entergy Nuclear Vermont Yankee, LLC, licensee for the Vermont Yankee Nuclear Power Station, submitted its written response to the Order.
The NRC staff has completed its review of your response. Based on that review, the NRC staff finds that your response to the January 7, 2003, Order is acceptable and responsive to the Order.
Please remember, pursuant to Section III.C.2 of the Order, you are to report to the Commission, in accordance with Title 10 of the Code of Federal Regulations, Section 50.4, when you have achieved full compliance with the requirements described in Attachment 2 to the Order. The NRC will determine the effectiveness of your implementation of the CMs through onsite inspections.
If you have any questions about this letter, please call Mr. Christopher Gratton at 301-415-1055.
Sincerely,
/RA/
Richard J. Laufer, Chief, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-333, 50-247, 50-286 50-293, and 50-271 cc: See next page
September 4, 2003 Mr. Michael Kansler, President Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601
SUBJECT:
RESPONSE TO ORDER FOR COMPENSATORY MEASURES RELATED TO ACCESS AUTHORIZATION (TAC NOS. MB7415, MB7423, MB7424, MB7450, AND MB7478)
Dear Mr. Kansler:
On January 7, 2003, the U.S. Nuclear Regulatory Commission (NRC or Commission) issued Orders to holders of licenses for operating nuclear power reactors, for the implementation of compensatory measures (CMs) related to access authorization. On January 27, 2003, Entergy Nuclear Operations, Inc., licensee for the James A. FitzPatrick Nuclear Power Plant, Indian Point Nuclear Generating Stations, Unit Nos. 2 and 3, Pilgrim Nuclear Power Station, and on behalf of Entergy Nuclear Vermont Yankee, LLC, licensee for the Vermont Yankee Nuclear Power Station, submitted its written response to the Order.
The NRC staff has completed its review of your response. Based on that review, the NRC staff finds that your response to the January 7, 2003, Order is acceptable and responsive to the Order.
Please remember, pursuant to Section III.C.2 of the Order, you are to report to the Commission, in accordance with Title 10 of the Code of Federal Regulations, Section 50.4, when you have achieved full compliance with the requirements described in Attachment 2 to the Order. The NRC will determine the effectiveness of your implementation of the CMs through onsite inspections.
If you have any questions about this letter, please call Mr. Christopher Gratton at 301-415-1055.
Sincerely,
/RA/
Richard J. Laufer, Chief, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-333, 50-247, 50-286 50-293, and 50-271 cc: See next page DISTRIBUTION:
PUBLIC C. Gratton R. Laufer J. Clifford S. Little J. Zwolinski T. Marsh C. Holden G. Vissing P. Milano M. Burrell C. Nolan T. Tate J. Trapp R. Pulsipher E. Hackett OGC ACRS B. Smith, EDO C. Raynor Adams Accession No.: ML032470005
- See Previous Concurrence OFFICE PDII-2/PM PDI-2/LA PD1-1/LA NSIR PDI-1/SC NAME CGratton:as CRaynor SLittle SW for CNolan RLaufer DATE 6/27/2003 7/30/2003 7/30/2003 8/25/2003 8/26/2003 OFFICIAL RECORD COPY
Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Indian Point Nuclear Generating Unit Nos. 2 & 3, and FitzPatrick Nuclear Power Plant cc:
Page 1 of 5 Resident Inspector U. S. Nuclear Regulatory Commission Pilgrim Nuclear Power Station Post Office Box 867 Plymouth, MA 02360 Chairman, Board of Selectmen 11 Lincoln Street Plymouth, MA 02360 Chairman, Duxbury Board of Selectmen Town Hall 878 Tremont Street Duxbury, MA 02332 Office of the Commissioner Massachusetts Department of Environmental Protection One Winter Street Boston, MA 02108 Office of the Attorney General One Ashburton Place 20th Floor Boston, MA 02108 Dr. Robert M. Hallisey, Director Radiation Control Program Commonwealth of Massachusetts Executive Offices of Health and Human Services 174 Portland Street Boston, MA 02114 Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. John M. Fulton Assistant General Counsel Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Steve Brennion Supt., Regulatory & Industry Affairs Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road, M/S 1 Plymouth, MA 02360-5508 Mr. Jack Alexander Manager, Reg. Relations and Quality Assurance Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5599 Mr. David F. Tarantino Nuclear Information Manager Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5599 Ms. Jane Perlov Secretary of Public Safety Executive Office of Public Safety One Ashburton Place Boston, MA 02108 Mr. Stephen J. McGrail, Director Attn: James Muckerheide Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399 Chairman Nuclear Matters Committee Town Hall 11 Lincoln Street Plymouth, MA 02360 Mr. William D. Meinert Nuclear Engineer Massachusetts Municipal Wholesale Electric Company P.O. Box 426 Ludlow, MA 01056-0426
Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Indian Point Nuclear Generating Unit Nos. 2 & 3, and FitzPatrick Nuclear Power Plant cc:
Page 2 of 5 Mr. Gary Taylor Chief Executive Officer Entergy Operations 1340 Echelon Parkway Jackson, MS 39213 Mr. John Herron Sr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Michael A. Balduzzi Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. William J. Riggs Director, Nuclear Assessment Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Bryan S. Ford Manager, Licensing Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Dan Pace Vice President, Engineering Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Randall Edington Vice President, Operations Support Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. John Kelly Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Ms. Charlene Faison Manager, Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Director of Oversight Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Senior Resident Inspector U.S. Nuclear Regulatory Commission Pilgrim Nuclear Power Station 600 Rocky Hill Road Mail Stop 66 Plymouth, MA 02360-5508 Ms. Stacey Lousteau Treasury Department Entergy Services, Inc.
