ML032270418
| ML032270418 | |
| Person / Time | |
|---|---|
| Site: | Ginna |
| Issue date: | 08/07/2003 |
| From: | Widay J Rochester Gas & Electric Corp |
| To: | Clark R Document Control Desk, NRC/NRR/DLPM/LPD1 |
| References | |
| Download: ML032270418 (3) | |
Text
R z5 An Energy East Company ROCHES1ER GWSAND ELECRIC CORPCOAT10N
- 89 EASTAVENME, ROCHESTEP, N.Y 14649-0001 585 546-2700 wwwrex.com August 7, 2003 US Nuclear Regulatory Commission Document Control Desk Attn:
Robert Clark Project Directorate l-1 Washington, DC 20555
Subject:
Monthly Report for July 2003 Operating Status Information R.E. Ginna Nuclear Power Plant Docket No. 50-244
Dear Mr. Clark:
Pursuant to Ginna Improved Technical Specifications Section 5.6.4, attached is the monthly operating status report for Ginna Station for the month of July 2003.
Very truly yours,
( ph A. Wida Plant Manager xc:
U.S. Nuclear Regulatory Commission Mr. Robert Clark (Mail Stop O-8E9)
Project Directorate 1-1 Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 U.S. NRC Ginna Senior Resident Inspector Attachments
OPERATING DATA REPORT 50-244 August 7, 2003 I COMPLETED BY:
t, I,IA John V. Walden TELEPHONE (585) 771-3588 OPERATING STATUS 1.
2.
3.
4.
Unit Name:
R.E. GINNA NUCLEAR POWER PLANT Reporting Period:
July, 2003 Design Electric Rating (Net MWe):
470 Maximum Dependable Capacity (Net MWe):
480 Notes:
This Month Yr.-to-Date Cumulative*
5.
6.
7.
8.
Number of hours Reactor Was Critical Hours Generator On-line Unit Reserve Shutdown Hours Net Electrical Energy Generated (MWH)
- 744.0 X 744.0 0.0 361547.0 5087.0 5076.1 0.0 2505083.4 244103.9 240935.2 8.5
- 109833992.4
- CUMULATIVE TOTAL COMMENCING NOVEMBER 8, 1969
DOCKET NO: 50-244 UNIT NAME: R.E. GINNA NUCLEAR POWER PLANT DATE: August 7. 2003 COMPLETED BY: John V. Walden TELEPHONE: (585) 771-3588 UNIT SHUTDOWN REPORTING PERIOD:
July 2003 (Month/Year)
NO.
DATE TYPE DURATION REASON(')
METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS)
SHUTTING l____
S: SCHEDULED DOWN(2)
COMMENTS
SUMMARY
- The unit operated at full power for the entire of the month of July. Average power for the month of July was 99.6%.
(1) Reason A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator TralninglUcense Examination F - Administrative G-Operational Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 -Other (Explain)