July 2003 Monthly Operating Report for Turkey Point Units 3 & 4
ML032380644
Person / Time
Site: Turkey Point  
(DPR-031, DPR-041)
Issue date: 08/12/2003
From: Jones T
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, L-2003-205
Download: ML032380644 (3)


Text

FPL AU 1 2 23 L-2003-205 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re:

Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthly Operating Report - July 2003 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the July 2003 Operating Data Reports and Summaries of Operating Experience for Turkey Point Units 3 and 4.

Very truly yLrs, Terry {b. fines Vice President Turkey Point Plant LDT Attachments NRC Regulatory Issue Summary 2001-05 waived the requirements that multiple copies of documents be submitted to the NRC.

s X~~~~~~~~~

an FPL Group company

A:

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-25 Turkey Point Unit 3 080412003 Linda Tudor (305) 246-6408 Reporting Period July, 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

____l720 Maximum Dependable Capacity (MWe-Net) 693 Month

4.

4 4-No. of hours reactor was critical 744.0 No. of hours generator was on line (service hours) 744.0 4278.5 l 1

Unit reserve shutdown hours 0

0 1 Net Electrical Energy (MWH) 520187 2900680

128, UNIT SHUTDOWNS No.

Date Type Duration Reason Method of Corrective Actionl Comments F=Forced (hours)

(1)

Shutting S=Scheduled Down (2)

I N/A N/A N/A N/A N/A N/A

/A (1) Reason (2) Method A-Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G -Operational Error (Explain)

H -Other 1 - Manual 2-Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

Summary Of Monthly Operating Experience Unit 3 operated at essentially 100% power for the month of July 2003.

.N DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50t251 Turkey Point Unit 4 08/04/03 Linda Tudor (305) 246-6408 Reporting Period July. 2003 Design Electrical Rating (MWe-Net) 720 Maximum Dependable Capacity (MWe-Net) 693 Month I-4-

No. of hours reactor was critical 744.0 1-No. of hours generator was on line (service hours) 744.0 Unit reserve shutdown hours 0

Net Electrical Energy (MWH)

I 514436 I

.5.

UNIT SHUTDOWNS (1) Reason A -Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D-Regulatory Restriction E - Operator Tralning/lcense Examination F - Administrative G -Operational Error (Explain)

H - Other (2) Method 1 - Manual 2-Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

Summary Of Monthly Operating Experlence Unit 4 operated at essentially 100% power for the month of July 2003.