Inspection/Activity Plan 09/01/2003 Through 09/30/2004
ML032390310
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 08/26/2003
From:
NRC/RGN-II
To:
Shared Package
ML032390302 List:
References
Download: ML032390310 (1)


Text

Page 1 of 1 Hatch 08/26/2003 10:38:05 Inspection / Activity Plan Report 22 09/01/2003 - 09/30/2004 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB2-HS - HEAT SINK 1 1, 2 IP 7111107B Heat Sink Performance 10/13/2003 10/17/2003 Baseline Inspections EB2-ISI - INSERVICE INSPECTION-U1 1 1 IP 7111108G Inservice Inspection Activities - BWR 02/23/2004 02/27/2004 Baseline Inspections PS-RP - RADIATION PROTECTION-ISFSI 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 06/21/2004 06/23/2004 Baseline Inspections PS-RP - RADIATION PROTECTION 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 07/12/2004 07/16/2004 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 07/12/2004 07/16/2004 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 07/12/2004 07/16/2004 Baseline Inspections 1, 2 IP 7112203 Radiological Environmental Monitoring Program 07/12/2004 07/16/2004 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 07/12/2004 07/16/2004 Baseline Inspections EB2-MODS - MODIFICATIONS/10CFR50.59 3 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 07/19/2004 07/23/2004 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 07/19/2004 07/23/2004 Baseline Inspections OL EP - EP INSPECTION 2 1, 2 IP 7111402 Alert and Notification System Testing 08/02/2004 08/06/2004 Baseline Inspections 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 08/02/2004 08/06/2004 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 08/02/2004 08/06/2004 Baseline Inspections 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 08/02/2004 08/06/2004 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 08/02/2004 08/06/2004 Baseline Inspections OL RQ - REQUAL INSPECTION 2 1, 2 IP 7111111B Licensed Operator Requalification 09/20/2004 09/24/2004 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.