July 2003 Monthly Operating Report for Seabrook Station
ML032250699
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 08/04/2003
From: St.Pierre G
Florida Power & Light Energy Seabrook
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
03-07, NYN-03067
Download: ML032250699 (3)


Text

FL Energy 1FPL Energy Seabrook Station Seabrook Station P.O. Box 300 Seabrook, NH 03874 (603) 773-7000 August 4, 2003 Docket No. 50-443 NYN-03067 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 Seabrook Station July 2003 Monthly Operating Report Enclosed please find Monthly Operating Report 03-07. This report addresses the operating and shutdown experience relating to Seabrook Station Unit 1 for the month of July, 2003 and is submitted in accordance with the requirements of Seabrook Station Technical Specification 6.8.1.5.

Should you require further information regarding this matter, please contact Mr. Paul V. Gurney, Reactor Engineering Manager, at (603) 773-7776.

Very truly yours, FPL Energy Seabrook, LLC Gene F. St. Pierre Station Director cc:

H. J. Miller, NRC Region I Administrator V. Nerses, NRC Project Manager, Project Directorate 1-2 G.T. Dentel, NRC Senior Resident Inspector

OPERATING DATA REPORT DOCKET NO. 50-443 UNIT Seabrook I DATE August 1,2003 COMPLETED BY P. E. Nardone TELEPHONE (603) 773-7074 OPERATING STATUS

1. Unit Name: Seabrook Station Unit I
2. Reporting Period: JULY 2003
3. Licensed Thermal Power (MWt): 3411.0
4. Design Electrical Rating (Net MWC): 1148.0
5. Maximum Dependable Capacity (Net MWe): 1155.3
6. If Changes Occur in Capacity Ratings (Items Number 3 through 5) Not Applicable Since Last Report, Give Reasons:

This Month Yr-to-Date Cumulative

7. Number of Hours Reactor Was Critical 744.0 5087.0 99721.6
8. Hours Generator On-Line 744.0 5087.0 96879.4
9. Unit Reserve Shutdown Hours 0.0 0.0 0.0
10. Net Electrical Energy Generated (MWH) 862148 5891145 109070049 OPERATING

SUMMARY

The unit operated at 100% power for the entire month. This yielded an availability factor of 100% and a capacity factor of 100.30% based on the MDC value of 1155.3 Net MWe.

I of 2

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-443 UNIT Seabrook I DATE August 1, 2003 COMPLETED BY P. E. Nardone TELEPHONE (603) 773-7074 MONTH: JULY 2003 NO. DATE TYPE DURATION REASON 2 METHOD OF SHUTFING CAUSE / CORRECTIVE ACTIONS (HOURS) DOWN REACTOR COMMENTS No entries for this month.

2 3 F: Forced Reason: Method:

S: Scheduled A - Equipment Failure (Explain) 1- Manual B - Maintenance or Test 2 -Manual Trip C - Refueling 3 - Automatic Trip D - Regulatory Restriction 4 - Continued from previous month E - Operator Training I License Examination 5 -Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other (Explain) 2 of 2