639 Loyola Avenue, Mail Stop L-ENT-15E New Orleans, LA 70113 Mr. David R. Lewis Shaw, Pittman, Potts & Trowbridge 2300 N Street, N.W.
Washington, DC 20037-1128 Ms. Christine S. Salembier, Commissioner Vermont Department of Public Service 112 State Street Montpelier, VT 05620-2601 Mr. Michael H. Dworkin, Chairman Public Service Board State of Vermont 112 State Street Montpelier, VT 05620-2701
Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Indian Point Nuclear Generating Unit Nos. 2 & 3, and FitzPatrick Nuclear Power Plant cc:
Page 3 of 5 Chairman, Board of Selectmen Town of Vernon P.O. Box 116 Vernon, VT 05354-0116 Mr. Michael Hamer Operating Experience Coordinator Vermont Yankee Nuclear Power Station 320 Governor Hunt Road Vernon, VT 05354 G. Dana Bisbee, Esq.
Deputy Attorney General 33 Capitol Street Concord, NH 03301-6937 Ms. Deborah B. Katz Box 83 Shelburne Falls, MA 01370 Mr. Raymond N. McCandless Vermont Department of Health Division of Occupational and Radiological Health 108 Cherry Street Burlington, VT 05402 Mr. Gautam Sen Manager, Licensing Entergy Nuclear Vermont Yankee, LLC P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Resident Inspector Vermont Yankee Nuclear Power Station U. S. Nuclear Regulatory Commission P.O. Box 176 Vernon, VT 05354 Director, Massachusetts Emergency Management Agency ATTN: James Muckerheide 400 Worcester Rd.
Framingham, MA 01702-5399 Jonathan M. Block, Esq.
Main Street P.O. Box 566 Putney, VT 05346-0566 Mr. Jay K. Thayer Site Vice President Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Manager, Licensing Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Mr. Ken L. Graesser BWR SRC Consultant 38832 N. Ashley Drive Lake Villa, IL 60046 Mr. Jim Sniezek BWR SRC Consultant 14601 Layhill Road Silver Spring, MD 20906 Mr. Ron Toole BWR SRC Consultant 605 West Horner Street Ebensburg, PA 15931
Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Indian Point Nuclear Generating Unit Nos. 2 & 3, and FitzPatrick Nuclear Power Plant cc:
Page 4 of 5 Mr. Fred Dacimo Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 295 Broadway, Suite 2 P.O. Box 249 Buchanan, NY 10511-0249 Mr. Christopher Schwarz General Manager, Plant Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 295 Broadway, Suite 2 P.O. Box 249 Buchanan, NY 10511-0249 Mr. James Comiotes Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.
Indian Point Energy Center 295 Broadway, Suite 2 P.O. Box 249 Buchanan, NY 10511-0249 Mr. John McCann Manager, Licensing Entergy Nuclear Operations, Inc.
Indian Point Energy Center 295 Broadway, Suite 2 P. O. Box 249 Buchanan, NY 10511-0249 Senior Resident Inspector, Indian Point 2 U. S. Nuclear Regulatory Commission 295 Broadway, Suite 1 P.O. Box 38 Buchanan, NY 10511-0038 Senior Resident Inspector, Indian Point 3 U. S. Nuclear Regulatory Commission 295 Broadway, Suite 1 P.O. Box 337 Buchanan, NY 10511-0337 Mr. Peter R. Smith, Acting President New York State Energy, Research, and Development Authority Corporate Plaza West 286 Washington Avenue Extension Albany, NY 12203-6399 Mr. J. Spath, Program Director New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Paul Eddy Electric Division New York State Department of Public Service 3 Empire State Plaza, 10th Floor Albany, NY 12223 Mr. Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Mayor, Village of Buchanan 236 Tate Avenue Buchanan, NY 10511 Mr. Ray Albanese Executive Chair Four County Nuclear Safety Committee Westchester County Fire Training Center 4 Dana Road Valhalla, NY 10592 Mr. William DiProfio PWR SRC ConsultaNT 139 Depot Road East Kingston, NH 03827
Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Indian Point Nuclear Generating Unit Nos. 2 & 3, and FitzPatrick Nuclear Power Plant cc:
Page 5 of 5 Mr. Dan C. Poole PWR SRC Consultant 20 Captains Cove Road Inglis, FL 34449 Mr. William T. Russell PWR SRC Consultant 400 Plantation Lane Stevensville, MD 21666-3232 Alex Matthiessen Executive Director Riverkeeper, Inc.
25 Wing & Wing Garrison, NY 10524 Paul Leventhal The Nuclear Control Institute 1000 Connecticut Avenue NW Suite 410 Washington, DC, 20036 Karl Copeland Pace Environmental Litigation Clinic 78 No. Broadway White Plains, NY 10603 Jim Riccio Greenpeace 702 H Street, NW Suite 300 Washington, DC 20001 Mr. Theodore H. Sullivan Vice President, Operations Entergy Nuclear Operations, Inc.
James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 Mr. Brian OGrady General Manager, Plant Operations Entergy Nuclear Operations, Inc.
James A. FitzPatrick Nuclear Power Plant P.O. Box 100 Lycoming, NY 13093 Resident Inspector's Office U. S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093 Mr. William Maquire Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.
James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 Mr. Andrew Halliday Manager, Regulatory Compliance Entergy Nuclear Operations, Inc.
James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 Supervisor Town of Scriba Route 8, Box 382 Oswego, NY 13126 Oswego County Administrator Mr. Steven Lyman 46 East Bridge Street Oswego, NY 13126 Mr. J. Haley Security Manager James A. FitzPatrick Nuclear Power Plant Entergy Nuclear Operations, Inc.
268 Lake Road Lycoming, NY 13093