FENOC Perry Nu RyMewcar Operal Cwpany F
August 13, 2003 PY-CEI/NRR-2729L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C.
20555 ucla~nne~n.,owe.D1an4
_=____________
Docket No. 50-440 License No. NPF-58 Monthly Operating Report Ladies and Gentlemen:
Attached is the July 2003 Monthly Operating Report for Perry Unit 1. Page 1 is the Operating Data Report and page 2 is the Unit Shutdowns Report. This report is submitted in accordance with Technical Specification 5.6.4 and Generic Letter 97-02, "Revised Contents of the Monthly-Operating Report."
If you have questions or require additional information, please contact Ms. Toni Phelps at (440) 280-7660.
Very truly yours, Vernon K. Higaki Manager - Regulatory Affairs Attachment cc: NRC Region Ell Administrator NRC Project Manager NRC Resident Inspector clear Power Plant 10 Center Road PO. Box 97 Perry, Ohio 44081
OPERATING DATA REPORT UNIT:
Perry DATE:
8/7103
- 1.
Docket: 50440
- 2.
Unit Name:
Perry Nuclear Power Plant
- 3.
Reporting Period: July 2003
- 4.
Utility
Contact:
T. Phelps
- 5.
Telephone: 440-280-7660
- 6.
Design Electrical Rating (Net MWe):
1260
- 7.
Maximum Dependable Capacity (Net MWe):
1235
= ;
X ;-~~~This Month; --Ao--
- 8.
Hours Reactor was Critical 744.0 3.804.6 108,708.1
- 9.
Hours Generator On-Line 744.0 3.743.1 106.013A
- 10.
Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 11.
Net Electrical Energy (MWeH) 919.277.0 4.352.488.0 120.927.699.0 Page 1
"C i
II UNIT SHUTDOWNS REPORT MONTH - July 2003
!i DOOKET NO: 50-440 NAME: Peny Nuclear Power Plant DAT : 817/03 TELFPHONE: (440) 280-7660 No.
Date Type Duration Re Method Cause and Corrective to Prevent Recurrence I
Hours 2
3__
SUMMARY
- The Perry Plant ran the entire month of Ju* 2003.
- 1. TYPE:
- 2. REASON:
1 F: Forced A - Equipment Failure (
lain)
S: Scheduled B - Maintenance or Test C - Refueling D - Regulatory E -Operating Training Ucense Examinatlor F - Administrative G - Operational Error (ei lain)
H - Other (explain)
- 3. METHOD:
I - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation 5 - Other Page 2 11 II