Reactor and Senior Reactor Operator Initial Examinations - Surry Power Station 05000280/2004-301 and 05000281/2004-301
ML032410147
Person / Time
Site: Surry  Dominion icon.png
Issue date: 08/29/2003
From: Ernstes M
Operator Licensing and Human Performance Branch
To: Christian D
Virginia Electric & Power Co (VEPCO)
References
50-280/04-301, 50-281/04-301
Download: ML032410147 (5)


See also: IR 05000280/2004301

Text

August 29, 2003

Virginia Electric and Power Company

ATTN: Mr. David A. Christian

Senior Vice President and

Chief Nuclear Officer

Innsbrook Technical Center

5000 Dominion Boulevard

Glen Allen, VA 23060

SUBJECT:

REACTOR AND SENIOR REACTOR OPERATOR INITIAL EXAMINATIONS -

SURRY POWER STATION 05000280/2004-301 AND 05000281/2004-301

Dear Mr. Christian:

In a telephone conversation on August 28, 2003, between Mr. David Llewellyn, Training

Manager, and Mr. Steven D. Rose, Operations Engineer, arrangements were made for the

administration of licensing examinations at Surry Power Station. The operating test is

scheduled for the weeks of February 23, 2004 and March 1, 2004. The written examination is

scheduled to be administered on February 18, 2004. The on-site preparatory week is

scheduled for the week of February 2, 2004.

The NRC will prepare the examinations based on the guidelines in Draft Revision 9 of NUREG-

1021, "Operator Licensing Examination Standards for Power Reactors." As agreed during the

telephone conversation, your staff will fill in the scenario details (ES-D-2) and the details of the

Job Performance Measures in accordance with the guidance in Draft Revision 9 of NUREG-

1021. Your staff has also agreed to make all of the copies of the examination materials prior to

administration. The NRC regional office will discuss with your staff any changes that might be

necessary before the examinations are administered. Your staff will be given the opportunity to

review the examinations during the week of January 12, 2004.

Your staff has already furnished the reference materials identified in Attachment 2 of ES-201 to

the NRC.

In order to conduct the requested written examinations and operating tests, it will be necessary

for your staff to provide adequate space and accommodations in accordance with ES-402, and

to make the simulation facility available on the dates noted above. In accordance with ES-302,

your staff should retain the original simulator performance data (e.g., system pressures,

temperatures, and levels) generated during the dynamic operating tests until the examination

results are final.

Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in

effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary senior reactor

operator license applications (Office of Management and Budget (OMB) approval number 3150-

VEPCO

2

0090), medical certifications (OMB approval number 3150-0024), and waiver requests (if any)

(OMB approval number 3150-0090) at least 30 days before the examination date. If the

applications are not received at least 30 days before the examination date, a postponement

may be necessary. Signed applications certifying that all training has been completed should

be submitted at least 14 days before the examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of

1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of

Management and Budget, approval number 3150-0018, which expires on June 30, 2006. The

public reporting burden for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per

response, including the time for reviewing instructions, gathering and maintaining the data

needed, and completing and reviewing the collection of information. Send comments on any

aspect of this collection of information, including suggestions for reducing the burden, to the

Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission,

Washington, DC 20555-0001, or by Internet electronic mail at BJS1@NRC.GOV; and to the

Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of

Management and Budget, Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection

of information unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its

enclosures will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Thank you for your cooperation in this matter. Mr. David Llewellyn has been advised of the

policies and guidelines referenced in this letter. If you have any questions regarding the NRC's

examination procedures and guidelines, please contact Steven Rose at (404) 562-4609,

(Internet E-mail: SDR2@NRC.GOV), or myself at (404) 562-4638, (Internet E-mail:

MEE@NRC.GOV).

Sincerely,

/RA/

Michael E. Ernstes, Chief

Operator Licensing and

Human Performance Branch

Division of Reactor Safety

Docket Nos. 50-280, 50-281

License Nos. DPR-32, DPR-37

cc: (See page 3)

VEPCO

3

cc contd:

Chris L. Funderburk, Director

Nuclear Licensing and

Operations Support

Virginia Electric & Power Company

Electronic Mail Distribution

Richard H. Blount, II

Site Vice President

Surry Power Station

Virginia Electric & Power Company

Electronic Mail Distribution

Virginia State Corporation Commission

Division of Energy Regulation

P. O. Box 1197

Richmond, VA 23209

Lillian M. Cuoco, Esq.

Senior Counsel

Dominion Resources Services, Inc.

Electronic Mail Distribution

Attorney General

Supreme Court Building

900 East Main Street

Richmond, VA 23219

David T. Llewellyn

Manager of Nuclear Training

Surry Power Station

5570 Hog Island Road

Surry, VA 23883

VEPCO

4

Distribution:

C. Gratton, NRR

C. Evans (Part 72 Only)

L. Slack, RII EICS

RIDSNRRDIPMLIPB

PUBLIC

OFFICE

RII:DRS

RII:DRS

RII:DRP

SIGNATURE

/RA/

/RA/

/RA By LGarner for/

NAME

SRose:pmd

MErnstes

KLandis

DATE

8/28/2003

8/28/2003

8/29/2003

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

PUBLIC DOCUMENT

YES

NO

OFFICIAL RECORD COPY DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML032410147.wpd