ML032460698

From kanterella
Jump to navigation Jump to search

Meeting Handout to Discuss Detroit Edisons Planned License Amendment Request for an Extended Power Uprate for Fermi 2
ML032460698
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 08/28/2003
From: Chernoff H
NRC/NRR/DLPM/LPD3
To:
References
TAC MC0277
Download: ML032460698 (9)


Text

NRC FORM 658 U.S. NUCLEAR REGULATORY COMMISSION (9-999)'

TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR IMMEDIATE PLACEMENT IN THE PUBLIC DOMAIN This form is to be filled out (typed or hand-printed) by the person who announced the meeting (i.e., the person who issued the meeting notice). The completed form, and the attached copy of meeting handout materials, will be sent to the Document Control Desk on the same day of the meeting; under no circumstances will this be done later than the working day after the meeting.

Do not Include proprietary materials.

DATE OF MEETING The attached document(s), which was/were handed out in this meeting, is/are to be placed 08/28/2003 in the public domain as soon as possible. The minutes of the meeting will be issued in the near future. Following are administrative details regarding this meeting:

Docket Number(s) 50-341 Plant/Facility Name Fermi 2 TAC Number(s) (if available)

MC0277 Reference Meeting Notice ML032230059 Purpose of Meeting (copy from meeting notice)

To discuss Detroit Edison's planned license amendment request for an extended power uprate for Fermi 2 NAME OF PERSON W1O ISSUED MEETING NOTICE TITLE Harold K. Chernoff Project Manager, Section 1 OFFICE NRR DIVISION DLP M BRANCH PD r-i Distribution of this form and attachments:

Docket File/Central File PUBLIC NRC FORM 658 (9-1999)

PRINTED ON RECYCLED PAPER This form was desOWe UskV WForms

a FERMI-2 EXTENDED POWER IIPRATE Kick-off Meeting; AiigUSL 2003 Ron McGee-Project Manager (734) 586-4774

Fermi-2 Extended Power Uprate 120 Power (%)

110 100 Core Flow

Fermi-2 Power Levels Case OLTP Current TPU LPU ELTR max

%OLTP 100 104.2 120 120 120 MWth 3293 3430 3952 3952 3952 Explanation Original Licensed Thermal Power Current Licensed Thermal Power Target Power Uprate License Power Uprate Maximum Licensable per CPPU

- ~~I-

-1 102010140i12004 20105 41 2013406 2007 0

1 Q 2 3Q 4Q Q 2Q 3 4Q -1~ I 2Q3Q1Q2 Q Q1Q2 Q4 I I __

_ i _. _. _.

Refuel Outage EPU Evaluations T/S Ammendment Submittal I 1 91 I I I 110 11 12 NRC Review I

MELLLA+ Evaluations I

4 -

I -

J -

4 -

4

.4. -

.4 -

4 -

i

_- I MELLLA+ Submittal Phase 1 Modifications installation I I I I

I I I I I I

Implement Phase 1 I

- i i

Phase 2 Modifications installation I I I I Implement Phase 2 I

I I I I I I

I Implement Phase 2 I I

Expected Significant Modifications Phase 1 MSR Replacements FIV monitoring for S/U testing

  • Instrumentation and setpoint changes
  • Simulator

Modifications (cont.)

Phase 2

  • Replace LP Turbine last stages in RF1 1
  • Replace FW Heaters 4 and 5 in RF1 1 or RF12
  • Install new HP Turbine Flowpath in RF12

Submittal lAW CLTR

  • No Increase in maximum Rx Dome pressure No Increase to maximum licensed core flow
  • No increase to MELLLA upper boundary No change to source term methodology No new fuel product line introduction No change to fuel cycle length No additions to currently licensed operational enhancements

Licensing Notes GE-14 fuel introduction will occur in RF-10 (currently have GE-1 1 fuel)

MELLLA+ submittal will not overlap EPU application

  • Requesting Positive Pressure allowance for NPSH Fluence Methodology update IAW RG 1.190 to meet previous commitment
  • AST update to match bases (currently under review)
  • Incorporating EPU Operating Experience